SD 412.1A, Work Authorizations
To supplement Department of Energy (DOE) Order 412.1A, Work Authorization System, for the purpose of establishing procedures to administer National Nuclear Security Administration (NNSA)-sponsored work authorizations (WA) with greater efficiency.
Associated DOE Directive:
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Partnership and Acquisition Services
https://directives.nnsa.doe.gov/
printed copies are uncontrolled
SUPPLEMENTAL DIRECTIVE
Approved: 11-20-24
Certification Due: 11-20-27
WORK AUTHORIZATIONS
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Partnership and Acquisition Services
NNSA SD 412.1A
https://directives.nnsa.doe.gov/
THIS PAGE INTENTIONALLY LEFT BLANK
SD 412.1A 1
11-20-24
WORK AUTHORIZATIONS
1. PURPOSE. To supplement Department of Energy (DOE) Order 412.1A, Work
Authorization System, for the purpose of establishing procedures to administer National
Nuclear Security Administration (NNSA)-sponsored work authorizations (WA) with greater
efficiency.
a. This Supplemental Directive (SD):
(1) Identifies the required WA processes, including the necessary formats.
(2) Identifies review and approval authorities for WAs.
(3) Establishes internal controls necessary to safeguard change control and
ensure consistency.
b. Any inconsistency in this SD must be resolved in the following order of priority:
(1) Contract schedule.
(2) Contract clauses.
(3) DOE Order 412.1A and other DOE Orders as applicable.
2. CANCELLATION. NNSA SD 412.1, Work Authorizations, Dated 1-18-17.
3. APPLICABILITY.
a. Federal. The provisions of this directive apply to all NNSA programs and
NNSA-funded work.
b. Contractors. Does not apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 United States Code (U.S.C.) sections 2406
and 2511, and to ensure consistency throughout the joint Navy/DOE Naval Nuclear
Propulsion Program, the Deputy Administrator for Naval Reactors (Director) will
implement and oversee requirements and practices pertaining to this SD for
activities under the Director’s cognizance, as deemed appropriate.
d. Exemption. Work involving Strategic Partnership Projects; and services, products,
or materials regularly produced for sale at scheduled rates under DOE programs
(e.g., routine irradiation services, radioisotopes, production or transmission of
electricity).
4. SUMMARY OF CHANGES. Implements requirements for storing executed WAs and a
schedule for completing draft WAs. This revision also updates responsibilities to reflect
organizational changes, incorporates changes to clarify the content of implementation
plans, and includes editorial changes for clarity.
2 SD 412.1A
11-20-24
5. BACKGROUND. Department of Energy Acquisition Regulation (DEAR) 970.1170-1
states:
Each contract for the management and operation of a DOE site or facility,
and other contracts designated by the DOE or the National Nuclear Security
Administration (NNSA) Senior Procurement Executive, must contain a scope
of work section that describes, in general terms, work planned and/or
required to be performed. Work to be performed under the contract must
be assigned through the use of a work authorization to control individual
work activities performed within the scope of work. Work authorizations
must be issued prior to the commencement of the work and incurrence of
any costs.
The annual performance-based implementation plan (IP) serves as the statement of work
and will be attached to the WA; the WA is incomplete if it does not have an IP attached.
6. REQUIREMENTS.
a. In accordance with DEAR 970.5211-1, activities must not be authorized nor costs
Section 2
incurred prior to the Contracting Officer (CO) issuance of a WA or direction
concerning continuation of activities of the contract. Therefore, WAs must be
generated and issued to the Contractor before the start of the fiscal year (FY) or as
early in the FY as possible, subject to programmatic needs.
b. Initial WAs must be submitted to the field offices for review on or before August 15
of the preceding FY. The program office must communicate any delays and
extenuating circumstances to the field office if this date will not be met. The
program office and the field office will determine if an interim WA is needed until
the final WA can be executed.
