BOP-50.005, Establishment of an Independent Cost Estimate (ICE) Policy
This Cost Estimating Business Operating Policy (BOP) provides for the implementation of policies and responsibilities relating to establishing a policy for independent cost estimating on projects being executed by the NNSA.
Associated DOE Directive:
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NNSA POLICY LETTER
BOP-50.005
Approved: 2-05-09
Establishment of an Independent Cost
Estimate (ICE) Policy
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Project Management and Systems Support
AVAILABLE ONLINE AT: INITIATED BY:
http://www.nnsa.doe.gov Office of Project Management and Systems Support
BOP-50.005 1
2-05-09
ESTABLISHMENT OF AN INDEPENDENT COST ESTIMATE (ICE) POLICY
1. PURPOSE. This Cost Estimating Business Operating Policy (BOP) provides for the
implementation of policies and responsibilities relating to establishing a policy for
independent cost estimating on projects being executed by the NNSA.
2. CANCELLATIONS. None
3. APPLICABILITY.
a. This policy pertains to all capital asset projects as defined in DOE 413.3a
(except General Plant Projects and Capital Equipment Projects) constructed for
NNSA or managed by NNSA personnel on behalf of other government agencies
with an estimated Total Project Cost (TPC) ≥$20 million. These projects
include: Major Items of Equipment (MIE) Line Item (Capital) projects,
Operation Expense funded (Op-Ex) projects, lease/alternate finance projects,
and Work for Others (WFO) projects. NA-10, NA-20, NA-40, NA-50, NA-60,
NA-70 and the service center or their designated Acquisition Executive may
invoke this policy for projects with a TPC < $20 million.
b. This policy does not apply to the Naval Nuclear Propulsion Program and its
contractors, where inconsistent with the authority of the Director, Naval Nuclear
Propulsion Program, pursuant to Executive Order 12344, as set forth in Public
Law (P.L.) 98-525, the Department of Energy (DOE) National Security and
Military Applications of Nuclear energy Authorization Act of 1985, and P.L. 106-
65, the National Nuclear Security Administration Act.
c. The Director, Office of Project Management and Systems Support (NA-54) may
grant waivers to this policy. This responsibility is non-delegable. There are no
other forums of redress.
d. This policy will be applied in conjunction with and will not supersede any
requirements established by DOE Order 413.3A. Execution of project activities,
including review thresholds and responsibilities, will follow the guidance of DOE
O 413.3A.
e. Financial Assistance awards (grants and cooperative agreements), which are
covered under 10 CFR 600, are excluded.
f. This policy does not apply to nuclear weapon research and development
activities, which are managed in accordance with guidance promulgated by
Defense Programs.
BOP-50.005 2
2-05-09
4. REQUIREMENTS.
a. Independent Cost Estimates
1. Attachment 1 enumerates requirements for the timing of development of
ICEs at various stages of line item projects within NNSA.
2. The classes of ICE in Attachment 1 are tailored to the maturity of a project.
The definitions are contained in Attachment 2.
3. The estimate types will be utilized by the ICE team is tailored depending
on the stage of the project, the level of documentation available.
The definition and descriptions are contained in Attachment 2.
b. Cost estimates shall be developed and maintained throughout the life of each
NNSA project. The Federal Project Director is responsible for the official
baseline estimate, developed prior to project acquisition (via contract/delivery
order/task order or subcontract (Management and Operating (M&O) Contract
award) and should ensure that adequate design has been accomplished on which a
credible estimate can be performed, before the project enters the budget process
The official baseline estimate should be developed to an 85% confidence level..
