NAP-3, NNSA Environment, Safety and Health Management Process Guidance
This guidance provides instruction for the preparation of NNSA Environment, Safety and Health (ES&H) Five-Year Site Plans. It is intended to ensure that information on the ES&H component of NNSA’s proposed budgets and operating work to be performed at each site is available to NNSA line managers, both in the Field and at Headquarters, in order for them to
be accountable for ES&H performance.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NNSA Policy Letter
NNSA Policy Letter: NAP-3
Date: July 18, 2002
TITLE: NNSA Environment, Safety and Health Management Process Guidance
I. OBJECTIVE: To “grandfather” this existing Guidance into the NNSA Policy Letter System.
This guidance provides instruction for the preparation of NNSA Environment, Safety and
Health (ES&H) Five-Year Site Plans. It is intended to ensure that information on the ES&H
component of NNSA’s proposed budgets and operating work to be performed at each site is
available to NNSA line managers, both in the Field and at Headquarters, in order for them to
be accountable for ES&H performance.
II. APPLICABILITY: The provisions of Policy Letters apply to all of the Administration’s
organizations and elements and to non-NNSA elements funding activities at sites where the
Administration is the landlord, with the exception of Naval Reactors.
III. REQUIREMENTS: See attached Guidance.
IV. RESPONSIBILITIES: See attached Guidance.
V. POINT OF CONTACT FOR ADMINISTRATION POLICY LETTER: Director, Office of
Environment, Safety and Health Operations Support (NA-53), 202-586-8395.
Attachment:
“Guidance Document for National Nuclear Security Administration Environment, Safety & Health
Management Process”
Distribution:
Manager, Albuquerque Operations Office
Manager, Nevada Operations Office
Site Manager, Y-12 Site Office
Assistant Manager for the Livermore Site, Oakland Operations Office
Assistant Manager for National Security, Savannah River Operation Office
Manager, Kirtland Site Office
Manager, Los Alamos Site Office
Manager, Kansas City Site Office
Manager, Amarillo Site Office
cc:
Director, Lawrence Livermore National Laboratory
Director, Los Alamos National Laboratory
President, Sandia National Laboratories
Guidance Document for
National Nuclear Security Administration
Environment, Safety & Health
Management Process
March 2002
Table of Contents
1.0 Purpose....................................................................................................................................................................... 1
2.0 Integrating ES&H Decisions.................................................................................................................................. 1
3.0 Planning Phase.......................................................................................................................................................... 2
3.1 Key NNSA ES&H Elements ............................................................................................................................. 3
3.2 NNSA ES&H Prioritization Guidance............................................................................................................. 3
4.0 Programming Phase................................................................................................................................................. 3
4.1 ES&H Five-Year Site Plans............................................................................................................................... 4
4.1.1 Scope.............................................................................................................................................................. 4
4.1.2 Site Plan Outline and General Contents................................................................................................... 5
4.1.3 Reporting and Deliverables........................................................................................................................ 5
Section 2
5.0 Budgeting Formulation and Justification Phase................................................................................................. 6
5.1 Reporting and Deliverables................................................................................................................................ 7
5.2 Coordination of Budget Changes...................................................................................................................... 8
6.0 Budgeting Execution Phase.................................................................................................................................... 8
6.1 Transition from Budgeting Formulation to Budgeting Execution Phase................................................... 8
6.2 ES&H Work Authorization................................................................................................................................ 9
6.2.1 ES&H Commitments .................................................................................................................................. 9
6.2.2 Reporting and Deliverables...................................................................................................................... 10
6.2.3 Change Control .......................................................................................................................................... 10
7.0 Evaluation Phase.................................................................................................................................................... 10
8.0 Roles and Responsibilities.................................................................................................................................... 11
Appendix A Suggested Format and Contentsfor ES&H Five-Year Site Plan .................................................. 14
Appendix B Related Terminology and Definitions................................................................................................ 22
Appendix C ES&H Compliance Liability Estimate ............................................................................................... 25
Appendix D Functional Areas .................................................................................................................................... 27
1
1.0 Purpose
This guidance will be institutionalized by a new National Nuclear Security Administration
(NNSA) Environment, Safety and Health (ES&H) Management Process policy when it is issued.
It is intended to ensure information on the ES&H component of NNSA's proposed budgets and
operating work to be performed at each site is available to NNSA line managers, both in the
Field and at Headquarters, in order for them to be accountable for ES&H performance.
As a result of requirements in the Department of Energy Acquisition Regulations (DEAR)
Clause 48 CFR 970.5223-1, Integration of Environment, Safety and Health into Work Planning
and Execution, NNSA contractors have developed and implemented Integrated Safety
Management (ISM) systems. ES&H management and resource requirements or issues are
elevated for fiscal or management attention to NNSA federal line management and will be
addressed during the appropriate phases of the NNSA’s Planning, Programming, Budgeting and
Evaluation (PPBE) process. This integration of ES&H within both ISM and PPBE will serve to
strengthen the contractor/federal interface and NNSA federal managers’ ability to satisfy their
line management responsibilities for ES&H oversight.
Section 3
This guidance provides directions for the preparation of NNSA ES&H Five-Year Site Plans.
These ES&H Five-Year Site Plans, as they extend through all phases of the PPBE process, shall
be a key federal “mechanism” of the NNSA ISM system, and are intended to interface with, but
not replace, existing contractor systems developed in support of their own ISM implementation.
2.0 Integrating Environment, Safety and Health Decisions
NNSA’s Line Managers will integrate ES&H activities with other programmatic activities, and
incorporate ES&H decisions at the appropriate steps during the PPBE process. The PPBE
process links long-range planning (what we need to do) with programming (how we accomplish
it), with budget formulation and justification (obtaining resources and applying fiscal
constraints), budget execution (applying resources to accomplish the mission), and evaluation
(verifying the mission has been accomplished and making necessary improvements). Line
managers must consider ES&H throughout all phases of the PPBE process. Details for the
process will be refined as NNSA and DOE become more specific in promulgating the PPBE
process.
A diagram illustrating the key steps of the NNSA’s PPBE process and how ES&H management
and resource decisions align with that process is presented in Figure 1. These elements also
parallel the processes used in the five core functions of ISM.
2
Figure 1. How ES&H aligns with the PPBE Elements.
BENEFITS
• Uses ISMS to enhance the visibility
of ES&H in the performance of work
• Identifies more timely, accurate, and
forward looking ES&H information
for line manager decision-making
• Provides a tool to link the ISM
process with PPBE
• Satisfies multiple reporting
requirements
• Facilitates line ES&H oversight with
the potential to reduce the number of
assessments
BUDGETING -
FORMULATION
• Program Plans, as supported by
ES&H Five-Year Site Plans, are used
as the basis for budget formulation
• Resources are allocated based on
prioritized tasks
• ES&H activities are prioritized using
the ISM verified budget process
• Funded and unfunded ES&H issues
are identified
• Total ES&H budget is identified
PLANNING
• Missions are translated to work per
the NNSA Strategic Plan with
ES&H activities
• Expectations are set and
communicated
• Tasks are identified
• Feedback is utilized from
Corporate ES&H metrics
• Compliance is proactive vs.
reactively applied
PROGRAMMING
Tasks are prioritized and resourced, e.g.,
for Campaigns, DSW, and RTBF to
support the Defense Programs Stockpile
Stewardship Plan
• Five-year, one-year, ES&H
requirements are identified
• Hazards are identified and controls are
developed
• ISM graded approach is used to balance
risk
EVALUATION
• Performance based
metrics and oversight
systems guide ES&H
oversight
• Opportunities for
refining the scope of
work are identified
• Line oversight is
conducted
• Periodic site program
reviews include ES&H
performance
BUDGETING -
EXECUTION
• ES&H compliance liabilities
and regulatory commitments
are established
• ES&H controls are
implemented and work is
authorized
• Work is performed using the
DOE approved ISM system
• Change control process is
established for ES&H
commitments at the site level
per the approved ISM system
• Periodic site program reviews
discuss ES&H commitment
progress
3
3.0 Planning Phase
Section 4
During the planning phase, NNSA will develop a strategic ES&H Five-Year Program Plan that
identifies ES&H short- and long-term programmatic needs and objectives. The program plan
will identify top- level ES&H goals, objectives, and strategies for incorporation into site and
program activities. This plan will also provide an NNSA framework for the development of
corporate- level, quantifiable, ES&H performance metrics thereby satisfying the requirements of
the Government Performance and Results Act of 1993.