c. If one or more parties do not approve of the scope of work, schedule, or estimated
cost requirements identified in the WA, the parties must find a resolution. In the
event a resolution cannot be reached, the CO has the ultimate authority to resolve
the conflict and may issue WAs unilaterally in accordance with DEAR 970.5211-1.
d. In the case of new work requirements, or changes during the course of the FY, a
WA must be generated or revised as soon as the requirement is identified, accepted
by the Contractor(s), and approved by the CO prior to the commencement of the
work and incurrence of any cost. All changes to a WA must be made using a formal
change control process that is the same as the generation and distribution process of
the initial WA.
e. If operating under a Continuing Resolution (CR) at the start of the FY, the WA must
be issued to align with and not exceed the Department’s Base Table. Within
30 calendar days of final appropriation or full-year CR enactment, the WA must be
updated to reflect any necessary change(s) in scope, schedule, or estimated cost
(price if a fixed price WA) to align with the signed enactment.
SD 412.1A 3
11-20-24
f. All WAs and revisions thereto must be reviewed and accepted by all responsible
parties as outlined in the process map in Appendix B. Signatures are required by
the Program Manager (IP only), the Contractor (WA only), and the cognizant Field
Office CO (WA only) to be considered fully executed. A formal, authorized
contractor signature on the WA indicates agreement on the WA and responsibility
for performance of all related work within the terms and conditions of the contract,
including satisfying all relevant legal, regulatory, integrated safety management,
integrated safeguards and security management, and quality assurance requirements.
The Field Office CO’s signature on both the WA and the associated funding
modification issued by the Procuring Contracting Officer indicates authorization to
begin work.
g. WAs must be generated using the required templates and guidance (see
Appendix A) to ensure consistency across NNSA programs.
(1) The estimated cost on the WA must reconcile the funds obligated or
planning to be obligated on the contract. Changes that are within the scope
of an existing WA do not warrant a new WA or modification to an existing
WA. These changes must be issued in writing via technical direction to the
Contractor by an authorized Contracting Officer’s Representative (COR)
with an informational courtesy copy to the CO and the NNSA Office of
Management and Budget (NA-MB). Program offices have discretion in
determining the most efficient means for routing technical direction within
the NNSA and to the Contractor. COs are required to sign WAs, but are not
Section 3
expected to approve technical direction. The COR’s technical direction
must provide sufficient detail to clearly articulate the expectations of the
work to be performed. However, changes that are not covered within the
scope of the WA must be executed through a new or revised WA.
(2) WAs must be consistent with performance-based contracting requirements
and cascade from the goals, objectives, strategies, and performance
measures reported in the NNSA Strategic Plans, the Future Years Nuclear
Security Program, work plans, and other guidance specifically identified.
(3) WAs must include an IP that serves as the statement of work and describes,
at a minimum, a general description of the work to be performed with a
milestone schedule and deliverables specific to the contractor that is
associated with the WA. The IP may include multiple contractors if the
description of work clearly identifies what is expected for the contractor
associated with the WA and is not a general description of work to be
applied across multiple contractors. Where detailed information is not
included in the work authorization’s attached IP, more specific project
plans, operating plans, or similar documents that describe the scope of work
and deliverables or performance measures and expectations must be
referenced. All documents referenced in the WA must be made available to
contractors, cognizant COs, and CORs upon request.
4 SD 412.1A
11-20-24
(4) Performance expectations, such as a general description of requirements,
estimated cost (price if a fixed price WA), metrics, specific deliverables or
interim milestones, and associated periods of performance must be included
in the WA, with similar or related work being aggregated to the highest
appropriate level (e.g., budget activity, work package, etc.).
h. WAs that crosscut multiple programs must be reviewed by the responsible program
offices to ensure that all programmatic interdependencies have been appropriately
reflected.
i. WAs must be reviewed to ensure:
(1) Programmatic execution guidance is adequate and appropriately
communicated.
(2) Estimated cost (price if a fixed price WA) does not exceed Department’s
Base Table and the final appropriation or full-year CR once enacted.