Section 2
c. Each NNSA site or Program Office for projects in foreign locations shall maintain
a cost estimate guide approved by the Site Manager containing the following: 1)
when estimates are required, 2) how they will be conducted, 3) who will perform
and review them, 4) the documentation and maintenance requirements for each
estimate. These guides must meet the minimum criteria shown in Attachment 1.
d. All sequential cost estimates shall be reconciled and kept on file with previous
estimates until the project is completed, thereby ensuring traceability from project
start to completion. The estimate documentation file shall also include the basis
for each estimate (BOE), show how the estimate was performed, and contain a
risk and contingency analysis. Risk and contingency analysis are required for both
capital and operating costs projects. All estimates shall be performed in constant-
year dollars and then escalated into year-of-expenditure (generally fiscal year)
dollars. Both the estimates and the escalation rates used will be kept on file until
the project is completed.
e. Check estimates are recommended for validating project estimates. Check
estimates can be made by the project engineer/manager or by any qualified DOE
or support contractor personnel. It is highly desirable that the check estimate be
made by someone other than those who performed the original estimate. The
check estimate may utilize any of the estimating methods shown in Attachment 3.
BOP-50.005 3
2-05-09
f. Site Offices or Program Office for projects in foreign locations shall record actual
costs while projects are being constructed, and maintain the data in some usable
form, either at the sub-element level or at a higher (macro) level. This data will
be used primarily to support cost estimating on new local projects, but it would be
highly desirable if it were exchanged with other offices, when desired and useful.
g. For the purpose of this BOP, all ICEs shall be developed concurrently and
independently of the prime, Management and Operating (M&O) or Management
and Integrator (M&I) contractor’s estimate development.
h. ICE’s will be developed for each NNSA project with a TPC >$100 million prior
to CD-2. For NNSA projects with a TPC<$100 million ICEs will be developed at
the discretion of the Acquisition Executive (AE), Program Office or the Federal
Project Director.
i. The ICE will be conducted in an open format. Program offices will be invited to
attend all review team sessions.
j. At the conclusion of each Independent Cost Estimate, an out brief will be
conducted with the Site Manager, or his designee, or Program Office for projects
in foreign locations regarding the review results.
k. Funding for ICE's is the responsibility of the program and project office. For line
item projects, funding for ICE's shall be included in the Congressional Budget
Request for each project and the type of funding (i.e. operating, Project
Engineering and Design (PED), or construction) can be determined by the phase
of the project. ICEs shall be identified in the planning schedule for the project.
l. The level of detail of an ICE will be appropriate to the phase of the project being
reviewed. (Per Attachment 1 of this BOP)
m. ICE will be conducted for each NNSA project at successive project phases as
delineated by critical decisions.
o. Guidelines for developing project estimates must be maintained by all NNSA Site
Section 3
Offices or Program Office for projects in foreign locations in accordance with
procedures contained in applicable NNSA and DOE policies. Independent cost
estimates and independent cost analyses must be conducted outside of proponent
organizations in support of Acquisition Executive critical decisions, or in
response to requests or recommendations by the Administrator, Principal Deputy,
Deputy and Associate Administrators, Program Managers, and Federal Project
Directors.
BOP-50.005 4
2-05-09
p. Project estimates and budget requirements shall include identifiable provisions for
price changes due to economic inflation or deflation predicted in accord with
guidance issued by the Office of Cost Analysis (CF-70).
5. RESPONSIBILITIES.
a. NA-50 is assigned the responsibility to serve as the independent assessor for cost
estimating; cost estimating is an essential part of overall project success within the
NNSA. The principal customers of these estimates are the Administrator,
Principal Deputy, Program Managers, Federal Project Directors and Deputy and
Associate Administrators. Cost Estimating is a cornerstone of planning and
executing projects.
b. The Office of Project Management and Systems Support (NA-54) will:
1. Perform all NNSA Independent Cost Estimates and independent cost
analyses for projects between $100 million and $750 million, or as
requested by the Administrator or the Program Deputy Administrator or
Program or Project Office. ICE’s on Projects with a TPC greater than
$750 million will be performed by CF-70.
2. Serve as a focal point for all cost estimating policy and standardization
within NNSA.