3.1 Key NNSA ES&H Elements
The strategies identified in the NNSA Strategic Plan and the Associate Administrator for
Facilities and Operations (AAFO) Program Implementation Plan (PIP) are the basis for
formulating the annual ES&H Five-Year Program Plan that provides additional high- level
objectives for executing ES&H program work. Five ES&H elements that have been endorsed by
NNSA as areas of emphasis are as follows:
• Implement and maintain an effective ISM program
• Ensure appropriate levels of public and employee health and safety
• Ensure appropriate levels of environmental protection/pollution prevention
• Ensure that ES&H operations support accomplishment of programmatic objectives and are
as efficient and cost effective as practicable
• Ensure that appropriate NNSA and Contractor management attention, is focused on ES&H
performance
Current Department of Energy (DOE) ISM performance metrics will be utilized by NNSA
Headquarters to monitor contractor performance. NNSA may provide additional ES&H
performance metrics related to the above five ES&H elements as appropriate.
3.2 NNSA ES&H Prioritization Guidance
Annually, AAFO and Program Offices will provide guidance on the prioritization of ES&H
activities through PIPs. Until the first PIP is issued, refer to existing program guidance in
establishing ES&H priorities.
4.0 Programming Phase
During the programming phase, NNSA will translate information and guidance from the
planning phase into a fiscally defined NNSA ES&H Five-Year Program Plan. The ES&H Five-
Year Site Plans will integrate programmatic mission needs with ES&H requirements. This is
similar to the integration of programmatic mission needs with F&I using the Ten Year
Comprehensive Site Plan (TYCSP) process and the integration of programmatic mission needs
with S&S using Site S&S Plans (SSSP).
4
4.1 Five-Year ES&H Site Plans
NNSA contractors have developed and implemented ISM systems that include key elements of
site ES&H management systems. Development of an ES&H Five-Year Site Plan will serve to
strengthen contractor/NNSA communication and NNSA federal managers’ ability to satisfy their
line management responsibilities for ES&H oversight.
ES&H Five-Year Site Plans are an important mechanism for facilitation of the NNSA ISM
system and are intended to interface with, but not replace, existing contractor systems developed
in support of their own ISM implementation.
4.1.1 Scope
The ES&H Site Plan provides a program plan for each site, on a five year planning horizon, of
how ES&H resources support the successful mission work at the site and for NNSA. The ES&H
Five-Year Site Plans will outline the strategies and performance measures for addressing high-
level ES&H issues and potential impacts. Identification of potential ES&H issues in ES&H
Five-Year Site Plans will assist NNSA in doing forward looking planning to ensure science and
production facilities are ready and available to perform core missions. For major ES&H issues
identified, alternatives, trade-offs and recommendations will be made and coordinated with
appropriate federal officials for concurrence.
Section 5
ES&H costs associated with program activities should be reported, as practicable. It is NNSA’s
expectation that direct mission support for ES&H activities be direct funded through the
sponsoring program (e.g., Campaigns, DSW, etc.) and that facility ES&H costs be direct funded
through RTBF for mission critical facilities, as appropriate. Non-RTBF facility ES&H costs
should be incorporated within the ES&H Five-Year Site Plans as either direct or indirect
accounts.
It is recognized that ISM initiatives have resulted in improved integration of ES&H into mission
work planning and execution. As this desired integration cont inues, it will become more difficult
to separately identify specific ES&H costs and resource requirements, i.e. ES&H becomes more
integrated with the work. As a result, the ES&H Five-Year Site Plan will become more focused
on the planning and deployment of discrete ES&H programmatic resources and less focused on
those resources integrated with mission work. The ES&H Five-Year Site Plan describes the
NNSA ES&H programs and infrastructure elements needed to provide support in the traditional
ES&H functiona l areas.
For the purpose of effective ES&H resource management and planning, both federal managers
and contractors should identify resource allocations, strategic ES&H issues, and potential
impacts. The ES&H Five-Year Site Plan provides a format and mechanism for contractors and
area/field offices to gather and report that information to NNSA.
The following ES&H functional areas have been identified to help categorize ES&H programs
and to assist in the preparation of the ES&H Five-Year Site Plan for a site's overall ES&H
5
program. Eleven Safety & Health functional areas and seven Environmental functional areas
have been defined for ES&H programming and budgeting. Functional area definitions are
provided in the DOE-wide ES&H guidance included with the Field Budget Call and/or in
Appendix D.
Safety and Health Environmental
Emergency Preparedness (EP)
Fire Protection (FP)
Industrial Hygiene (IH)
Industrial Safety (IS)
Occupational Medical Services (MS)
Safety Authorization Basis (AB)
Nuclear Criticality Safety (NC)
Nuclear Safety (NS)
Radiation Program (RP)
Transportation Safety (TS)
Management Oversight & Reporting (MO)
Protection of Air Quality (CA)
Protection of Water Quality (CW)
Control of Toxic Substances (CS)
Environmental Restoration (ER)
Pollution Prevention/Waste Minimization (PP)
Waste Management (WM)
Management Oversight & Reporting (MR)
ES&H Five-Year Site Plans provide the information necessary to determine the ES&H
Compliance Liability estimate for the site (reference Section 6.2.1 and Appendix A).
4.1.2 Site Plan Outline and General Contents
The outline and format in Appendix A of this document meets NNSA’s expectation for the
ES&H Five-Year Site Plan. The basic contents of the ES&H Five-Year ES&H Site Plan will
include a resource summary (annual funding requirements and ES&H compliance liability
estimate information), ES&H compliance activities (both funded and unfunded) in priority order
by fiscal year, open commitments to regulators (both funded and unfunded) in priority order by
fiscal year, unfunded core program maintenance/investment/improvement information in priority
order, and a site section which includes ES&H performance metrics. Other formats are
acceptable with the concurrence of the NNSA Field Element Manager. The NNSA Field
Element and their contractor(s) should establish the level of detail for the communication format.
The scope and contents of each section is described in more detail in Appendix A.
Section 6
4.1.3 Reporting and Deliverables
ES&H Five-Year Site Plans shall be prepared annually to support out-year programming, the
budget request for the next budget year, and to provide ES&H execution information. ES&H
Five-Year Site Plans must be closely linked with the information in the sites’ FY 2004 Budget
Call submission. Any funding profiles shown in ES&H Five-Year Site Plans must track and be
consistent with the same elements shown under the appropriation (e.g., DSW, Campaigns,
RTBF, etc.) section of the FY 2004 Budget Call. The following is the schedule for delivery of
the ES&H Five-Year Site Plans:
• A draft ES&H Five-Year Site Plan is due May 1, 2002 to NNSA Headquarters to initiate
program and budget discussions. This deliverable schedule is intended to ensure draft
ES&H Five-Year Site Plans are consistent with NNSA’s FY 2004 Budget Request.
6
[Note: The draft plan should provide the budgeting formulation, budgeting execution, and
evaluation information described in Sections 5.1, 6.2.2, and 7.1.]
