NAP 413.3, Responsibilities for Independent Cost Estimates
To establish policy and responsibilities for conducting Independent Cost Estimates (ICEs) and Independent Cost Reviews (ICRs) within the U.S. Department of Energy’s National Nuclear Security Administration (DOE/NNSA).
Cancels NAP 28A, Responsibilities for Independent Cost Estimates, dated 2-24-16.
Version history and related documents
Superseded by
A newer version replaces this document.
- NAP 413.3AResponsibilities for Independent Cost Estimates (Apr 30, 2021)
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Cost Estimating and Program Evaluation
http://directives.nnsa.doe.gov/
printed copies are uncontrolled
NNSA POLICY
Approved: 02-13-19
Expires: 02-13-22
RESPONSIBILITIES FOR INDEPENDENT
COST ESTIMATES
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Cost Estimating and Program Evaluation
NAP 413.3
http://directives.nnsa.doe.gov/
THIS PAGE INTENTIONALLY LEFT BLANK
1 NAP 413.3
02-13-19
RESPONSIBILITIES FOR INDEPENDENT COST ESTIMATES
1. PURPOSE. To establish policy and responsibilities for conducting Independent Cost
Estimates (ICEs) and Independent Cost Reviews (ICRs) within the U.S. Department of
Energy’s National Nuclear Security Administration (DOE/NNSA).
2. CANCELLATION. NAP 28A, Responsibilities for Independent Cost Estimates,
dated 2-24-16.
3. APPLICABILITY.
a. Federal. This applies to all NNSA Elements.
b. Contractors. Does not apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 USC sections 2406 and 2511, and to
ensure consistency throughout the joint Navy/DOE Naval Nuclear Propulsion
Program, the Deputy Administrator for Naval Reactors (Director) will implement
and oversee requirements and practices pertaining to this Directive for activities
under the Director's cognizance, as deemed appropriate.
4. SUMMARY OF CHANGES.
a. Added references.
b. Added definitions/acronyms.
c. Modified contact information (refer to Section 10).
d. Added ICE/ICR process (refer to Appendix 2).
5. BACKGROUND. Independent Cost Estimates and Independent Cost Reviews offer
NNSA the ability to verify and validate program baseline estimates by providing
unbiased and objective comparisons for, and assessments of, the reasonableness of the
baseline estimate. ICEs and ICRs have been recognized as a best practice by both
Federal and industry organizations, including the Government Accountability Office
(GAO), the Department of Defense (DOD), and the Defense Acquisition University
(DAU). The GAO Cost Estimating and Assessment Guide affirms that, “A realistic cost
estimate allows better decision making, in that an adequate budget can accomplish the
tasks that ultimately increase a program’s probability of success.”
Recent legislation codified in 50 U.S.C. 2411 and 50 U.S.C. 2537 established the NNSA
Office of Cost Estimating and Program Evaluation (CEPE), defined Major Atomic
Energy Defense Acquisition (MAEDA) Programs, and specified when ICEs are to be
performed on those programs. MAEDA programs do not fall under DOE Order 413.3.B,
Program and Project Management for the Acquisition of Capital Assets and its associated
Guides and NNSA Business Operating Procedures, and necessitate the creation of this
2 NAP 413.3
02-13-19
NAP. This NAP establishes roles and responsibilities for conducting ICEs and ICRs on
acquisition programs and capital asset projects.
6. REQUIREMENTS. The following organizations will conduct ICEs or ICRs when
required at project and program milestones, such as Critical Decision points or 6.X
process phases, and at the request of the Administrator:
a. Acquisition and Program Management (NA-APM) will conduct the ICE and ICR
for capital asset acquisition projects covered by DOE Order 413.3B (or successor
order) with an estimated total project cost less than $100 million and based on
criteria defined in DOE Order 413.3B. For projects with an estimated total
project cost greater than $100 million, the ICEs and ICRs will be conducted by
the DOE Office defined per DOE Order 413.3B (or successor order).
Section 2
b. The appropriate Deputy Administrator or Associate Administrator will conduct
the ICE or ICR for acquisition programs where the total project or program cost is
less than $500 million and are not covered by DOE Order 413.3B (or successor
order). That ICE or ICR will be provided to CEPE for review and approval.