(3) Full compliance with acquisition regulation, policy, and the terms and
conditions of the contract.
j. Fully executed WAs must be maintained in Strategic Integrated Procurement
Enterprise System (STRIPES) or another location designated by the cognizant CO.
If a location outside of STRIPES is used, a reference must be included in STRIPES
to identify where the WAs are stored. The repository must be organized in a
manner that allows for WAs to be readily identified and obtained.
k. Revisions or amendments to WAs must be issued whenever there is a change
resulting in a change in the work scope and for other changes as determined by the
Program/Project Manager. Revisions or amendments must be numbered and
reflected in the WA.
7. RESPONSIBILITIES.
a. Office of Partnership and Acquisition Services, Strategic Initiatives Branch.
(1) Provides guidance and coordination to facilitate the preparation of WAs and
any revisions thereto.
(2) Assists in the resolution of issues relating to the WA.
(3) Conducts random reviews of WAs submitted to the Work Authorization
Expense Object Coding (WAEOC) mailbox (WAEOC@nnsa.doe.gov) for
quality control, including compliance with regulation and policy. NA-PAS
Section 4
reserves the option to review all WAs for compliance at any time.
SD 412.1A 5
11-20-24
b. Program Office.
(1) Develops initial and subsequent IP in accordance with this SD, applicable
requirements, and the Appendix A template.
(2) Provides the signed IP to NA-MB.
(3) Sends NA-MB funding changes by site, including a high-level description of
those funding changes.
(4) Issues technical direction in writing through an authorized COR, as
appropriate.
(5) Works with COs and contractors to resolve questions or concerns regarding
scope of work, schedule, and associated estimated cost (price if a fixed price
WA) for each WA.
(6) Provides additional programmatic information when requested to review and
approve WAs.
(7) Ensures the estimated cost does not exceed the Department’s Base Table
plus carry over, when under a CR, or the final appropriation or full-year CR
once enacted.
(8) Coordinates with the CO and other internal stakeholders to ensure the work
is completed within the negotiated cost (price if fixed price WA).
c. Management and Budget (NA-MB).
(1) Reviews Approved Funding Program (AFP) input and funding changes from
program office.
(2) Enters values and funding changes into financial system (i.e., Budget
Formulation and Distribution System).
(3) Confirms funding information with program office.
(4) Issues AFP to field office.
(5) Completes the WA using the template in Appendix A. The WA integrates
the IP received from the program office and the AFP amounts.
(6) Issues WA (with the IP attached) to NA-PAS WAEOC Request Mailbox
and field CO.
(7) Validates that funding identified in the WA has been obligated to the
contractor or made available to the field office for obligation.
6 SD 412.1A
11-20-24
(8) Reconciles and resolves discrepancies between WA language, funding, and
obligations.
(9) Maintains record of financial reports and CO-signed WAs to support
reconciliation.
d. Contracting Officers.
(1) Work jointly with the Program or Project Officers and Contractors to reach
agreement on an acceptable scope, cost (price if a fixed price WA), and
schedule for each WA.
(2) Review and sign the proposed WA for each contract under their cognizance
to ensure work is appropriate for performance by the contractor and is within
the contracted scope.
(3) Ensure that the contractor signs the WA within 30 calendar days.
(4) Ensure that the government has funds available and obligates those funds
through a formal contract funding modification or through a formal
incremental funding modification for the authorized work.
(5) Ensure the work is completed within the negotiated cost (price if fixed price
WA).
(6) Send WA to management and operating (M&O) contractor for signature.
(7) Retain the fully signed WA in STRIPES or another repository. If a
repository outside of STRIPES is used, a reference must be included in
STRIPES.
(8) Distribute fully executed WA to program, NA-MB, and WA mailbox
(NNSAWAs@nnsa.doe.gov).
(9) Serve as the primary point of contact for questions or issues concerning the
WA.