• Final ES&H Five-Year Site Plans are due to NNSA Headquarters 30 days after the end of
FY 2002 or after the FY 2003 funds have been appropriated, whichever is later. [Note:
The final plan should provide the revised budgeting formulation, budgeting execution,
and evaluation information described in Sections 5.1, 6.2.2, and 7.1.]
The scope of the ES&H Five-Year Site Plans is also governed by the following:
• NNSA Landlord Sites. Sites for which NNSA is landlord should address all site ES&H
requirements, regardless of the funding Program Secretarial Officer (PSO) or outside
funding source.
• Other Lead Program Secretarial Officer (LPSO) Landlord Sites. NNSA elements located
at sites for which NNSA is not landlord or where another LPSO’s contractor and budget
are entirely independent of the NNSA contractor, e.g., Savannah River Site or Y-12, only
need to address NNSA specific ES&H requirements.
Each site contractor shall negotiate the development and review schedule of the site plan with the
local NNSA Field Element (i.e., Area/Operations/Field Office) Manager. ES&H Five-Year Site
Plans shall be signed by contractor executive management signifying that the plan represents
management’s commitment to conduct the defined ES&H programs and activities. If the ES&H
Five-Year Site Plan submittal includes compliance activities, the contractor executive
management signature will also attest to the accuracy of the cost and scope of the ES&H
compliance activities.
The manager/contracting officer of the local NNSA Field Element shall review and comment on
the draft and formally approve the contractor’s final ES&H Five-Year Site Plan, signifying
acceptance of the risk associated with the ES&H Five-Year Site Plan on behalf of the NNSA.
Significant issues involving substantial risks that cannot be resolved at the field level should be
formally raised to NNSA Headquarters’ attention. Additionally, any significant issues relating to
the lack of funding and/or policy guidance should also be raised to NNSA Headquarters’
attention.
5.0 Budgeting Formulation and Justification Phase
For FY 2004 budgeting, program requirements from the planning and programming phase (i.e.,
ES&H Five-Year Site Plan) are defined and converted into requests for resources.
The ES&H Five-Year Site Plan will be the basis for NNSA’s ES&H budget year resource
requirements. Contractors should ensure the Budget Year ES&H resource summary information
in the ES&H Five-Year Site Plan is accurate and that both the funded and unfunded ES&H
compliance activities and regulatory commitments are described.
Section 7
7
ES&H requirements considered in prioritization should include laws, regulations, executive
orders, and commitments to regulators and the Defense Nuclear Facility Safety Board (DNFSB).
Some specific information requirements that should be addressed in the FY 2004 Budget include,
but are not limited to:
• Executive Order 13148, Greening the Government through Leadership in Environmental
Management, which requires the implementation of environmental management systems
and environmental compliance audits at all agency sites. The order also imposes specific
pollution prevention goals and requires implementation of return-on- investment
programs. Sites should include activities that meet the requirements of this executive
order, as well as the other Greening the Government Orders as applicable. DOE N 450.4,
Assigning Responsibilities for Executive Order 13148, Greening the Government
Through Leadership in Environmental Management, dated 02-05-01, provides specific
implementing instructions.
• Sites should incorporate activities into their ES&H Five-Year Site Plans that meet the
Departmental pollution prevention goals established by former Secretary of Energy
Richardson in his November 12, 1999 memorandum for the Heads of all Departmental
Elements on Pollution Prevent ion and Energy Efficiency Leadership Goals for Fiscal
Year 2000 and Beyond. In this memorandum he set specific pollution prevention goals
to be achieved by 2005 and 2010. These pollution prevention/energy goals are DOE-
wide goals, not site-specific. On December 6, 2000, the former Deputy Secretary of
Energy issued a memorandum on Commitment to Implement the Secretary’s Pollution
Prevention and Energy Efficiency (P2/E2) Leadership Goals that provides specific site
goals that contribute to the P2/E2 goals for FY 2005.
• Defense nuclear sites that are subject to DNFSB Recommendation 2000-2, Configuration
Management Vital Safety Systems, should identify specific ES&H activities needed to
correct deficiencies in their vital safety systems discovered in Phase I and II operability
assessments and other such assessments. The deliverable under Commitment 8 to the
Departmental Implementation Plan for DNFSB 2000-2 is to provide a summary of
resources allocated within the FY 2003 and FY 2004 budget request to Congress. To
meet this deliverable, the specific ES&H activities identified as necessary to address this
commitment should be included in ES&H Five-Year Site Plans as compliance activities.
Of particular importance are major activities requiring capital funding (General Plant
Project (GPP) or Line Item Project (LIP)).
5.1 Reporting and Deliverables
The schedule for delivery of the ES&H Five-Year Site Plans is noted in Section 4.1.3. Specific
information that should be reported for the Budget Year in the plan is as follows:
• At the draft stage, the FY 2004 ES&H budget information in the resource tables should
reflect the site’s best estimate of the total ES&H funding (core and compliance) for FY
8
2004. The ES&H compliance activities and open commitments to regulators proposed
for the Budget Year (FY 2004) should be described in accordance with the ES&H Five-
Year Site Plan instructions.
• NNSA Headquarters will communicate any changes to budget targets that may occur
Section 8
during the budget deliberations in the PPBE programming and budget formulation phases
to the NNSA Field Element Manager. Accordingly, the final ES&H Five-Year Site Plan
deliverable should be updated to reflect the agreed upon budget targets for FY 2004
ES&H budget information (both core and compliance) in the resource tables. In addition,
the ES&H compliance activities and open commitments to regulators information should
be updated to reflect the actual activities that will be included in the Office of
Management and Budget (OMB) Stage Budget request for the Budget Year (FY 2004).
5.2 Coordination of Budget Changes
Budget targets are likely to change as the budget goes through the different stages from field
submission and Headquarters preparation of the NNSA budget to the OMB budget to the
President’s budget culminating in the Congressional appropriation.
Changes in the Budget Year target level will be communicated from NNSA Headquarters to
NNSA Field Element Managers. If changes in the budget target have a significant impact on
planned ES&H activities, the NNSA contractors should communicate these impacts to the
NNSA Field Element Manager who will inform NNSA Headquarters as appropriate.
6.0 Budgeting Execution Phase
The execution phase is designed to improve the budget and schedules control process, resource
accountability, implementation of ES&H aspects of the integrated NNSA change control
process, timely distribution of program requirements and work authorizations, and clearer federal
and contractor accountability for program requirements. During execution, the resources that
have been allocated will be applied to meet the established ES&H requirements.
This NNSA guidance is the DOE “program and budget and execution guidance” referenced in
DEAR Clause 48 CFR, 970.5223-1 that requires annual reporting of major ES&H performance
objectives, measures, and commitments made for work execution during the fiscal year.
The ES&H Five-Year Site Plan will also be the basis for NNSA’s ES&H execution resource
requirements. Specific information requirements are described in Section 6.2.2.
6.1 Transition from Budgeting Formulation to Budgeting Execution Phase
Implementation of the DEAR Clause 48 CFR, 970.5223-1 requires, in part, that sites meet ES&H
budget needs. The annual ES&H budget information submission identifies significant hazards
associated with planned work and describes the planned ES&H resource requirements necessary
to implement safety controls and satisfy major ES&H requirements and commitments for the
9
Budget Year. These planned activities and resource requirements may change somewhat as they
proceed through the 18 month budget appropriation cycle; however, they eventually become
actual ES&H work commitments to which NNSA will hold contractors accountable.
In transitioning from out-year programming and budgeting to actual work, accountability is
achieved by conducting the actions necessary to meet the five core safety management functions
described in DOE P 450.4 and DOE G 450.4-1. Contractors should annually update their safety
performance objectives and commitments in response to NNSA program and budget execution
guidance and direction. ES&H resources needed to conduct work safely in the execution year
should be identified and allocated to meet ES&H objectives and performance commitments. It is
recognized that while the scope and level of detail may differ, both NNSA Field Element
Managers and NNSA Headquarters require information on these ES&H performance measures,
objectives, and commitments.