3. Improve cost estimating techniques and practices within NNSA.
4. Define policy and establish guidelines for the implementation of
independent cost estimating and analysis in NNSA. Any changes will be
made in consultation with Program Secretarial Officers and Site Office
Managers.
5. Organize, direct, and perform independent cost and schedule estimates,
analyses, and reviews of project estimates, and provide members for
independent cost estimating task groups.
6. Coordinate expertise requirements supporting independent estimates with
the applicable organizations. Conduct reviews, in coordination with the
appropriate Associate Administrator, office director, or NNSA Site Office
Manager, of major variances (greater than 10%) between independent cost
estimates and project office estimates and report the results of such
reviews.
BOP-50.005 5
2-05-09
7. Reconcile all independent cost estimates with program or project office
estimates in order to identify and clarify differences prior to reporting the
completion of the independent cost estimate.
8. Recommend the conduct of an independent cost estimate or independent
cost analysis where major budget issues are involved. Serve as focal point
for all cost estimating policy and standardization within NNSA.
9. Develop, and annually update, the NNSA Cost Analysis Improvement
Plan.
10. Help user organizations to develop their own indices as requested.
Validate indices developed by using organizations, at least once, to assure
that standard guidance is clearly understood and being used.
11. Provide guidance and, if required, training in the development and use of
price change indices.
12. Develop and establish the NNSA definitions of estimate components such
as contingency and escalation, and how they should be estimated and
treated in NNSA cost estimates.
Section 4
13. Develop databases and models to facilitate and improve cost estimating.
14. Establish and maintain an NNSA-wide Work Breakdown Structure (WBS)
code of accounts for use in cost data collection on NNSA construction
projects.
15. Visit each NNSA Site Office at least once every two years to discuss local
cost problems and provide assistance.
16. Recommend training courses for cost estimators.
17. Provide members for independent cost estimating activity with contract
and other pricing/cost expertise.
18. Assist in the development and integration of historical cost data, including
construction cost data.
c. Cognizant Deputy and Associate Administrators (NA-10, NA-20, NA-50, NA-60
and NA-70) shall:
BOP-50.005 6
2-05-09
1. Provide points of contact for independent cost estimating task groups upon
request.
2. Recommend disposition actions to project managers after major variations
between an independent cost estimate and project office estimate have
been identified and analyzed.
3. Approve corrective actions regarding major variances which would entail
changes in or to the project cost estimate.
4. NA-60 shall ensure that cost and schedule data collection and reporting
requirements are embedded in the NNSA contracts.
d. NNSA Sites Offices shall:
1. Develop and maintain local cost guides, per minimum criteria found in
Attachment 3, that outline cost estimating procedures to be used by
operating contractor and NNSA personnel performing and reviewing cost
estimates. Copies of guides are to be forwarded to NA-54 along with the
initial issuance or distribution.
2. Develop local price change indices appropriate for their region. When
local indices are developed, separate price indices for construction,
operating expenses, and capital equipment categories are necessary.
These locally-produced indices are also to be forwarded to NA-54 to add
to the knowledge base available to all NNSA programs.
3. Forward any unusual price change phenomena to CF-70 and NA-54 for
dissemination.
4. Approve project cost estimates developed by the M&O’s or other site
contractors.
5. Collect actual cost and schedule data for use in future estimates.
6. Ensure check estimates are conduct on projects < $100 million. Approve
check estimates.
e. NNSA Federal Project Director
1. The Federal Project Director is responsible for the development of cost
estimates and their maintenance throughout the life of each NNSA project.
BOP-50.005
2-05-09
2. The Federal Project Director is responsible for the official baseline
estimate, developed prior to project acquisition (via contract/delivery
order/task order or subcontract (Management and Operating (M&O)
Contract award) and should ensure that adequate design has been
accomplished on which a credible estimate can be performed, before the
project enters the budget process
6. REFERENCE. DOE Order 413.3A, Program and Project Management for the
Acquisition of Capital Assets, 7-28-2006.