8. DEFINITIONS. See Appendix C.
9. REFERENCES. See Appendix D.
10. CONTACT. Office of Partnership and Acquisition Services, 202-586-4921.
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 412.1A Appendix A
11-20-24 APA-1
APPENDIX A: WORK AUTHORIZATION TEMPLATES
WORK AUTHORIZATION TEMPLATE (COST REIMBURSEMENT) .......................................... 2-14
Section 5
WORK AUTHORIZATION TEMPLATE (FIRM-FIXED-PRICE) .................................................... 15-28
Appendix A NNSA SD 412.1A
APA-2 11-20-24
WORK AUTHORIZATION TEMPLATE (COST REIMBURSEMENT)
National Nuclear Security Administration (NNSA)
Office Name
Program Name
Fiscal Year 20XX Work Authorization [insert Work Authorization title]
M&O Site/Contractor:
Work Authorization No: XXXXXX Revision No: 0X
Period of Performance:
Start Date Completion Date Revised Completion
Date
Date of Revision
The following table provides estimated costs for the period of performance.
Fund
Type
Budget &
Reporting No.
(full 9-digits)
Estimated
Cost
Current Change Revised
Authorization
$ $ $
Explanation of Funds:
[Include Explanation of Funds table to identify the intended purposes of the funds. The
EOF may also be included as an attachment.]
Summary of Changes (For Work Authorization Revisions Only):
[Include a brief description of the changes (e.g., incremental funding, additional scope,
etc.).]
1.0 Scope
The Contractor must, in accordance with the terms of the prime Contract and this
Work Authorization, provide the personnel, equipment, materials, supplies, and
services, (except as may be furnished by the Government) and otherwise do all
things necessary for, or incidental to execute the requirements described in this
Work Authorization to include meeting the specific milestones, and providing the
NNSA SD 412.1A Appendix A
11-20-24 APA-3
specific deliverables as described in the Implementation Plan, (which serves as
the Work Authorization Statement of Work) Attachment 1, of this Work
Authorization, “Program Name FY20XX Implementation Plan & Work
Authorization” at [M&O Name]. This Work Authorization is incorporated into
the prime contract in accordance with Department of Energy Acquisition
Regulation (DEAR) 970.5211-1 “Work Authorization.”
2.0 Changes
This Work Authorization and any subsequent changes must be executed in
accordance with the Federal Acquisition Regulation and all other contract terms
and conditions. In accordance with DEAR 970.5211-1, the Contractor must notify
the Contracting Officer immediately whenever the cost incurred plus the
projected cost to complete the work outlined in this Work Authorization is
projected to differ (plus or minus) from the estimated cost by 10 percent.
Changes to the work scope, schedule, or estimated cost as specified in the
attached Implementation Plan must be issued via a Work Authorization revision
signed and issued by the Contracting Officer as required by DEAR 970.5211-1,
DOE Order 412.1A, and NNSA Supplemental Directive 412.1.
3.0 Agreements
No work shall commence until this Work Authorization is approved by the
Contracting Officer. The Contractor signature is a commitment that all Integrated
Safety Management, Integrated Safeguards and Security Management, and
quality assurance requirements have been met, and that auditable records and
files on this project are available for review.
Funding for this work will be obligated through a funding modification issued by
the Contracting Officer as specified in the most recent Approved Funding
Program (AFP).
4.0 DEAR 970.5232-4 Obligation of Funds, flow down to Work Authorizations
This contract clause is hereby flowed down to this Work Authorization. The
Contractor must segregate, allocate, and account for all costs incurred under
this specific Work Authorization. Such cost data must be made available to
Section 6
the Contracting Officer upon request. In addition, the Contractor must
notify the Contracting Officer, in writing, when they recognize that they will
exceed the estimated cost by 10 percent, insufficient actual and expected
funding is available to continue work, or if their actual funding is insufficient
Appendix A NNSA SD 412.1A
APA-4 11-20-24
to operate until further expected funding.