Section 9
6.2 ES&H Work Authorization
It is NNSA’s expectation that the NNSA Field Element Manager/Contracting Officer be aware
of the actual ES&H related work, including institutional ES&H funded by indirect funds, being
conducted at their respective sites. The process by which NNSA will authorize ES&H work
identified in ES&H Five-Year Site Plans will be established and managed locally between the
NNSA Field Element Manager/Contracting Officer and the contractor consistent with the site’s
approved ISM system. ES&H activities should become a part of the site’s work authorization
systems (e.g., Work Planning Documents, Work Authorization Documents, Annual Operating
Plan, etc.) and monitored like any other programmatic work.
It is NNSA’s expectation that progress in performing ES&H work shall be communicated from
the contractor to NNSA. In particular, progress in meeting ES&H work commitments should be
discussed during routinely scheduled (e.g., quarterly) program reviews (e.g., RTBF, Campaigns,
DSW, etc.).
6.2.1 ES&H Commitments
ES&H commitments should be established annually between NNSA Field Element Managers/
Contracting Officers and NNSA sites in accordance with the DEAR Clause 48 CFR, 970.5223-1,
and the site’s approved ISM System Description (ISMSD). For the execution year(s), the ES&H
Five-Year Site Plans should provide information on those ES&H compliance activities and
commitments to regulators, with any applicable metrics and milestones that were agreed upon as
ES&H commitments. Site ISM/business systems should provide the ability to track actual
allocation of ES&H resources against planned commitments and should enable NNSA to
monitor and hold contractors accountable for ES&H commitments, as it does programmatic
commitments.
The responsibility for monitoring contractor ES&H performance in meeting commitments rests
with the NNSA Field Element Manager/Contracting Officers for their respective site(s). As part
10
of the ES&H performance evaluation process, ES&H commitments will be tracked at the NNSA
Field Element level and monitored via specific milestones and/or performance measures.
6.2.2 Reporting and Deliverables
The schedule for delivery of the ES&H Five-Year Site Plans is noted in Section 4.1.3. Specific
information that should be reported for Budgeting Execution in the plan is as follows:
• At the draft stage, the ES&H budgeting execution information in the resource tables
should reflect the site’s current plan for total ES&H funding (core and compliance) for
FY 2002, and the site’s best estimate of the total ES&H funding for FY 2003. The plan
should reflect the actual ES&H Compliance Activities and Open Commitments to
regulators being conducted in FY 2002 and those currently planned for FY 2003.
• In the final ES&H Five-Year Site Plan deliverable, the ES&H budgeting execution
information in the resource tables should reflect the site’s best estimate for actual total
ES&H funding (core and compliance) expended in FY 2002 and the site’s approved plan
for total ES&H funding in FY 2003. The plan should be updated to reflect status of the
actual ES&H Compliance Activities and Open Commitments to regulators that were
conducted in FY 2002 and those included in the approved work plans for FY 2003.
6.2.3 Change Control
Section 10
The contractor will manage changes to ES&H work priorities and commitments in accordance
with the site’s approved ISMSD. The NNSA Field Element Manager/ Contracting Officer
should be advised of significant changes to ES&H work per the ISMSD. However, major
changes to baselines that breach established cost or schedule agreements will normally be
approved by the NNSA Field Element Manager/Contracting Officer and will be reported to
NNSA Headquarters. Using a tailored approach, Headquarters and the Field will agree to a set
of minimum thresholds prior to the start of the current year.
Each NNSA Area/Operations/Field Office is expected to have/implement a change control
mechanism for ES&H work.
7.0 Evaluation Phase
The objective of the evaluation phase is to provide management with timely and accurate
information that will be used to evaluate ES&H progress and performance and to identify
significant cost and schedule variances from NNSA commitments.
ES&H Performance Measurement
ES&H metrics should be established annually between NNSA Field Element Managers/
Contracting Officers and NNSA sites in accordance with the DEAR Clause 48 CFR, 970.5223-1,
and the site’s approved ISMSD. It is NNSA’s expectation that in establishing these annual
metrics, NNSA Field Element Managers/Contracting Officers will utilize the Conditional
11
Payment of Fee, Profit, and Incentives Clause (48 CFR, 970.5204-86) as appropriate to enhance
contractor ES&H performance.
The annual ES&H performance metrics agreed to by the contractor and NNSA Field Element per
the ISMSD should be listed in the Site Section of the ES&H Five-Year Site Plan.
The current DOE ISM Performance metrics will be utilized by NNSA Headquarters to monitor
contractor performance. NNSA may provide additional ES&H performance metrics related to
the five ES&H elements described in Section 3.1, as appropriate. These corporate metrics may
differ from those utilized to monitor the contractor’s contractual performance for fee
determinations as part of ISM.
8.0 Roles and Responsibilities
Site Contractor
NNSA contractors should conduct ES&H planning, programming, budgeting, execution and
evaluation in accordance with negotiated contracts and the site-approved ISMSD. As a means of
communicating ES&H planning, resource requirements and execution to NNSA line
management, the contractor shall prepare an ES&H Five-Year Site Plan as specified by this
guidance. It is recognized that utilization of this information out of existing contractor business
systems that have been validated to meet the requirements for implementation of ISM.
Contractor executive management (e.g., laboratory director, plant manager, etc.) shall review the
accuracy and validity of the ES&H resource requirements identified in the site’s ES&H
submissions required by this guidance and approve the draft and final submissions. The ES&H
Five-Year Site Plan should represent the best estimate of a site’s current overall ES&H posture
and path forward.
NNSA Field Element
Each NNSA Field Element is responsible for collecting the ES&H Five-Year Site Plans from
each of its operating organizations and forwarding to NNSA Headquarters. In addition, the
NNSA Field Element Manager/Contracting Officer is responsible for monitoring and approving
ES&H work during the execution phase. Using a tailored approach, Headquarters and the Field
will agree to a set of minimum change control thresholds prior to the start of the current year.
Section 11
Each NNSA Field Element should determine its own ES&H resource requirements necessary to
conduct its ES&H oversight functions under DOE P 450.5. These requirements may include
both federal employees and support services costs used to provide ES&H support. The Federal
Full-Time Equivalents (FTEs) for ES&H should be determined. The format for this reporting
requirement is not prescribed, however, costs should be related to the individual ES&H
functional areas described in the DOE-wide ES&H guidance included with the Field Budget Call
and Appendix D where practicable. This should include FTEs for facility representatives,
environmental engineers, and other ES&H related subject matter experts (SMEs).
12
The NNSA Field Element should review ES&H Five-Year Site Plans for quality and
completeness of the ES&H information and to ensure the information supports NNSA's strategic
goals. It is expected the NNSA Field Element will review the ES&H compliance activities and
commitments to regulators. The NNSA Field Element should review the ES&H priorities
established by the contractors in their ES&H Five-Year Site Plan and the funding decisions that
result from those priorities. They should assure that all significant ES&H risks are adequately
addressed or that adequate compensatory actions are in place until more permanent solutions can
be funded. The NNSA Field Element is responsible for assuring that the ES&H information is
consistent with Departmental and NNSA guidance.
The financial management and budget offices in the NNSA Field Element should ensure that the
funding status and cost information is consistent with the financial information provided in the
primary budget materials (i.e., field work proposals, project data sheets, etc.) that comprise the
field submission. In particular, the FY 2002 funded ES&H activity costs should be reviewed to
ensure consistency with ES&H commitments and the current year appropriations/ expenditures.
The FY 2003 direct funded activity costs should be consistent with the information in the
Congressional Request Budget (or the most up-to-date information available). The FY 2004
direct funded activitie s and costs should be consistent with the operating organization's budget
submission.
