ACD 530.1, Indirect Cost Accounting on Line-Item Construction Projects in the National Nuclear Security Administration (NNSA)
Optimize indirect cost allocation practices for line-item construction projects performed by NNSA Management and Operating (M&O) contractors.
Canceled By:
NAP 530.1, Cost Allocation Optimization on May 26, 2023
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
National Nuclear Security Administration Advance Change Directive
NNSA ACD 530.1
10-06-2021
SUBJECT: INDIRECT COST ACCOUNTING ON LINE-ITEM CONSTRUCTION
PROJECTS IN THE NATIONAL NUCLEAR SECURITY ADMINISTRATION
(NNSA)
PURPOSE: Optimize indirect cost allocation practices for line-item construction projects performed by
NNSA Management and Operating (M&O) contractors.
URGENCY: NNSA’s vital mission priorities necessitate the development of capabilities and
infrastructure that are expanding the portfolio of line-item construction projects. NNSA must evaluate
and adapt cost allocation practices on line-item construction projects with a total project cost (TPC) above
$500 million to ensure effective and efficient execution of critical projects, several of which are currently
in the planning phase.
APPLICABILITY: This ACD applies to all NNSA federal elements. !
BACKGROUND: Currently, NNSA has multiple line-item construction projects over $500M
approaching Critical Decision (CD)-2. These line-item construction projects differ from the M&O’s core
mission program both in type of work performed and M&O resources consumed. Cost accounting
approaches used by M&O contractors when allocating direct and indirect costs to projects may cause, in
some cases, excessive cost allocations and result in inflated TPCs. While Public Law’ governs standards
for proper allocation of indirect costs precluding their total omission from overall project costs, NNSA
and M&Os can more effectively determine proper cost allocation for line-item construction projects and
prevent ad hoc, disproportionate burdens.
REQUIREMENTS:
e After CD-1, NNSA must create an Integrated Federal Review Team (IFRT) for each site where
line-item construction projects with a TPC over $500M are being executed.
o The IFRT will be comprised of representatives from the Office of Management and
Budget (NA-MB), Office of Acquisition and Project Management (NA-APM), and any
applicable Field or Project Office(s).
o The IFRT will evaluate site cost accounting practices for line-item construction projects
with a TPC over $500M and recommend improvements to current practices, where
applicable.
'In accordance with the responsibilities and authorities assigned by Executive Order 12344, codified at 50 U.S.
Code sections 2406 and 2511, and to ensure consistency throughout the joint Navy/DOE Naval Nuclear Propulsion
Program, the Deputy Administrator for Naval Reactors (Director) will implement and oversee requirements and
practices pertaining to this Directive for activities under the Director's cognizance, as deemed appropriate
2 Public Law 100-670 (41 U.S.C. 422) requires certain contractors to comply with Cost Accounting Standards
(CAS). CAS is codified at 48 Code of Federal Regulations, Chapter 99.
Page |lof2
National Nuclear Security Administration Advance Change Directive
NNSA ACD 530.1
10-06-2021
e NA-MB, in partnership with NA-APM and M&Os, will develop and issue NNSA-wide cost
accounting guidance applicable to line-item construction projects with a TPC above $500M.
For questions or comments concerning this ACD, please contact NA-MB at 202-586-0101.
Jill Hruby
Administrator