When directed by the Administrator, CEPE will conduct the NNSA ICE or ICR
on these programs.
c. CEPE will conduct the NNSA ICE and ICR for programs meeting the definition
for a MAEDA program where the total project or program cost is greater than
$500 million or the total lifetime cost is greater than $1 billion (see process in
Appendix 2). The appropriate Deputy Administrator or Associate Administrator
may perform their own independent cost estimate as needed, such as for the
annual Stockpile Stewardship and Management Plan (SSMP, or its successor).
7. RESPONSIBILITIES.
a. Director of Cost Estimating and Program Evaluation is responsible for
maintaining this NAP and establishing BOPs and instructions for its
implementation.
b. Deputy Administrators and Associate Administrators are responsible for
providing to CEPE the ICEs and ICRs conducted under this policy.
c. Associate Administrator for Acquisition and Project Management (NA-APM) is
responsible for conducting ICEs and ICRs for capital asset construction and
Major Items of Equipment projects in accordance with this policy and for
maintaining BOPs specific to ICEs and ICRs on capital asset acquisition projects.
d. Federal Program Managers and Federal Project Directors are responsible to
provide data and documentation in support of ICEs and ICRs as requested, and
coordinate schedules to accommodate ICEs and ICRs as needed, to meet
milestone decisions. For programs meeting the definition of a MAEDA program,
NAP 413.3 3
02-13-19
the Federal Program Manager will provide a cost analysis requirements
description (CARD).
8. REFERENCES.
a. Federal Laws and Regulations
(1) 50 United States Code Section 2411, Director for Cost Estimating and
Program Evaluation
(2) 50 United States Code Section 2537, Selected Acquisition Reports and
independent cost estimates and reviews of life extension programs and
new nuclear facilities
(3) 50 United States Code Section 2753, Notification of cost overruns for
certain Department of Energy projects
b. Government Accountability Office
GAO-09-3SP, GAO Cost Estimating and Assessment Guide
c. DOE
(1) DOE Order 413.3B, Program and Project Management for the
Acquisition of Capital Assets
(2) Nuclear Weapons Council, Procedural Guideline for the Phase 6.X
Process, dated 4-19-00
d. NNSA
BOP 06.03, Independent Cost Estimates Procedure
9. DEFINITIONS/ACRONYMS.
a. Acquisition Program – A defined duration, funded effort from
conceptualization, initiation, design, development, test, contracting, production,
deployment, logistics support, modification, and disposal to provide a new,
improved, or continuing weapon and weapon systems or other product to satisfy
NNSA mission requirement or capability gap, intended for use in, or in support
of, NNSA missions.
b. Baseline – A quantitative definition of cost, schedule, and technical performance
that serves as a base or standard for measurement and control during the
performance of an effort; the established plan against which the status of
resources and the effort of the overall program, field program(s), project(s),
task(s), or subtask(s) are measured, assessed, and controlled. Once established,
baselines are subject to change control discipline.
Section 3
4 NAP 413.3
02-13-19
c. Capital Asset Acquisition Project – A project with defined start and end points
required in the acquisition of capital assets. The project acquisition cost of a
capital asset includes both its purchase price and all other costs incurred to bring it
to form and a location suitable for its intended use. It is independent of funding
type. It excludes operating expense funded activities such as repair, maintenance
or alterations that are part of routine operations and maintenance functions and do
not exceed the general plant project threshold.
d. Cost Analysis Requirements Description (CARD) – A description of the
relevant features of the acquisition program or project and of the system itself. It
is the common description of the technical and programmatic features of the
program that is used by the teams when preparing the ICE and/or program office
cost estimates. It is intended to define the program to a sufficient level of detail
such that no confusion exists between the many parties who may be concerned
with estimating the program’s cost.
e. Cost Estimating Risk (CER) – The risk reflects one's confidence in the input
parameters used to develop a cost estimate. Cost estimating risk arises from the
inaccuracies inherent in the programmatic assumptions or technical data used as
inputs to CERs.