The responsible NNSA Field Element Manager shall approve the ES&H Five-Year Site Plan(s)
submitted by the contractor(s). This signature signifies acceptance by the NNSA of the risks
assumed by the contractor(s) on behalf of the NNSA, agreement with the relative funding
priorities, acceptance of the related ES&H deliverables and performance measures, and
satisfactory completion of the financial management review as described above.
The ES&H Five-Year Site Plans and NNSA Field Element resource requirements should be sent
to NNSA Headquarters and to the DOE Chief Financial Officer (CFO). If another PSO is direct
funding programs that require direct ES&H support funding, provide that PSO with a copy of the
relevant ES&H Five-Year Site Plan information.
NNSA Headquarters
NNSA is responsible for collecting the ES&H Five-Year Site Plans from each NNSA Field
Element. Using a tailored approach, Headquarters and the Field will agree to a set of minimum
change control thresholds prior to the start of the current year.
NNSA Headquarters should determine its own ES&H resource requirements necessary to
conduct its ES&H oversight functions under DOE P 450.5. These requirements may include
both federal employees and support services costs used to provide ES&H support. The number
of federal FTEs for ES&H should be determined.
Section 12
After the draft ES&H Five-Year Site Plans have been received at NNSA Headquarters, each
NNSA program manager with responsibility for direct funding of ES&H activities will be
provided the information, i.e., those ES&H compliance activities or commitments to non-
13
DOE/NNSA regulators, appropriate to their program management responsibilities. These
managers will review the ES&H activities from each site and the relative priorities established by
the Field. They should ensure that program related risks are being prudently and appropriately
managed. In addition, ES&H SMEs in AAFO will review the ES&H funding totals and ES&H
compliance activities and commitments, particularly indirect funded Institutional ES&H
requirements. If necessary, the program manager/AAFO can adjust the relative priorities of
activities to reflect the NNSA current perspective and strategic initiatives.
As part of the NNSA Headquarters programming phase, AAFO, the responsible program, and
NNSA financial managers, will confirm that the "Target" (i.e., funded) resources provided by the
Field are indeed addressed within the current budget targets provided by the CFO. They will
review those compliance activities and commitments identified as "unfunded", their associated
risks, any interim compensatory measures in place that ensure all important ES&H issues have
been adequately addressed, and engage the Field where appropriate. Finally, NNSA will present
and defend the ES&H program to the Secretary and other budget process stakeholders.
The NNSA budget and program managers may revise the ES&H priorities for the Budget Year
to reflect decisions made during the programming phase decision-making process. These
revisions, if any, will be made in consultation with the affected NNSA Field Element Manager
and, when appropriate, communicated to the contractor for use in updating the final ES&H Five-
Year Site Plan.
After completing the programming phase, the Field will submit the final ES&H Five-Year Site
Plans. NNSA will formulate its budget and provide the CFO a consolidated and/or updated
submission of ES&H resource requirements from the ES&H Five-Year Site Plans and federal
ES&H resource requirements that reflect current ES&H budget information.
In addition, AAFO and Program Managers will participate in the annual NNSA Contractor
Performance Evaluation Process as follows: provide performance objectives for transmittal to
the Field in the April-May time period, review and comment on the Field Offices’ performance
evaluation plans/laboratory appraisal plans, monitor performance against the plans during the
execution year, provide input to the Field Offices on contractor performance against the plans,
and review and comment on the Field Offices’ annual contractor performance evaluation reports.
14
Appendix A
Suggested Format and Contents for
ES&H Five-Year Site Plan
15
(Title Page)
Environment, Safety, and Health
Five-Year Site Plan
for
Budget Year FY 200X
(Identify Site)
(Date of Plan)
16
Section 1:
Resource Summary ($K) Execution Budgeting Programming
DIRECT FUNDING Prior Yr Current Yr Budget Yr BY+1 BY+2 BY+3 BY+4
Safety and Health (General)
Safety Authorization Basis
Emergency Preparedness
Fire Protection
Industrial Hygiene
Industrial Safety
Safety and Health
Management and Oversight
Occupational
Medical Services
Nuclear Criticality Safety
Nuclear Safety
Radiation Protection
Transportation Safety
Environmental (General)
Protection of Air Quality
Section 13
Control of Toxic
Substances
Protection of Water
Quality
Environmental
Restoration
Environmental
Management, Oversight
and Reporting
Pollution Prevention and
Waste Minimization
Waste Management
Total
Resource Summary ($K) Execution Budgeting Programming
INDIRECT FUNDING Prior Yr Current Yr Budget Yr BY+1 BY+2 BY+3 BY+4
Safety and Health (General)
Safety Authorization Basis
Emergency Preparedness
Fire Protection
Industrial Hygiene
Industrial Safety
Safety and Health
Management and Oversight
Occupational
Medical Services
Nuclear Criticality Safety
Nuclear Safety
Radiation Protection
Transportation Safety
Environmental (General)
Protection of Air Quality
Control of Toxic
Substances
Protection of Water
Quality
17
Environmental
Restoration
Environmental
Management, Oversight
and Reporting
Pollution Prevention and
Waste Minimization
Waste Management
Total
Resource Summary (FTEs)
Prior Yr Current Yr Budget Yr BY+1 BY+2 BY+3 BY+4
Environment, Safety &
Health
ES&H Compliance Liability Estimate Table
CY SCY to CY+6
Funded Operating Expense + Capital Equipment
Operating Expense 0 0
Capital Equipment 0 0
Total 0 0
Funded General Plant + Line Item Projects
General Plant Projects 0 0
Line Item (Construction) 0 0
Total 0 0
All Unfunded Compliance
Operating Expense 0 0
Capital Equipment 0 0
General Plant Projects 0 0
Line Item (Construction) 0 0
Total 0 0
Grand Total 0 0
Reconciliation
Beginning Balance as of FY 2002 (from the FY 2003 plan) 0
Less FY 2002 costs incurred (from the FY 2003 plan) 0
Changes due to items no longer compliance 0
Changes due to a change in scope 0
Other items (new compliance activities) 0
ES&H liability – Ending balance 0
18
Section 2:
ES&H Compliance Activities (by Fiscal Year in Priority Order, Funded and Unfunded)
• Description
• Source of Require ment
• Potential Impact of Non-Compliance
• Cost and Schedule to Correct
• DOE/NNSA Funding Source (e.g. B&R Category or PSO)
(These items should also be reflected in the ES&H Compliance Liability Table above)
Section 3:
Open Commitments Made to Regulators (by Fiscal Year in Priority Order, Funded and Unfunded)
• Description
• Regulatory Agency
• Committed Completion Date
• Status
• Potential Impact if Not Met
Section 4:
Unfunded Core Program Maintenance/Investment/Improvement (in Relative Priority Order)
• Description
• Potential Impact if Not Funded
• Cost and Time to Resolve
Section 5:
Site Section
• (See the Content Guidance Below for Examples)
• Contractual ES&H Performance Metrics
Site Declaration:
ES&H Five-Year Site Plans shall include a signature of an appropriate senior manager attesting to the
accuracy of the cost (i.e., budget quality) and scope of the ES&H data. Such a statement might be:
"Management has reviewed the ES&H activities provided in this ES&H Five-Year Site. The compliance
activities represent our best estimate of the scope and cost of activities needed to maintain and bring the
facility into compliance with applicable laws, regulations, executive orders, and DOE order requirements.
No significant unfunded ES&H vulnerabilities are known except those identified in this Plan."
_____________________________ _____________
Signature Line for Contractor Mgt. Date
Title
_____________________________ _____________
Concurrence Line for Area Office Mgt. Date
19
General Guidance for Content of ES&H Five-Year Site Plan Sections:
Section 14
Section 1:
Resource Summary Tables ($K)
• Include discrete ES&H program infrastructure activities; both compliance and core.