7. CONTACT. The point of contact for this Policy Letter is the Associate Administrator
for Infrastructure and Environment (NA-50) 202-586-7349.
BY ORDER OF THE ADMINISTRATOR:
~ ~- 1'( o~n~
THOMAS P. D'AGO~.Jo
Administrator
ATTACHMENT I REQUIRED INDEPENDENT COST ESTIMATES
ATTACHMENT 2 DEFINITIONS AND GENERAL ROLES
ATTACHMENT 3 CRITERIA FOR LOCAL COST ESTIMATING GUIDES
7
BOP-50.005 8
2-05-09
ATTACHMENT 1 INDEPENDENT COST ESTIMATES (1)
Section 5
ICE’s will be developed for each NNSA project with a TPC >$100 million prior to CD-2. For NNSA
projects with a TPC<$100 million ICEs will be developed at the discretion of the Acquisition Executive
(AE), Program Office or the Federal Project Director."
Timing: Review
purpose Direction Estimate
Class
ICE Type
Prior to
CD-0
Project cost
magnitude
range
A project cost magnitude range should be established based
on project alternatives. This establishes the Acquisition
Authority Level for Critical Decision-0 (CD-0). Normally,
depending on techniques used, there will be little, if any,
distinction between components or categories within the cost
estimate (e.g., direct costs, indirect costs, contingency, or
escalation; labor, materials, equipment, etc.; types of work).
The cost estimate for the Conceptual Design Review (CDR)
phase of the project should be developed to a more definitive
level.
Class 5 Type 1
At CD-
0
Conceptual
Phase
estimate
Cost estimates prepared to support achieving CD-1 will
range from Class 5, Order of Magnitude to Class 3,
Preliminary cost estimates, using several cost estimating
techniques. For alternatives explored, varying levels of
available information should be expected. Ranges should be a
little more refined than those at CD-0, but still established
based on the range of project alternatives. The cost estimate
for the Preliminary Design phase of the project should be
developed to a more definitive level.
Class 4 Type II,
III, IV, V
Prior to
CD-1
Alternative
analysis ICE
(LCCA)
The cost range developed at this point in the project planning
process will represent all viable alternatives considered to
achieve the required performance capability. These estimates
also should include costs for exploring alternative concepts
and the development of solutions and alternatives during the
project definition phase.
Life-cycle cost estimates that are developed early in a
project’s life may not be derived from detailed engineering,
but they must be sufficiently developed to support budget
requests for the remainder of the project definition phase.
They should also include all anticipated resources, using
appropriate estimating techniques that are necessary to
acquire or meet the identified capability.
Class 4 Type II,
III, IV, V
BOP-50.005 9
2-05-09
Timing: Review
purpose Direction Estimate
Class
ICE Type
Preferred
Alternative
and Cost
Range ICE
During the project definition phase, at the conclusion of the
concept exploration process, the alternative selected as the
best solution to a mission need is presented for approval. The
solution presented as a subset of a conceptual design report
must include the TPC range, a schedule range with key
milestones and events, and annual funding profiles. The TPC
range presented must be a risk-adjusted cost estimate that
defines all required resources necessary to successfully
execute the planned work.
Class 3 Type II,
III, IV, V
After
CD-1
Preliminary
Design Phase
Estimate
This is the estimated cost associated with the preliminary
design and should contain activities for final design phase.
This estimate will be the basis for the Federal CD decision
process.
Class 2 Type III,
IV, V
Performance
ICE
Establishes the project’s performance baseline. The cost
estimate shall be risk adjusted and capture the Total Project
Cost (TPC) to acquire the asset. This estimate should be
organized using a work breakdown structure that supports
earned value management reporting requirements and easily
facilitates evaluation of all estimated costs.
Section 6
Class 1 Type III,
IV, V
Prior to
CD-2
Reconciliation
between ICE
and contractor
cost estimate
Reconciliation between the ICE and contractor estimate for
the purpose of validating the BOE. This estimate will be the
basis for the Federal CD decision process.