f. Cost Estimating Uncertainty – The uncertainty reflects one's confidence in the
point estimate. Cost estimating uncertainty arises from the inaccuracies inherent
in the cost estimating methodologies.
g. Earned Value Management (EVM) – A project performance method that
utilizes an integrated set of performance measurements (e.g., scope, cost, and
schedule) to assess and measure project performance and progress, and estimate
cost and schedule impacts at completion.
h. Federal Program Manager (FPM) – An individual in the headquarters
organizational element responsible for managing a program and its assigned
projects. They ensure that all the projects are properly phased, funded over time,
and that each project manager is meeting their key milestones. They are the
project manager's advocate, ensure proper resourcing, and facilitate the execution
process. They predict programmatic risks and put mitigation strategies in place so
that projects are not affected.
i. Independent Cost Estimate (ICE) – A cost estimate prepared by an organization
independent from the government line manager’s authority and the contractor
organization responsible for the project or program, using the same detailed
technical and procurement information to develop the program and/or project
estimate in accordance with GAO best practices.
j. Independent Cost Review (ICR) – An evaluation of a program’s or project’s
cost estimate that examines the reasonableness of the estimate quality,
NAP 413.3 5
02-13-19
assumptions, and risks, also prepared by an organization independent from the
government line manager’s authority and the contractor organization responsible
for the project or program.
k. Life-Cycle Cost Estimate (LCCE) – The cost to the government of acquisition
and sustainment of a system over its useful life. It includes the cost of
development, acquisition, operations, and support (to include manpower), and
where applicable, disposal. For defense systems, LCCE is also called Total
Ownership Cost (TOC).
Section 4
l. Major Atomic Energy Defense Acquisition (MAEDA) Program – An atomic
energy defense acquisition program of which the total project cost is more than
$500 million and/or the total lifetime cost is more than $1 billion. The term
‘major atomic energy defense acquisition program’ does not include a project
covered by DOE Order 413.3B (or a successor order) for the acquisition of capital
assets for atomic energy defense activities.
m. Phase 6.X Process – Provides the framework for nuclear weapons activities
(including life extension programs), such as routine maintenance, stockpile
evaluation, surveillance, baselining, and annual certification.
n. Total Lifetime Cost (TLC) – Is equivalent to the lifecycle cost for projects and
programs. The TLC includes the costs of conceptualization, initiation, design,
development, test, contracting, production, deployment, logistics support,
modification, and disposal.
o. Total Project Cost/Total Program Cost (TPC) – For projects following DOE
Order 413.3B (or successor order), TPC is all costs between CD-0 and CD-4
specific to a project incurred through the startup of a facility, but prior to the
operation of the facility. For programs following the 6.X process, the TPC will
cover all costs from phase 6.1 through phase 6.6. For other acquisition programs,
the TPC is the cost of conceptualization, initiation, design, development, test,
contracting, and production prior to operation and disposal.
p. Work Breakdown Structure (WBS) – A numeric structure incorporating logic
to capture scope, cost, and schedule of work. The WBS mentioned in this
document will be standardized and common across the nuclear security enterprise
and will include Work for Others and other Department of Energy programs to
identify total site costs and scope. A program WBS provides a framework for
program and technical planning, cost estimating, resource allocations,
performance measurements, and status reporting. The WBS should define the
total system to be developed or produced; display the total system as a product-
oriented family tree composed of hardware, software, services, data, and facilities;
and relate the elements of work to each other and to the end product.
6 NAP 413.3
02-13-19
10. CONTACT. Director, Office of Cost Estimating and Program Evaluation, 202-586-6910.
BY ORDER OF THE ADMINISTRATOR:
Appendixes:
1. NAP Defined ICE/ICR Responsibilities
Lisa E. Gordon-Hagerty
Administrator
2. Independent Cost Estimate and Independent Cost Review Process
NAP 413.3 Appendix 1
02-13-19 AP1-1
APPENDIX 1: NAP DEFINED ICE/ICR RESPONSIBILITIES
FIGURE 1. Areas of responsibilities for ICE/ICRs
THIS PAGE INTENTIONALLY LEFT BLANK
NAP 413.3 Appendix 2
02-13-19 AP2-1
APPENDIX 2: INDEPENDENT COST ESTIMATE AND INDEPENDENT COST
REVIEW PROCESS
1. REQUIREMENTS. This appendix applies to the NNSA ICEs and ICRs on programs
conducted by CEPE. For capital asset acquisition projects that fall under DOE Order
413.3B (or successor order), refer to BOP 06.03, Independent Cost Estimates Procedure.