Contractor
[Insert authorized individual
Title
Phone number
email]
[signature]
Date:
Contracting Officer
[insert name
Title
Phone number
email]
[signature]
Date:
NNSA SD 412.1A Appendix A
11-20-24 APA-5
<PROGRAM/PROJECT NAME>
IMPLEMENTATION PLAN (Statement of Work)
Version <1.0>
<mm/dd/yyyy>
Appendix A NNSA SD 412.1A
APA-6 11-20-24
VERSION HISTORY
Versio
n #
Implement
ed
By
Revisio
n
Date
Approve
d
By
Approva
l
Date
Reason
1.0 Author name mm/dd/yy name mm/dd/yy <reason>
NNSA SD 412.1A Appendix A
11-20-24 APA-7
Table of Contents
I. OVERVIEW [REQUIRED] .............................................................................................................................. 7
II. CORPORATE PROGRAM GOAL(S) [REQUIRED] ......................................................................................... 7
III. MAJOR ACTIVITIES [REQUIRED] ................................................................................................................. 7
IV. FUNDING GUIDANCE [REQUIRED] ............................................................................................................. 7
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED] ............................................................................... 8
VI. REPORTING REQUIREMENTS [REQUIRED] ................................................................................................. 9
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED] ................................................................ 9
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL] ....................................................................... 9
IX. POINTS OF CONTACT [REQUIRED] ............................................................................................................ 9
X. APPROVALS ............................................................................................................................................... 11
APPENDIX A: KEY TERMS [OPTIONAL] ............................................................................................................... 12
Appendix A NNSA SD 412.1A
APA-8 11-20-24
I. OVERVIEW [REQUIRED]
This section:
• Describes the purpose of the program/project and is sourced
by the most recent Congressional Budget Request; and
• Provides clear strategic alignment for the program/project to the most
current DOE and NNSA Strategic Plans by strategic goal and objective.
Optional: A table is optional in this subsection if the Work Authorization (WA)
supports multiple strategic objectives.
Required boilerplate language: “Specific work activities and scope contained
herein are consistent with: ( 1) the Department’s Base Table when operating
under a Continuing Resolution (CR); and (2) the final appropriation or full-year CR
once enacted.”
II. CORPORATE PROGRAM GOAL(S) [REQUIRED]
This section is required by Government Performance and Results Act Modernization
Act of 2010. Information to include: Program Name, Performance
Measure/Indicator Title and Description, Fiscal Year Target and, where applicable,
Section 7
End Point Target. Source: Most current Congressional Budget Request
performance table(s).
Program or Project
Name
Performance
Measure/Indicator Title
and Description
FY201X
Target
Endpoint Target
Required boilerplate language: “Preliminary targets are subject to change
based on a final, enacted budget.”
III. MAJOR ACTIVITIES [REQUIRED]
This section provides a description of the program/project major activities
that are not site-specific, but general program priorities during the period of
performance. These major activities are traceable to the most current
NNSA SD 412.1A Appendix A
11-20-24 APA-9
Congressional Budget Request.
IV. FUNDING GUIDANCE [REQUIRED]
This section describes Program and Fiscal Guidance, such as including the
estimated cost for each management and operating (M&O) Contractor. The
table below (or some variation as directed by the Office of Partnership and
Acquisition Services [NA-PAS]) must be completed for inclusion in the WA.
Program/O
CL
President’s
FY20XX
Budget
Request
FY20XX CR
Operating
Target
FY20XX
Enacted/Full-
Year
CR
Difference
between
Request vs.
Enacted
The initial estimated cost is equal to the Department’s Base Table and must
reflect 100 percent completion of the work activities as described in Section V,
Description of Planned Activities. Once an appropriation or full-year CR is
enacted the estimated cost must be updated to reflect any updates to the scope
of work.
Required language: “To support the scope of work contained in this Work
Authorization (WA), funding will be distributed through the existing Approved
Funding Program (AFP) process described in DOE Order 130.1A and NAP 130.1C,
or successor Order/NAP, as applicable. The AFP is adjusted on an as-needed
basis for the execution of congressionally approved programs, projects, or
activities (PPAs). Specific work activities are authorized via this document, with
incremental funding plans for each site authorized via the AFP and obligated via
formal contract modification. The work contained herein will be funded on an
incremental basis. The Contractor is authorized to expend up to the dollar
amount indicated in the Program/Obligation Control Level (OCL) funding table or
as otherwise noted in the AFP allotment, whichever is less, and subject to the
availability of funds in the M&O contract.