Class 1 Type III,
IV, V
Prior to
CD-3
Construction
or Execution
Readiness
If TPC > $750 million Class 1 Type III,
IV, V
(1) The estimate type to be utilized by the ICE team is tailored depending on the stage of the project, the level of
documentation available, and the time available
BOP-50.005 10
2-05-09
ATTACHMENT 2 DEFINITIONS
Acquisition Executive – the individual designated by the Secretary of Energy to integrate and
unify the management system for a program portfolio of projects, and implement prescribed
policies and practices. The Acquisition Executive is the approving authority for a project’s
Critical Decisions, per DOE O 413.3A.
Basis of Estimate, or BOE—documentation that describes how an estimate, schedule, or other
plan component was developed, and defines the information used in support of development.
The basis of estimate documents the estimate assumption, exclusions, and criteria used in
producing the estimate and include; the cost estimate purpose and class; WBS, including
deliverables and scope of work; code of accounts; project/program requirements and milestones,
including constraints, special conditions, regulatory drivers, applicable DOE Orders, and
industry standards; description of assumptions and exclusions; backup data, including quantity
takeoffs, calculations, commercial databases; historical data, cost estimating relationships
(CERs), quotes, and other general sources of information; basis of direct costs (e.g., industry
standards and historical information); basis of indirect costs (e.g., rates from a corporate
perspective); basis of escalation; and basis of contingency, which may include or reference a
risk analysis or risk management plan.
Check Estimates - are one way that a field office can infuse quality assurance/quality control
practices into a cost estimate. These estimates should be developed and performed by a third
party who did not participate in the original cost estimate. An "outsider" provides the
opportunity for the estimate to be reviewed by a fresh observer. Check estimators should be able
to identify any weaknesses in estimate documentation or methodology before these weaknesses
have a negative effect on the estimate. For example, if personnel performing the check estimate
cannot follow the existing documentation, chances are that the documentation is not sufficient to
support the estimate in the approval process.
Critical Decision – a formal determination made by the Secretarial Acquisition
Executive/Acquisition Executive at a specific point in a project’s life cycle that allows the
project to proceed to the next phase or Critical Decision. Critical Decision requirements are
specified in DOE O 413.
Class 5, Order of Magnitude Cost Estimates, also known as rough order of magnitude (ROM)
or top-down cost estimates are typically performed in the early stages of a project’s life. These
cost estimates are based on the least amount of available information and may indicate a low
level of confidence or accuracy in the estimate. Techniques used to develop these estimates
include stochastic, most parametric, and professional judgment (parametric, specific analogy,
expert opinion, trend analysis).
BOP-50.005 11
2-05-09
Section 7
Class 4, include a combination of Class 5 and Class 3 cost estimates. The techniques used to
develop estimates in this class vary, with more parametric (parametric, specific analogy, expert
opinion, trend analysis) estimates being the norm.
Class 3, Preliminary, or budgetary, cost estimates contain diverse levels of available and
supporting information, use various techniques, and portray a moderate level of confidence.
Various techniques, including combinations (detailed, unit-cost, or activity-based; parametric;
specific analogy; expert opinion; trend analysis) are used to develop these estimates.
Class 2, Intermediate cost estimates include a combination of Class 3 and Class 1 cost estimates.
The techniques employed here vary, with more definitive (detailed, unit-cost, or activity-based;
expert opinion; learning curve) approaches being utilized.
Class 1, Definitive cost estimates, also known as detailed, detailed unit-cost, or activity-based
cost estimates, are those with the most abundantly available support information using a
definitive technique for development and representing a greater level of confidence. These
techniques include deterministic and most definitive (detailed, unit-cost, or activity-based; expert
opinion; learning curve).
Independent cost estimate (ICE) -a documented, independent detailed, unit-cost, or activity-
based cost estimate that serves as a tool to validate, crosscheck, or analyze cost estimates
developed by project proponents.
