NA-2016-001-01, Low Level Waste Facility and Transurance Liquid Waste Facility Projects at the Los Alamos National Laboratory
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
Under Secretary for Nuclear Security i] VW
Administrator, National Nuclear Security Administration
Washington, DC 20585
October 7, 2016
MEMORANDUM FOR PHILIP T. CALBOS
ACTING DEPUTY ADMINISTRATOR
FOR DEFENSE PROGRAMS
\ ) c
FROM: MICHAEL A. THOMPSON j= Po 5
ASSISTANT DEPUTY ADMINISTRATOR
FOR MAJOR MODERNIZATION PROGRAMS
SUBJECT: ACTION: Low Level Waste Facility and Transuranic Liquid Waste Facility
Projects at the Los Alamos National Laboratory
ISSUE: Whether to delegate the Project Management Executive functions for the subject
projects to the Assistant Deputy Administrator for Major Modernization Programs.
BACKGROUND: On December 1, 2010, the National Nuclear Security Administration (NNSA)
Administrator, Mr. Thomas D’Agostino, delegated the Acquisition Executive (now called Project
Management Executive) functions for the Radioactive Liquid Waste Treatment Facility Upgrade
Project to the Deputy Administrator for Defense Programs. Table 1 of the Department of
Energy (DOE) Order 413.3B, “Program and Project Management for the Acquisition of Capital
Assets,” allows further delegation.
At the time that Mr. D’Agostino approved the delegation, the subject projects were two
subprojects under the Congressional Control Line Item No. 07-D-220. However, the Fiscal Year
(FY) 2014 Omnibus Appropriation created a separate line item for the Transuranic Liquid Waste
Facility Project with its own budget and schedule.
Both the Low Level Waste and the Transuranic Liquid Waste Facility Projects are planned to
replace the existing Radioactive Liquid Waste Treatment Facility that is beyond its design and
economic life. Most of the liquid wastes being treated at the existing facility, which will be
treated at the two new facilities when completed, are generated at the Plutonium Facility
(PF)-4.
The Total Project Cost for each project is less than $100 million. The Low Level Waste Facility
Project has an approved baseline with the Total Project Cost of approximately $83 million and is
in construction. The Transuranic Liquid Waste Facility Project is in design, which is expected to
be completed in 1* Quarter of Fiscal Year 2017. A combined Critical Decision 2 (Approve
®
Department of Energy HN iINSS
4
National Nuclear Security Administration
Performance Baseline), and Critical Decision 3 (Approve Start of Construction) is planned for the
Transuranic Liquid Waste Facility Project in 1Q FY 2018. The top range Total Project Cost
approved at the Critical Decision 1 for the Transuranic Liquid Waste Facility Project was $96
million and is expected to be maintained.
Secretary Moniz December 1, 2014, memorandum related to project management
improvements, mandated that the Under Secretaries assign a senior Manager as Project Owner
who identifies the mission need and is responsible for the budget to support the mission need. |
have been designated by the NNSA Administrator as the Project Owner for the two projects.
Delegating the Project Management Executive will strengthen the role of the Project Owner.
RECOMMENDATION: That you approve the delegation of the Project Management Executive
to the Assistant Deputy Administrator for Major Modernization Programs.
APPROVE: SZC CLL Op isaprrove: DATE: 1O/ al Ie
cc: Kimberly Davis-Lebak, NA-LA
Juan Griego, NA-LA
John Evans, NA-19
Shah Jaghoory, NA-19
Summer Jones, NA-19
John Michele, NA-19
Eric Trujillo, NA-APM-1.5
Everett Trollinger, NA-APM 1.5
Robert Raines, NA-APM-1
Cameron Manning, NA-AMP-20
Robin Noyes, PM-20