a. The Federal Program Office (FPO) program schedule must include sufficient time
for independent reviews of all cost estimates as required. The notional timelines
for submission are outlined in Section 3.
b. Guidance and oversight will be provided by the Cost Integrated Product Team
(IPT). The Cost IPT must be chaired by CEPE and include the Federal Program
Manager (FPM), program cost group representative, and other stakeholders as
needed.
Section 5
c. The following deliverables must be produced:
(1) ICE/ICR Notification must be sent to CEPE when the program is at least
210 days before a program milestone and requires an ICE or ICR.
(2) Cost Analysis Requirements Description (CARD) must be consistent with
guidance developed by CEPE. The CARD must contain the system
purpose, detailed technical system and performance characteristics, work
breakdown structure, description of legacy or similar systems, quantities,
program schedule, system test and evaluation plan, staffing requirements,
and other support and sustainment requirements.
(3) Program Cost Estimate must be developed and submitted to CEPE no later
than 60 days before a program milestone or as determined by the Cost IPT.
(4) ICE/ICR Report on the results of the ICE or ICR must be sent to the
Administrator and the Deputy Administrator or Associate Administrator
(DA/AA) as appropriate.
d. The ICE/ICR process must be consistent with published GAO best practices on
cost estimating. When GAO best practices cannot be followed, any deviations
must be justified and documented as part of the cost estimate reporting.
2. RESPONSIBILITIES.
a. Director of Cost Estimating and Program Evaluation (CEPE):
(1) Develops ICEs and ICRs;
(2) Approves the CARD with the FPM; and
Appendix 2 NAP 413.3
AP2-2 02-13-19
(3) Provides a report on the results of the ICR or ICR to the
Administrator and the DA/AA.
b. Deputy Administrator or Associate Administrator (DA/AA):
(1) Develops program cost estimates;
(2) Notifies CEPE when their program is at least 210 days before a
program milestone and requires an ICR or ICR; and
(3) Provides the program cost estimate to CEPE no later than 60 days
before a program milestone or as determined by the cost IPT.
c. Federal Program Manager (FPM):
(1) Provides data and documentation in support of current and future
ICEs/ICRs consistent with guidance developed by CEPE;
(2) Coordinates schedules to accommodate ICEs/ICRs as needed prior
to milestone decisions;
(3) Develops a CARD; and
(4) Approves the CARD with the Director of CEPE.
d. Cost Integrated Product Team (IPT):
(1) Integrates and synchronizes cost efforts related to the program
prior to a program milestone;
(2) Defines the purpose of the estimate;
(3) Develops the estimate plan; and
(4) Ensures that data is shared between stakeholders and that
deliverable dates are met in a timely manner.
3. PROCESS.
a. Figure 1 sets forth the typical timeline of events and deadlines to support the
timely completion of an ICE/ICR. This timeline may be tailored by the Cost IPT,
depending upon the program and the information needed to support the decision
maker.
b. At least 210 days before the program milestone, the DA/AA must notify CEPE of
a program’s upcoming event that requires an ICE or ICR that is covered by
NNSA policy. The Administrator will notify CEPE of an ICE or ICR requirement
that is not covered by NNSA policy.
NAP 413.3 Appendix 2
02-13-19 AP2-3
c. A kick-off meeting is held no later than 180 days before the program milestone.
Before the kick-off meeting, CEPE and the FPM will develop an agenda of
information to discuss, to include requirements for the cost estimates, alternatives
to consider, and the assumptions on which the cost estimates will be based. A
CEPE representative and the FPM must co-chair the kick-off meeting.
d. The FPO will prepare and deliver the draft CARD to CEPE no later than 180 days
before the program milestone.
