NA-2014-NA1-02, Delegations of Acquisition Executive Functions
Issue - Whether to delegate Critical Decision and Acquisition Executive functions to the Deputy Administrator for Defense Programs.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Department of Energy MP HF NY ME 2:8)
National Nuclear Security Administration Ut NE Be P'S)
Washington, DC 20585
November 21, 2014
MEMORANDUM FOR FRANK G. KLOTZ
UNDER SECRETARY FOR NUCLEAR SECURITY
ADMINISTRATOR, NNSA
CX Calbia
FROM: Con. sa COOK
DEPUTY ADMINISTRATOR
FOR DEFENSE PROGRAMS
SUBJECT: Delegation of Acquisition Executive Functions
ISSUE: Whether to delegate Critical Decision and Acquisition Executive functions to the
Deputy Administrator for Defense Programs.
BACKGROUND: In Fiscal Year (FY) 2017 Defense Programs plans to request design funds
to initiate two projects in order to replace the following facilities:
1. Lithium Production facility at the Y-12 National Security Complex, and
2. Tritium Reservoir processing facility at the Savannah River Site.
For capital asset projects with Total Project Cost (TPC) between $100 million and $750
million, the Department of Energy Order 413.3B designates critical decision (CD)
approval authority as the Acquisition Executive (AE) to the Under Secretaries with
further delegation allowed. Furthermore, the Order states that the designated AE must
approve all non-major system project CDs, except for CD-0 (Approve Mission Need),
which cannot be delegated below the Program Secretarial Officers, such as the Deputy
Administrators. The TPC for each of these projects is anticipated to be higher than $100
million.
Recent guidance from the Department of Energy Chief Financial Officer is reinforcing the
requirements of Title 50 of the United States Code (USC) Section 2746. USC Section
2746 requires completion of a conceptual design before requesting funds for a
construction project. However, the mission need for a project must be approved before
authorizing the project team to prepare the conceptual design. The mission need
approval for the above two projects is planned for the first quarter of FY 2015.
Developing the conceptual design and preparing budget-quality cost and schedule
estimates will take approximately 12 to 18 months. The conceptual design needs to be
approved no later than December 2015 to enable the request of design funds in
& Printed with soy ink on recycled paper
FY 2017. In order to allow expeditious approval of the mission need and the start of
conceptual design development, | request that critical decision approvals and
acquisition executive functions for these projects be delegated to the Deputy
Administrator for Defense Programs.
Recommendation: Delegate approval of Critical Decisions and Acquisition Executive
functions.
Approved: de. sa] 10] ary Disapproved: Date:
cc: S. Erhart, NPO
D. Dearolph, SRS
A. Beard, NPO
R. Edlund, NPO
D. St. Pierre, NPO
R. Jump, SRFO
C. McFall, SRFO
S. Ho, NA-1.3
M. Thompson, NA-19
S. Jaghoory, NA-193
M. Kosnar, NA-193
D. Gezelle, NA-MB-51
T. Wilson, NA-MB-51
R. Raines, NA-APM
M. Hickman, NA-APM-20
D. Henderson, NA-APM-20
T. Haley, NA-APM-20