• Do not include those ES&H activities largely integrated into mission work and budgeted for as a part of
that program/project that cannot easily be categorized as ES&H.
• Include ES&H activities performed to support mission work if budgeted for as part of the site's
traditional ES&H program.
• Include activities within the list of ES&H functional areas contained in this guidance document.
• Report budget amount as thousands of dollars ($K).
Complete tables for both direct funded and indirect funded ES&H by functional area. If the identified
expense can not be uniquely identified by functional area, list as Safety and Health (general) and/or
Environmental (general). [Note: The Direct Funded ES&H Resource Table should include the combined
funding from all sources, i.e., NNSA, the Office of Environmental Management (EM), Other PSOs, Work for
Others.]
Resource Summary Table (FTEs)
• Report total ES&H FTE’s estimated by fiscal year reflected by the activities in the above Resource
Summary Table ($K).
ES&H Compliance Liability Estimate Table
• See Appendix B for further guidance.
Section 2:
ES&H Compliance Activities
The intent of this section is to identify to NNSA Area/Field/Headquarters and site contractor management
known conditions of non-compliance that exist with current or anticipated applicable laws, regulations,
orders, notices, executive orders, or other contractual obligations. Further, the intent is to identify those
conditions that have potential for significant impact if not corrected in a timely manner and will result in need
for additional resources or a diversion of resources from other activities. (For example: a new DOE/NNSA
directive has been or is soon to be issued will require additional resources to implement and those resources
are unavailable or will be diverted from other core/compliance activities.)
This section should include both Funded ES&H Compliance Activities (those activities that are currently
being addressed or will be addressed within future budget targets) and Unfunded ES&H Compliance
Activities (known non-compliances that cannot be accomplished within current or future budget targets).
Activities should be listed by the fiscal year in which they are being addressed (or when they will be
required).
The information submitted in this section could be a list or table. For each entry provide the following:
• Description - Short narrative description of the compliance issue.
• Source of Requirement - Identify regulatory agency and cite regulatory reference.
• Potential Impact of Non-Compliance - describe realistic potential impacts of continued non-
compliance. Consider impacts to worker safety, environmental protection, mission work, public
perception, and potential fines.
• Cost and Time to Correct - Describe the cost and time necessary to correct deficiency(ies) and come
into compliant state. Most compliance activities are considered project-like with specific start and
end states and associated costs.
• Source of Funding - Identify the B&R category and/or DOE/NNSA PSO responsible for funding, i.e.
the PSO which should be made aware of the unfunded condition.
• Cost estimates for funded and unfunded ES&H compliance issues should also be entered in the
ES&H Compliance Liability Estimate Table in Section 1, (reference Appendix C for additional
guidance).
Section 15
If multiple entries are submitted in this section, they should be prioritized by risk and/or impact from highest
to lowest.
20
Section 3:
Open Commitments Made to Regulators
The intent of this section is to identify to NNSA Area/Field/Headquarters and site contractor management
commitments made to non-NNSA regulators that need to be brought to their attention and tracked to
completion. (For example: commitments made to a state or local environmental regulator for additional site
environmental monitoring.)
This section should include both Funded ES&H Commitments (those activities that are currently being
addressed, or will be addressed within future budget targets) and Unfunded ES&H Commitments (known
regulatory requirements that cannot be accomplished within current or future budget targets). Activities
should be listed in by the fiscal year in which they are being addressed (or when they will be required).
The information submitted in this section could be a list or table. For each entry provide the following:
• Description - Short narrative description of the compliance issue.
• Regulatory Agency - Identify the regulatory agency to which the commitment has been made.
• Committed Completion Date - Indicate completion date negotiated with the regulator and any
significant intermediate milestones.
• Status - Short description of current status. In particular, describe any issues or barriers that may
prevent meeting the commitment.
• Potential Impact if Not Met - Describe realistic potential impacts of not meeting the commitment.
Consider impacts to worker safety, environmental protection, mission work, public perception, and
potential fines.
If multiple entries are submitted in this section they should be prioritized by risk and/or impact from highest
to lowest.
There is no need to duplicate entries reported in Section 2.
Section 4:
Unfunded Core Program Maintenance/Investment/Improvement
The intent of this section is to identify to NNSA Area/Field/Headquarters and site contractor management
activities/investments needed to maintain an adequate core ES&H program that are currently unfunded or for
which resources are unavailable. (For example: replacement of aging industrial hygiene instrumentation,
addition of new technology equipment, upgrades for environmental monitoring stations, etc.)
The information submitted in this section could be a list or table. For each entry provide the following:
• Description - A short narrative description of the issue including the anticipated improvement.
• Potential Impact if Not Funded - Describe realistic potential impacts of not resolving. Consider
impacts to worker safety, environmental protection, mission work, public perception, and potential
fines. Consider short and long term impacts.
• Cost and Plan to Resolve - Describe the dollar amount and options being considered to resolve. If
this is an investment issue describe estimated payback period on investment.
If multiple entries are submitted in this section they should be prioritized by risk and/or impact from highest
to lowest.
Section 5:
Site Section
The annual ES&H performance metrics agreed to by the contractor and NNSA Field Element
Manager/Contracting Officer per the ISMSD should be listed in this section. In addition, this section is
available for the contractor site to identify to the NNSA Field Element/Headquarter and site contractor
management other items of significance.
Examples:
Section 16
• Describe prior year accomplishments and successes.
• Identify ES&H awards or site certifications received since prior year ES&H Five-Year Site Plan.
• Describe resolution of unfunded items and/or regulatory commitments (Sections 2, 3, 4) from prior
year ES&H Five-Year Site Plans.
21
• Describe site's prioritization and/or change control processes.
• Provide general five-year outlook, planning assumptions, issues looming on the horizon but not yet
significant enough to include in Sections 2, 3, 4.
• Provide general comments from site.
22
Appendix B
Related Terminology and Definitions
Compliance activities – Additional corrective actions, activities, or programs over and
above the current core ES&H programs, that are required to improve the facility's state of
compliance and move the facility toward full compliance or conformance with all
applicable ES&H laws, regulations, agreements, executive orders, and DOE orders. After
compliance is achieved, any continuing activities and resources required to maintain
compliance should be considered as core programs. Generally, compliance activities will
be of shorter duration than core activities and have a discrete beginning and end point.
Compliance activities would include activities such as improvements to RTBF facilities to
correct safety deficiencies, work to meet DNFSB recommendation commitments, etc.
Core activities – Currently performed ES&H activities that are considered necessary by site
management to maintain current levels of ES&H compliance or to prevent increases in the
current levels of ES&H risks. Core activities have the characteristic that if they were not
performed, either (1) the level of compliance of the facility would be lower than the current
level, or (2) the level of risk posed by facility operation would be greater than the current
level. Generally, core activities will be continual site-wide activities and programs needed
to do work safely, such as a radiological protection program, that are included in a site’s
ISM systems. Core activities would be considered the normal ES&H support necessary to
conduct Campaigns and DSW and maintain surveillance and maintenance of RTBF funded
facilities, as well as the normal institutional ES&H work.
Budget Year (BY) - This guidance uses the standard CFO nomenclature for budget years as
used in the UNICALL and as defined in the Budget Formulation Handbook As such,
Budget Year is the fiscal year for which the budget is being considered, i.e. FY 2004.
Commitment - An agreement between NNSA Field Element Manager/Contracting Officer
and contractor management to accomplish certain ES&H work activities or meet certain
conditions, as described in a site’s annual update to its ISMSD.
Current Year (CY) or (BY-1) - This guidance uses the standard CFO nomenclature for
budget years as used in the UNICALL and as defined in the Budget Formulation
Handbook. As such, Current Year is the fiscal year immediately preceding the budget year.
It is the fiscal year of the budget currently being considered in Congress, i.e. FY 2003.