Note: As indicated in Section 4.0, the Contractor is required to notify the
Contracting Officer, in writing, when they recognize that they will exceed the
estimated cost by 10 percent, insufficient actual and expected funding is available
to continue work, or if their actual funding is insufficient to operate until further
expected funding.”
Appendix A NNSA SD 412.1A
APA-10 11-20-24
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED]
This subsection provides the information referenced under the Scope Section of
the WA cover sheet and must be in sufficient detail to meet the requirements of
DEAR 970.5211-1. At a minimum, the planned activities must replicate the
Congressional Budget Request (budget narrative), must be written to the
site-specific level, and must include: a general description of the work, primary
deliverables or performance expectations, and schedule of key deliverables as
shown in the table below or a specific reference where the work and estimated
cost information can be found.
Required language: “The purpose of this WA is to outline key work
Section 8
requirements to be performed and to control individual work activities within the
scope of work. Contractors may not deviate from this plan without a revised
WA.”
Required language (for NNSA M&O Contracts only): “Annual performance
expectations for each M&O Contractor outlined in this document may be
considered in determining the Contractor’s performance rating and fee earned
through the NNSA Corporate Performance Evaluation Process (CPEP).”
Note: The level of detail must provide sufficient information to the site to
enable mission execution at a level of performance needed to support the
appropriate CPEP evaluation requirements.
Note: If the type of work is considered a level of effort (LOE), performance
criteria can be either quantitative or qualitative, yet it must be measurable. It is
appropriate to think of criteria as “entry” and “exit” criteria (i.e., the current state
of the planned activities and the expected state of the planned activities at
completion of the LOE) that supports mission accomplishment of deliverables.
Exit criteria should reflect what must be done to clearly ascertain if the event has
been successfully completed. The Implementation Plan/Work Authorization
includes the approval of work at designated site(s).
VI. REPORTING REQUIREMENTS [REQUIRED]
This subsection must contain sufficient detail on any applicable reporting
expectations or include reference to applicable document(s) with detailed
reporting expectations.
NNSA SD 412.1A Appendix A
11-20-24 APA-11
Examples:
• All sites (M&O Contractor and non-M&O Contractor sites) must report
cost data at the project level on or before the 10th day of the month.
• Monthly performance reporting for completed activities is required on or
before the 5th workday of the month.
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED]
Required language: “The following documents are incorporated by reference:”
This subsection is in bullet format and must include key execution year reference
documents, which may include:
• X Strategic Plan (Month, Year)
• X Integrated Master Plan and Integrated Master Schedule
• X Program Management Plan (PMP) (Month, Year, Version)
• Portfolio Work Plans (PWPs)
• Approved Funding Program Explanation of Changes (AFP) and
regular monthly financial plan adjustments.
• Other (references to detailed Statements of Work (SOW), work
proposals, project plans or similar documents).
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL]
This subsection can be used to outline programmatic risk associated with the
authorized scope. If needed, the Program should provide details here that will
help manage expectations to ensure accomplishment of mission scope and
deliverables absent of unanticipated barriers or reference a document that
discusses risk management (e.g., PMP).
IX. POINTS OF CONTACT [REQUIRED]
This subsection identifies responsible organization(s), titles, e-mail addresses,
and telephone numbers of the staff who serve as key implementation points
of contact. These contacts must include the HQ Federal Program Manager,
Project Manager, or other managers and representatives with responsibilities
related to implementation. If the applicable team members are listed in the
Project Management Plan, reference the appropriate section within that
Appendix A NNSA SD 412.1A
APA-12 11-20-24
document.