Independent Cost Review - An essential project management tool used to analyze and validate
an estimate of project costs by individuals having no direct responsibility for project
performance.
Life-cycle cost - The overall estimated cost for a particular program alternative over the time
period corresponding to the life of the program, including direct and indirect initial costs plus
any periodic or continuing cost of operation and maintenance. The sum total of the direct,
indirect, recurring, nonrecurring, and other costs incurred or estimated to be incurred in the
design, development, production, operation, maintenance, support, and final disposition of a
major system over its anticipated useful life span. Where system or project planning anticipates
the use of existing sites or facilities, restoration, and refurbishment, costs should be included.
Life-cycle cost analysis (LCCA) - assessment of the direct, indirect, recurring, nonrecurring,
and other related costs incurred or estimated to be incurred in the design, development,
production, operation, maintenance, support, and final disposition of a major system over its
anticipated useful life span.
Project – A group of related activities that has a defined starting and end point and undertaken to
create a unique product or service in support of a program.
BOP-50.005 12
2-05-09
Traceability - A life cycle cost and schedule estimate file will be maintained on all projects.
The file will contain all cost and schedule estimates from the beginning to the end of project
construction. Significant variances between subsequent estimates must be explained and kept on
file so that traceability can be maintained throughout the project’s life. Changes in scope,
escalation assumptions, estimating methods, contingency, and schedule shall be explained,
recorded, and tracked from one estimate to the next, and kept on file.
Section 8
Type I - Documentation Review. This type of review is not normally accomplished as an ICE,
nor does it fulfill the requirements necessary to support an Energy System Acquisition Advisory
Board (ESAAB) decision, since it only consists of an assessment of the documentation available
to support the estimate. It is merely an inventory of existing documents, not a review, and
determines that the required support documentation exists and identifies missing data.
Type II - Reasonableness Review. For this review, the ICE team reviews all available project
documentation, receives briefings from the project team, holds discussions with the project team,
completes sufficient analysis to assess the reasonableness of the project assumptions supporting
the cost and schedule estimates, ascertains the validity of those assumptions, assesses the
rationale for the methodology used, and checks the completeness of the estimate. The result is a
report that details findings and recommendations.
Type III - Parametric Estimating Technique. This technique, in addition to incorporating all the
activities needed for a reasonableness review, uses parametric techniques, factors, etc., to
analyze project costs and schedules and is usually accomplished at a summary (WBS) level. The
parametric techniques should be based on accepted historical cost/schedule analyses. At a
minimum, these tools should be based on historical estimates from which models have been
derived, and, where possible, from actual completed projects. An estimate with a minimum of
75 percent of the total project cost (TPC) based on parametric techniques is classified as a
parametric estimate.
Type IV - Sampling Technique. This review also begins with the activities needed for a
reasonableness review, but in addition, it requires the ICE team to identify the key cost drivers.
A “cost driver” is a major estimate element whose sensitivity significantly impacts the TPC.
Detailed independent estimates must be developed, which should include vendor quotes for
major equipment and detailed estimates of other materials, labor, and subcontracts. For the
balance of the project costs, the project estimate may be used (if deemed to be reasonable
through the reasonableness review), or, if appropriate, parametric techniques may be used for
certain portions of the project costs. An estimate that provides a detailed cost for all cost drivers
is classified as a sampling estimate.
Type V - Bottom-up Estimating Technique. This is the most detailed and extensive ICE effort,
and begins with the activities needed for a reasonableness review. In addition, it requires a
detailed bottom up independent estimate for both cost and schedule. This involves quantity take-
offs, vendor quotations, productivity analysis, use of historical information, and any other means
BOP-50.005 13
2-05-09
available to do a thorough and complete estimate of at least 75 percent of the project’s cost. It
may not be possible to do a completely independent estimate on some portions of the PSO
estimate, and for those portions—which should not exceed 25 percent of the total estimate—the
project estimate may be used if it has passed the test of reasonableness. In all cases, a total cost
(both total estimated cost (TEC) and TPC should be developed. It must be recognized that all
estimates will involve a combination of the techniques described in this section, because varying
levels of information will be available. The accuracy of the estimate will be subjectively
determined based on the weighted totality of the information available.