Direct Costs/Funding - Any costs that can be specifically identified with a particular cost
objective that are directly related to and are being incurred principally for the benefit of the
program receiving the charges. Costs that can be directly charged to a specific NNSA
appropriation or other PSO appropriation: specific Campaigns, DSW, RTBF, etc.
Section 17
Environment, Safety and Health (ES&H) Activities – Work conducted whose primary
intent is to protect the health and safety of the public, workers, and the environment.
Indirect Costs Funding – A cost incurred by an organization for common objectives that
cannot be identified specifically with a particular project or activity, (also referred to as
allocable funding).
23
Integrated Safety Management (ISM) – A formal, organized process for planning
(including programming and budgeting), performing (executing), assessing and improving
the safe conduct of work established in response to DNFSB Recommendation 95-2 and
primarily implemented via DOE P 450.4, Safety Management System Policy, and DEAR
48 CFR, 970.5223-1. Within ISM, the term safety means “environment, safety and health”.
ISM is structured around five core functions: define work, identify hazards, develop
controls, perform work, and feedback and continuous improvement; and seven guiding
principles (line manager responsibility for ES&H, clear ES&H roles and responsibilities,
competence commensurate with responsibilities, balanced priorities, identification of
ES&H standards and requirements, hazard controls tailored to work being performed, and
operations authorization).
Out-year (BY+1 through BY+2) – This guidance uses the standard CFO nomenclature for
budget years as used in the UNICALL and as defined in the Budget Formulation
Handbook. As such, an out-year is any fiscal year or years beyond the budget year for
which projections are made, i.e. FY 2005 through FY 2006.
Planning, Programming, Budgeting, and Evaluation (PPBE) Process – The formal process
by which NNSA conducts long-range planning, develops programming requirements for
resources in the short-term planning period (five-years), develops its budget for direct
mission and mission support activities, accomplishes the mission and mission support
activities once funding has been appropriated by Congress, and evaluates the effectiveness
of the activities in meeting the mission goals.
Program Execution Guidance – Guidance that is developed jointly by DOE/NNSA
Headquarters and NNSA Area/Operations/Field Offices and issued to contractors that
provides programmatic assumptions, expected outcomes, milestones, performance
measures, financial controls and reporting requirements, to be used in developing,
implementing, and monitoring fiscal year operations at a site.
Prior Year (PY) or (BY-2) – This guidance uses the standard CFO nomenclature for budget
years as used in the UNICALL and as defined in the Budget Formulation Handbook. As
such, Prior Year is the fiscal year immediately preceding the current year and two fiscal
years preceding the budget year. It is the fiscal year in which the budget is being executed,
i.e. FY 2002.
Significant Risks – Those conditions which have been identified in activities considered
necessary to prevent accidents and manage "immediate" risks to the public, site workers, or
the environment; or high interest activities needed to meet commitments to regulatory
bodies such as DNFSB recommendations accepted by DOE, commitments with regulators,
compliance agreements, etc.
Significant Vulnerabilities – ES&H vulnerabilities identified during Departmental or local
assessments (such as the Plutonium Working Group Report, Highly Enriched Uranium
Working Group Report, Oversight Assessments, etc.) or by external groups (such as the
DNFSB) which have been evaluated as having a high likelihood and medium to high
consequences of posing a risk to the public, site workers, or the environment, and those
vulnerabilities which contribute to the conditions that pose significant risks as described in
the definition of “Significant Risks” above.
Section 18
24
Unfunded Activity – ES&H work that is desirable to conduct, but for which target funding
is not anticipated to be provided, based on planned program direction and budget decision-
making. This also includes the unfunded portion of partially funded ES&H activities.
Unified Budget Call (UNICALL) – Guidance that is issued by the DOE CFO in January to
DOE and NNSA Area/Operations/Field Offices that provide the contents, timing, format,
and instructions for formulating budgets.
25
Appendix C
ES&H Compliance Liability Estimate
ES&H Five-Year Site Plans should provide information necessary to determine the ES&H
Compliance Liability for the site. ES&H compliance activities are considered ES&H
liabilities under GMRA. These liabilities must be recorded by the Field in their annual
financial statement. However, core ES&H activities are not considered part of the ES&H
liability. The compliance activities submitted for the FY 2004 data call should be traceable
back to the compliance activities identified during the FY 2003 budget cycle. ES&H
compliance activities should be specifically identified in ES&H Five-Year Site Plans so the
ES&H Compliance Liability can be defined for the site. The definitions for compliance
activities and core activities are provided in Appendix B.
Compliance activities identified in ES&H Five-Year Site Plans should specify the
underlying drivers (i.e., law, regulation, agreement, DOE order, standard, or guidance) that
are motivating the activity.
Specific guidance on what comprises the ES&H Compliance Liability is as follows:
On an annual basis, the DOE CFO directs sites to verify their total cumulative
ES&H liability funding and the individual activities that make up the total.
Therefore, site and NNSA Area/Operations/Field Offices must be able to reconcile
any differences between compliance activities for two subsequent annual budget
submissions. Any differences should be known and attributable to a specific
reason, i.e., either the activity was completed in the fiscal year, the activity was re-
scoped, or the activity is no longer considered a compliance issue.
The FY 2002 ES&H Compliance Liability estimate should include the total
estimated costs of all compliance activities identified in FY 2004 ES&H Five-Year
Site Plans. Funding identified in both funded and unfunded ES&H compliance
activities should be summed for FY 2003 and beyond. Field Offices should ensure
their data is consistent with NNSA's FY 2004 budget process.
Per the guidance developed by the DOE CFO, the ES&H Compliance Liability
Estimate is the total estimated cost of all compliance activities funded by all
Cognizant Secretarial Officers, except Environmental Management (EM). The EM
portion of the ES&H compliance liability is reported separately under the
Accelerating Cleanup: Paths to Closure effort. The estimate should also exclude
compliance activities funded by other federal government agencies, e.g., the
General Services Administration. Compliance funding should be allocated among
the following three categories:
(1) Funded operating expenses (OE) and capital equipment (CE) activities,
summed from FY 2003 to the completion of the activity;
(2) Funded general plant projects (GPP) and line- item construction projects
(LIP), summed for FY 2003 to the completion of the project; and
(3) Total estimated funding (OE, CE, GPP, and LIP) for all currently unfunded
compliance activities that need to be funded in the future, summed for FY
2003 to the completion of the activity/project.
Section 19
26
Documentation should be maintained to describe all adjustments to the ES&H
compliance liability that was recorded for FY 2001. A reconciliation schedule must
be provided to the Office of Financial Control and Reporting as part of the year-end
financial statement footnote disclosures. The reconciliation should reflect the
differences between FY 2001 and FY 2002 in terms of compliance activities (1)
completed; (2) re-scoped; or (3) no longer deemed necessary. The year-end
footnote disclosure guidance will provide a general format for this reconciliation.
In general, the reconciliation of the ES&H Compliance Liability information should
utilize the following structure:
• Beginning balance as of FY 2002 (from FY 2003 plan)
• Less FY 2002 costs incurred (from FY 2003 plan)
• Changes due to items no longer compliance
• Changes due to a change in scope
• Other items (new compliance activities)
• ES&H liability – Ending balance
Field Offices should retain a signed copy of ES&H Five-Year Site Plans identifying
ES&H compliance activities at their sites for audit purposes. Signatories comprise
facility/site managers and cognizant Field Element Manager. In addition, the
Operations Office/Area Office Manager or designee must sign the forwarding
memorandum for the ES&H compliance liability estimate and is responsible for the
accuracy of the estimated cost and scope of the ES&H compliance data.
27
Appendix D
Functional Areas
As noted in section 4.1.1 of this guidance, ES&H functional areas have been
established to assist planners in understanding and communicating the major ES&H
issues, activities, and costs associated with a facility or sites overall ES&H program.
