NA-2014-NA1-01, Delegation of Acquisition Executive Responsibilities for Nuclear Materials Safeguards and Security Upgrade Project (Phase II), Security Improvements Project and Device Assembly Facility Argus Upgrade Project
These authorities encompass the project management
aspects relating to the NMSSUP Phase II, the SIP and the DAF Argus, including but not limited to Energy
Systems Acquisition Advisory Board equivalents, Critical Decisions, and Quarterly Project Reviews, except for
those specifically reserved for the Administrator or the Deputy Secretary of Energy. All Acquisition Executive
Authority delegations previously issued for these projects are hereby rescinded.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
O44
Department of Energy
We USS
in 7M Se National Nuclear Security Administration
National Nuclear Security Administration ;
Washington, DC 20585
February 24, 2014
MEMORANDUM FOR EDWARD BRUCE HELD
ACTING ADMINISTRATO
FROM: _J\ MICHAEL K. LEMPKE oN
4 ACTING CHIEF, DEFENSE NUCLEAR SECURITY
SUBJECT: ACTION: Delegation of Authority for Signature
ISSUE: Whether to sign the attached Delegation of Authority for the Acting Chief
and Associate Administrator for Defense Nuclear Security (CDNS),
Michael Lempke.
BACKGROUND: Acquisition Executive responsibility has been delegated to the
permanent or Acting Chief, Defense Nuclear Security, for the Nuclear Materials
Safeguards and Security Upgrade Project (NMSSUP) at Los Alamos National
Laboratory, the Security Improvements Project (SIP) at the Y-12 National
Security Complex and the Device Assembly Facility (DAF) Argus Upgrade project
at the Nevada National Security Site. As the successor Acting CDNS, | must be
delegated authority from the Administrator to function as the Acquisition
Executive for NMSSUP, SIP, and DAF and request these authorities be delegated
as soon as possible, to fulfill my statutory responsibilities.
RECOMMENDATION: Approve the Delegation of Authority for Michael Lempke.
Attachment
cc: David McDarby, NA-71
Donald Stout, NA-70.1
Dale Oliff, NA-71
Robert Raines, NA-APM
Michael Hickman, NA-APM
Steven Erhart, NPO
Eric Thompson, NPO
Michael Duvall, NA-00-LA
Kimberly Davis Lebak, NA-00-LA
Thomas Whitacre, NA-00-LA
Steven Lawrence, NA-00-NV
& Printed with soy ink on recycled paper
DEPARTMENT OF ENERGY
NATIONAL NUCLEAR SECURITY ADMINISTRATION
DELEGATION OF ACQUISITION EXECUTIVE RESONSIBILITIES FOR NUCLEAR MATERIALS
SAFEGUARDS AND SECURITY UPGRADE PROJECT (PHASE II), SECURITY IMPROVEMENTS
PROJECT AND DEVICE ASSEMBLY FACILITY ARGUS UPGRADE PROJECT
DELEGATION. Under the authority vested in me under Section 3212 of the National Nuclear Security
Administration (NNSA) Act (50 U.S.C. 2402) and in accordance with Department of Energy Order 413.3, -
Program and Project Management for the Acquisition of Capital Assets, the Acquisition Executive Authority
for the Nuclear Materials Safeguards and Security Upgrade Project (NMSSUP) (Phase II) construction line
item, for the Security Improvements Project (SIP) construction line item and for the Device Assembly F acility
(DAF) Argus Upgrades Project, is Michael K. Lempke. These authorities encompass the project management
aspects relating to the NVSSUP Phase II, the SIP and the DAF Argus, including but not limited to Energy
Systems Acquisition Advisory Board equivalents, Critical Decisions, and Quarterly Project Reviews, except for
those specifically reserved for the Administrator or the Deputy Secretary of Energy. All Acquisition Executive
Authority delegations previously issued for these projects are hereby rescinded.
1. LIMITATION.
1.1 In exercising the authority delegated herein, a delegate is governed by the applicable rules and
regulations of the Department of Energy and the policies and procedures of the Secretary.
1.2 Nothing in this delegation precludes the Secretary from disapproving any Administration-specific
_ policy or exercising any of the authority delegated by this delegation whenever in the Secretary’s judgment the
exercise of that authority is necessary or appropriate to administer the functions vested in the Secretary.
1.3 The authorities delegated herein shall only be exercised with regard to NNSA employees,
contractors, or activities.
1.4 Any amendments to this delegation shall be in consultation with the NNSA General Counsel.
1.5 Nothing in this Delegation precludes the Administrator from exercising any of the authority
delegated in this Delegation.
2. EFFECTIVE DATE.
This delegation is effective immediately. A “7
Dated this __ day of March, 2014. j /
Edward Bruce Held
Acting Administrator
National Nuclear Security Administration