Section 6
e. No later than 45 days after receipt of the draft CARD (usually at least 135 days
before the program milestone), CEPE will provide feedback to the FPO stating
that the CARD is sufficiently or insufficiently developed to continue with
preparation of the cost estimates.
f. Following the kick-off meeting and continuing until the program milestone,
representatives from CEPE and FPO will conduct site visits, and collect and
review program data consistent with guidance developed by CEPE.
g. A final copy of the CARD must be provided to CEPE by the FPO at least 90 days
before the scheduled program milestone and placed into the electronic CEPE Data
Library. The Director of CEPE and the FPM must jointly approve the final
CARD.
h. In accordance with GAO best practices, CEPE will conduct a sensitivity analysis
in order to identify the effects of changing key cost driver assumptions and
factors. The sensitivity analysis will provide a range of possible costs, a point
estimate, and a method for performing what-if analysis.
i. In accordance with GAO best practices, the ICE will reflect the degree of
uncertainty, so that a level of confidence can be given about the estimate. CEPE
will conduct quantitative risk and uncertainty analysis in order to calculate a
confidence interval or range of possible costs.
j. The DA/AA must deliver the final, signed Program Cost Estimate to CEPE and
the Cost IPT at least 60 days before the program milestone or as determined by
the Cost IPT. For an ICR, the DA/AA must deliver the full life-cycle cost
estimates (LCCEs) for each option to CEPE and the Cost IPT at least 60 days
before the program milestone or as determined by the Cost IPT. Copies of these
documents must be submitted to the CEPE Data Library.
k. No later than 60 days before the program milestone, CEPE must deliver the draft
ICE or ICR to the Cost IPT. During this time, CEPE, DA/AA, and FPO
representatives will have ongoing discussions with the Cost IPT concerning the
cost estimating strategies and methodologies used to develop the ICE/ICR and the
DA/AA Program Cost Estimate or LCCEs.
Appendix 2 NAP 413.3
AP2-4 02-13-19
l. No later than 45 days before the program milestone, representatives from CEPE,
FPO, and the DA/AA will meet with the Cost IPT to compare and discuss the
results of the final ICE/ICR and the DA/AA Program Cost Estimate or LCCEs,
and address any data inaccuracies. Major discrepancies between the two estimates
will be reconciled and briefed to the DA/AA and the Administrator as well as
captured in a Decision Memorandum. Reconciliation will also address changes to
the proposed budget in the FYNSP where applicable.
m. A CEPE representative will provide a summary brief of the ICE or ICR to the
DA/AA no later than 30 days before the program milestone as appropriate.
n. A CEPE representative will provide a summary brief of the ICE or ICR to the
Administrator no later than 15 days before the program milestone as appropriate.
o. No later than 10 days before the program milestone, CEPE must issue its ICE or
ICR report, a copy of which must be placed into the CEPE Data Library.
p. CEPE uses the information submitted to the CEPE Data Library when preparing
its annual report to Congress. The annual report summarizes the cost estimation
and analysis activities of the NNSA during the previous year and assesses the
progress of the NNSA in improving the accuracy of its cost estimates and
analyses.
Appendix 2
AP2-5
NAP 413.3
02-13-19
Section 7
Figure 1: Timeline for the Preparation of the NNSA ICE/ICR
NAP 413.3 Responsibilities for Independent Cost Estimates
1. Purpose
2. Cancellation
3. Applicability
a. Federal.
b. Contractors.
c. Equivalency.
4. Summary of Changes
5. Background
6. Requirements
7. Responsibilities
a. Director of Cost Estimating and Program Evaluation
b. Deputy Administrators and Associate Administrators
c. Associate Administrator for Acquisition and Project Management (NA-APM)
d. Federal Program Managers and Federal Project Directors
8. References
9. Definitions/Acronyms
10. Contact
Appendix 1: NAP Defined ICE/ICR Responsibilities
Appendix 2: Independent Cost Estimate and Independent Cost Review Process
1. Requirements
2. Responsibilities
a. Director of Cost Estimating and Program Evaluation (CEPE):
b. Deputy Administrator or Associate Administrator (DA/AA):
c. Federal Program Manager (FPM):
d. Cost Integrated Product Team (IPT):
3. Process
Figure 1: Timeline for the Preparation of the NNSA ICE/ICR