Functional area definitions are provided in the DOE-wide ES&H Guidance included
with the Field Budget Call. NNSA has established three unique functional areas
(Safety Authorization Basis, Nuclear Criticality Safety, and Nuclear Safety) that are
defined in this attachment. These definitions are intended as guidance for the types of
programmatic activities that are included in the particular functional area.
Sites with approved Contract List B’s or approved Work Smart Standard sets should
utilize their List B or Work Smart Standard sets to determine requirements applicable
to their site. These definitions do not add requirements or supercede the site’s
approved requirements in the Contract List B or Work Smart Standard sets. Specific
sub-areas and associated compliance drivers are delineated in each func tional area to
facilitate the development of comprehensive programs.
Additional NNSA Safety and Health Functional Areas
Functional
Area Code Functional Area Name and Description
AB SAFETY AUTHORIZATION BASIS
The Safety Authorization Basis functional area includes all activities related
to the development and review of authorization basis documentation required
at DOE sites. The authorization basis establishes the safety envelope for a
facility operation or activity and defines what will have to be done to control
safety of the operation (or activity). The authorization basis includes the
hazard analysis, the definition of administrative and engineering controls to
prevent and mitigate hazards, and the associated technical and operational
limits. The type of safety documents that will constitute the authorization
basis will vary with the hazard and complexity of the operation or activity.
The costs associated with the activities for preparation of these hazards
analyses shall be reported herein; costs associated with operational testing,
training of operating personnel, and similar costs involved in the preparation
of new facilities for weapon production operations shall be reported under
Facilities Management and Site Planning. Primary regulations and DOE
orders relevant to this area include: 10 CFR 820; 10 CFR 830; DOE O 420.1;
DOE G 420.1-1; DOE G 420.1-2; DOE O 420.2A; DOE O 430.1A; DOE O
5480.21; DOE O 5480.22; DOE O 5480.23; DOE O 5480.30; DOE O
6430.1A; DOE P 410.1A; DOE P 430.1.
Section 20
AB1 Nuclear Explosive Facilities Operation Authorization Basis
The costs for authorization basis documentation as required by DOE O 452.1B,
Nuclear Explosive and Weapons Surety Program; DOE O 452.2B, Safety of Nuclear
Explosives Operations; DOE G 452.2A-1A, Implementation Guide for DOE Order
452.2A, Safety of Nuclear Explosives Operations; DOE O 452.4 Security and
28
Control of Nuclear Explosives and Nuclear Weapons; and DOE M 452.4-1,
Protection of Use Control Vulnerabilities and Designs and associated requirements.
AB2 Nuclear Facilities Operation Authorization Basis
The costs for authorization basis documentation as required by DOE O
5480.23, Nuclear Safety Analysis Reports; DOE O 5480.22, Technical safety
Requirements; and DOE O 5480.21, Unreviewed Safety Question, and
associated requirements.
AB3 Non-Nuclear Facilities Operation Authorization Basis
The costs for authorization basis documentation as required in DOE orders and
associated requirements.
AB4 Readiness Review Program
Activities for the contractor to implement an internal Readiness Review
Program, and to undergo a DOE/NNSA Operational Readiness Review
(ORR) or Readiness Assessment (RA), where determined by DOE/NNSA in
accordance with DOE O 425.1B, Startup And Restart Of Nuclear Facilities,
and supporting requirements. These include contractor activities to prepare
the following documents: startup/restart notification reports, plans-of-action,
implementation plans, ORR/RA final reports, and pre-start/post-start action
plans.
NC NUCLEAR CRITICALITY SAFETY
The Nuclear Criticality Safety functional area includes those activities that serve to
prevent or terminate an inadvertent nuclear chain reaction in non-reactor
environments. Included are: practices and procedures relevant to nuclear criticality
safety program administration and oversight, nuclear criticality safety design and
performance of safety evaluations and analyses, criticality alarms and detection
systems and emergency response, and programmatic engineering and/or
administrative controls of processes, storage, and procedures for fissionable
materials that exist in such form and quantity where the potential for a nuclear
criticality accident exists and thus, presents a potential nuclear hazard to the
employees and the general public. Also included are activities involving nuclear
criticality safety physics experiments on such materials, development and
maintenance of computational codes and methods for determining nuclear
criticality hazards, and nuclear criticality safety personnel selection, training, and
qualification for the following types of operations: production, processing, or
storage of radioactive liquid or solid waste (prior to their transfer to facility waste
operations units), nuclear material separations operations; irradiated materials
inspection, fuel fabrication, decontamination or recovery operations; and fuel
enrichment operations.
NC.1 Nuclear Criticality Safety Physics and Computation
Primary regulations and DOE orders relevant to this area include: 10 CFR 830;
DOE O 420.1; DOE G 421.1-1.
29
NC.2 Design, Engineering and Administrative Controls
Primary regulations and DOE orders relevant to this area include: 10 CFR 830;
DOE O 420.1; DOE G 420.1-1; DOE G 421.1-1; DOE O 425.1B; DOE 5480.21;
DOE 5480.22.
NC.3 Personnel Training and Qualifications
Primary regulations, DOE orders and standards relevant to this area include: 10
CFR 830; DOE O 420.1; DOE G 421.1-1; DOE O 5480.20A; DOE-STD-1135-99.
Section 21
NC.4 Program Administration, Safety Evaluation and Analysis
Primary regulations, DOE orders and standards relevant to this area include: 10
CFR 830; DOE O 420.1; DOE G 421.1-1; DOE O 5480.23; DOE-STD-3007-93;
DOE-STD-1134-99.
NC.5 Criticality Alarms, Detection Systems and Emergency Response
Primary regula tions and DOE orders relevant to this area include: 10 CFR 830;
DOE O 420.1; DOE G 421.1-1.
NS NUCLEAR SAFETY
The Nuclear Safety functional area includes those activities that serve to maintain
or improve the level of safety involved with radioactive and or fissionable materials
that exist in such form and quantity that a nuclear hazard potentially exists to the
employees or the general public. Included are activities involving explosive safety
or nuclear operations safety associated with the following types of operations:
production, processing, or storage of radioactive liquid or solid waste (prior to their
transfer to facility waste operations units), fissionable materials or tritium; nuclear
material separations operations; irradiated materials inspection, fuel fabrication,
decontamination or recovery operations; and fuel enrichment operations. In
addition, Safety Authorization Basis and Nuclear Criticality Safety are addressed in
their own separate functional areas.
It is not intended that the programmatic aspects of nuclear operations be captured
and reported in this functional area; only those activities designed to enhance or
maintain the safety and health performance of the line programs should be
categorized as nuclear safety. The physical systems, personnel and programs to
provide nuclear material accountability, and S&S are not included in ES&H Five-
Year Site Plans.
NS.1 Explosive Safety
Primary regulations and DOE orders relevant to this area include: 10 CFR 830;
DOE O 452.2B.
NS.2 Operations and Processing Safety
Primary regulations and DOE orders relevant to this area include: 10 CFR 830; DOE O
420.1; DOE G 420.1-1; DOE G 420.1-2; DOE O 5480.20A; DOE O 425.1B.
30
NS.3 Material Handling and Control
Primary DOE orders relevant to this area include: DOE O 460.2; DOE O 461.1;
DOE M 461.1-1; DOE O 5660.1B.
NS.4 Facilities and Systems
Primary regulations and DOE orders relevant to this area include: 10 CFR 820; 10
CFR 830; DOE O 420.1; DOE G 420.1-1; DOE G 420.1-2; DOE O 420.2A; DOE
O 430.1A; DOE O 5480.21; DOE O 5480.22; DOE O 5480.23; DOE O 5480.30;
DOE O 6430.1A; DOE P 410.1A; DOE P 430.1.