BOP-001.2, PPBE Programming Process
To institutionalize an annual NNSA Programming process to facilitate analysis and prioritization of program elements and resources and to provide recommendations to the Administrator for the best possible mix of resources attainable within fiscal realities.
Associated DOE Directive:
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
http://hq.na.gov Office of Financial Management
Business Operating Procedure
Approved: 05-08-03
Update: 09-30-04
Update: 02-15-08
Update: 11-08-11
PPBE PROGRAMMING PROCESS
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Financial Management
BOP-001.2
BOP-001.2 1
11-08-11
PPBE PROGRAMMING PROCESS
1. PURPOSE. To institutionalize an annual NNSA Programming process to facilitate
analysis and prioritization of program elements and resources and to provide
recommendations to the Administrator for the best possible mix of resources attainable
within fiscal realities.
2. CANCELLATIONS. None.
3. APPLICABILITY. All NNSA program elements and organizations.
4. REQUIREMENTS. The NNSA will conduct a Headquarters-driven process to facilitate
program development, prioritization and integration, for decision-making by the
Administrator to define the future budget and outyear program profile for all NNSA
elements.
a. The Programming process takes a programmatic, fiscally conscious look at the
current Future-Years Nuclear Security Program (FYNSP) baseline, and provides
the mechanism for each NNSA program element to consider program proposals
resulting from their internal PPBE planning and programming processes for
discussion with the Principal Deputy Administrator and the Program Review
Council (PRC).
b. NNSA Program Reviews will be conducted annually in the fall. The purpose of
the reviews is to provide the Principal Deputy Administrator with the overall
status of each program with a particular emphasis on the underlying assumptions
and issues that will have to be addressed during the upcoming Programming
process. Specific requirements for the reviews will be provided by the Principal
Deputy Administrator.
c. The Programming process begins annually in February with the issuance of
NNSA Program and Fiscal Guidance (NPFG). The NPFG, which ideally
cascades from the DOE Program and Fiscal Guidance, lays out the overriding
program and fiscal guidance from the Administrator to drive the Programming
process. The guidance identifies emerging issues, Office of Management and
Budget (OMB) guidance, and the FYNSP baseline and five year budget profile.
In concert with the Programming Process Instructions, NNSA elements then
conduct their own internal Programming processes.
d. Each NNSA program element conducts internal sessions to prioritize program
requirements to accommodate new priorities and emerging issues, assesses risks,
and develops an updated, integrated Baseline program that supports the
mission. The results of these internal sessions are documented and provided for
discussion with the Principal Deputy Administrator and the PRC. Specific
2 BOP-001.2
11-08-11
instructions for the information needed for the Administrator and the PRC are
available through the NNSA Intranet site at https://hq.na.gov/ppbe/
e. The PRC meets with the Principal Deputy Administrator to discuss the various
program proposals, along with impacts, alternatives and performance.
f. At the end of the Programming process, the Administrator issues the
Administrator’s Final Recommendations (AFR), which document NNSA’s
resource allocation decisions to change the NNSA baseline program in the
FYNSP. The AFR becomes the basis for NNSA’s participation in the
Department’s Strategic Resources Review.
5. RESPONSIBILITIES.
a. The Principal Deputy Administrator, NNSA, is responsible for:
Section 2
(1) Conducting NNSA Program Reviews annually in the fall.
(2) Issuing the NPFG annually in February.
(3) Making final program decisions for the PRC.
(4) Issuing the AFR.
(5) Briefing the Department on the AFR during the Strategic Resources
Review.
b. The Director, Office of Financial Management (NA-MB-30) is responsible for:
(1) Managing the overall PPBE Programming process.
(2) Developing guidance and coordinating the NNSA program reviews.
(3) Developing and coordinating the NPFG.
(4) Coordinating the preparation of Programming process deliverables for the
PRC.
(5) Serving as staff to the Principal Deputy Administrator in analyzing the
Programming process inputs from NNSA elements.
(6) Developing and coordinating the AFR.
https://hq.na.gov/
BOP-001.2 3
11-08-11
(7) Keeping this NNSA Programming process BOP and other process
instructions current and maintaining them on the NNSA intranet at
https://hq.na.gov/ppbe/.
c. NNSA Headquarters Elements (Defense Programs, Defense Nuclear
Nonproliferation, Naval Reactors, Nuclear Counterterrorism Incident Response,
Defense Nuclear Security, Cyber Security, Science and Policy, and Management
and Budget) are responsible for:
1) Being familiar with the requirements of the PPBE Programming process,
including current Programming Process Instructions available on the
NNSA intranet at http://nnsaweb.na.gov.
2) Providing NNSA Program Reviews to the Principal Deputy Administrator.
3) Incorporating the NPFG, NNSA Strategic Planning Guidance, and other
internal multi-year program plans and project plans in generating
proposals for the PRC.
4) Incorporating appropriate Field input into internal Programming processes.
5) Conducting appropriate internal processes to develop an integrated,
updated, fiscally-conscious program baseline, and providing appropriate
information that meets the requirements of the Programming Process
Instructions.
6) As a Program Advocate, participate in the PRC to first justify and defend
the Program’s baseline proposals and work corporately to assist the
Administrator in developing an integrated NNSA program.
d. Other NNSA entities
1) Other NNSA Headquarters elements (those not listed in “C” above) serve
as Corporate Advocates on the PRC. Roles and responsibilities of
Corporate Advocates are outlined in the Programming Process Instructions
available on the NNSA intranet at http://nnsaweb.na.gov.
2) The Albuquerque Complex and Site Offices may participate at various
stages of the Programming process as specified in the annual update of
Programming Process Instructions, the PFG or as requested by the NNSA
Headquarters program elements.
6. REFERENCES. DOE O 130.1, Budget Formulation.
http://nnsaweb.na.gov/
http://nnsaweb.na.gov/
4 BOP-001.2
11-08-11
7. CONTACT. The NNSA, Office of Financial Management, NA-MB-30, 202-586-1087.
\f.__w~r~
KENNETH W. POWERS
Associate Administrator
for Management and Budget