EXEC-2016-003564
Department of Energy HB AF NG ME
National Nuciear Security Administration WH NaF Bs Red
Washington, DC 20585
July 13, 2016
MEMORANDUM FOR THE DEPUTY SECRETARY
THROUGH: FRANK G. KLOTZ Pkt F/13/dore
UNDER SECRETARY FOR NUCLEAR SECURITY
ADMINISTRATOR, NNSA
FROM: ROBERT B. RAINES we
ASSOCIATE ADMINISTRATOR
FOR ACQUISITION AND PROJECT MANAGEMENT
SUBJECT: ACTION: Chemistry and Metallurgy Research Replacement
Project Preliminary Project Execution Plan and Delegation of
Project Management Executive Authority
ISSUE: Requesting your approval/signature of the Chemistry and Metallurgy Research
Replacement (CMRR) Project Preliminary Project Execution Plan (PPEP) and Delegation
of Project Management Executive (PME) Authority for the CMRR Subprojects.
BACKGROUND: On October 20, 2015, you chaired a meeting of the Energy Systems
Acquisition Advisory Board (ESAAB) to discuss restructuring the CMRR Project, for which
you are the Chief Executive for Project Management. You approved the CMRR Project
restructuring on November 25, 2015, and requested that the PPEP be updated for your
signature to reflect the new project structure. The PPEP is the governing document that
establishes the means to execute, monitor, and control projects that are subject to
Department of Energy (DOE) Order 413.3B Program and Project Management for the
Acquisition of Capital Assets.
With the restructuring of the CMRR Project, each Subproject now has a cost range
below the $750M threshold in DOE Order 413.3B, allowing PME authority to be
delegated to the appropriate Under Secretary. Therefore, your approval of this PPEP
delegates PME authority for the CMRR Subprojects to the Under Secretary for Nuclear
Security. You previously delegated, with the Project Management Risk Committee’s
concurrence, PME authority to the Under Secretary for Nuclear Security to approve CD-
3B, approve long lead procurements and site preparation, for the CMRR Subprojects.
RECOMMENDATION: That you approve and sign the attached PPEP for the CMRR
Project and delegate PME authority for the CMRR Subprojects to the Under Secretary
for Nuclear Security.
APPROVE: # DISAPPROVE: NEEDS DISCUSSION: DATE: vy No