Section 9
BOP-50.005 14
2-05-09
ATTACHMENT 3 CRITERIA FOR LOCAL COST ESTIMATING GUIDES
While it is recognized that local conditions will influence the content of local cost guides to some
degree, these guides must, at minimum, include the following items:
a. Types of Cost Estimates. List and define the seven types of cost estimates.
b. Basis for the Cost Estimate. Establish and document the basis for the estimate. The
basis for the cost estimate must describe the purpose of the project, general design
criteria, stage of design at the time of the estimate, significant features and components,
proposed methods of accomplishment, proposed construction schedule, research and
development requirements, and any other pertinent facts that may impact costs.
c. Planning for the Estimate. Describe the need for planning the approach and selecting
the cost methods that will be used. Determine the type of estimate to be performed and
the level of detail desired. Also, show such items as the basis for estimating quantities of
materials not yet detailed on drawings, and for wage rates, productivity factors, and
installation unit man-hours.
d. Performing the Estimate. List the steps to be followed in performing a cost and
schedule estimate and show the categories of cost that must be included.
e. Cost Codes of Account. The cost codes of account in Chapter 6 of DOE Cost Guide
DOE/MA-0063 Volume 6 should be used for the estimates. If sufficient reasons exist,
local cost codes may be developed and used.
f. Contingency. A contingency analysis shall be required on all construction project
estimates, and the analysis shall become and remain part of the estimate documentation.
This section will also show how to estimate contingency.
g. Inflation (and Economic Escalation). All construction projects will be estimated in
constant-year dollars in the year the estimate is performed. The constant-year cost will
then be spread over the years in which costs will be incurred and each year’s cost will
then be escalated using an appropriate escalation index. The constant-year estimate,
escalated estimate, and indices used will remain on file for future reference.
h. Cost Estimate Reviews. Procedures will be established for reviewing all cost and
schedule estimates including: (1) when reviews will be made; (2) how they will be made;
and (3) who will make them. Cost review procedures will require all cost estimates to be
reviewed by someone other than the estimator. Precaution will be taken to ensure there is
BOP-50.005 15
2-05-09
no conflict of interest when operating contractors (or other non-DOE personnel) are
reviewing estimates.
i. Traceability. A life cycle cost and schedule estimate file will be maintained on all
projects. This file will contain all cost and schedule estimates from the beginning to the
end of project construction. Significant variances between subsequent estimates must be
explained and kept on file so that traceability can be maintained throughout the project’s
life. Changes in scope, escalation assumptions, estimating methods, contingency, and
schedule shall be explained, recorded, and tracked from one estimate to the next, and kept
on file.
j. Documentation. All estimates shall be documented and the documentation file shall be
Section 10
kept current. Documentation shall include: (1) the purpose and basis of the estimate; (2)
a technical description and the scope of the project being estimated; (3) all ground rules,
constraints, and assumptions; (4) a detailed traceable recording of how the estimate was
performed (e.g., quantity takeoffs, price sources, factors, cost estimating relationships,
commercial cost manual, and in-house data base), and who performed it; (5) a
contingency analysis; (6) a schedule; (7) a spread sheet showing funding requirements by
year in both constant-year and escalated dollars; and (8) escalation rates used, and how
they were obtained and applied.
k. Collecting Actual Cost Data. Actual cost data will be collected as the project is being
built for both project control and for cost data banks. Cost estimating guides will
describe how they will be collected, normalized, stored in the data bank, and be available
to cost estimators.
l. Requirements for Review and Approval. The Site Manager will review and approve
the Local Cost Estimating Guide and ensure it is maintained under change control
procedures.