HQ Programmatic Point of Contact List (Name, Title, Organization, Email,
Phone)
Name, Title
Section 9
Organization
XXX@nnsa.doe.gov
202-586-XXXX
HQ Programmatic Point of Contact List (Name, Title, Organization, Email,
Phone)
Name, Title
Organization
XXX@nnsa.doe.gov
202-586-XXXX
HQ Programmatic Point of Contact List (Name, Title, Organization, Email,
Phone)
Name, Title
Organization
XXX@nnsa.doe.gov
202-586-XXXX
mailto:XXX@nnsa.doe.gov
mailto:XXX@nnsa.doe.gov
mailto:XXX@nnsa.doe.gov
NNSA SD 412.1A Appendix A
11-20-24 APA-13
X. APPROVALS
The undersigned acknowledge that they have reviewed the <Program/Project
Name> Implementation Plan and agree with the information presented within
this document. Changes to this Program/Project Implementation Plan will be
coordinated with, and approved by, the undersigned, or their designated
representatives.
Signature: Date:
Print Name:
Title:
Role:
Signature: Date:
Print Name:
Title:
Role:
Signature: Date:
Print Name:
Title:
Role:
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 412.1A Appendix A
11-20-24 APA-15
APPENDIX A: KEY TERMS [OPTIONAL]
The following table provides definitions and explanations for terms and acronyms
relevant to the content presented within this document.
Term Definition
[Insert Term] <Provide definition of term and acronyms used in this
document.>
Appendix A NNSA SD 412.1A
APA-16 11-20-24
WORK AUTHORIZATION TEMPLATE (FIRM-FIXED-PRICE)
National Nuclear Security Administration (NNSA)
Office Name
Program/Project Name
Fiscal Year 20XX Work Authorization (Firm-Fixed-Price) [insert Work Authorization
title]
M&O Site/Contractor:
Work Authorization No: XXXXXX Revision No: 0X
Period of Performance:
Start Date Completion Date Revised Completion Date Date of Revision
Firm-Fixed-Price (FFP): $[insert negotiated dollar amount], inclusive of allowable,
allocable, and reasonable direct and indirect costs.
The following table provides the Not-to-Exceed funding amounts for the period of
performance.
Fund Type
Budget and
Reporting (B&R)
No.
(full 9-digit)
Not-to-Exceed Funding Amounts
Basic Previous Change or
Revision
Current
Authorization
$ $ $ $
Explanation of Funds:
[Include Explanation of Funds (EOF) table to identify the intended purposes of the funds.
The EOF may also be included as an attachment.]
Summary of Changes (For Work Authorization Revisions Only):
[Include a brief description of the changes (e.g., incremental funding, additional scope,
etc.).]
1.0 Scope
The Contractor must, in accordance with the terms of the prime Contract and this
Work Authorization (WA), provide the personnel, equipment, materials, supplies,
NNSA SD 412.1A Appendix A
11-20-24 APA-17
and services, (except as may be furnished by the Government) and otherwise do
all things necessary for, or incidental to execute the requirements described in
this WA to include meeting the specific milestones, and providing the specific
deliverables as described in the Implementation Plan, (which serves as the WA
Statement of Work) Attachment 1, of this Work Authorization, “Program Name
FY20XX Implementation Plan & Work Authorization” at [M&O Name]. This
Work Authorization is incorporated into the prime contract in accordance with
Department of Energy Acquisition Regulation (DEAR) 970.5211-1 “Work
Authorization.”
2.0 Changes
This Work Authorization and any subsequent changes must be executed in
accordance with the Federal Acquisition Regulation and all other contract terms
and conditions. The Government shall not be liable for any costs due to
Section 10
modifications, changes, or revisions to this WA from the requirements and prices
originally negotiated and agreed to without the express prior written approval of
such modification, change, or revision by the cognizant Contracting Officer.
Changes to the scope, schedule, or price as specified in the attached
Implementation Plan must be issued via a Work Authorization revision signed and
issued by the Contracting Officer as required by DEAR 970.5211-1, DOE Order
412.1A, and NNSA Supplemental Directive 412.1.
3.0 Agreements
Work must not commence until this Work Authorization is approved by the
Contracting Officer. The Contractor signature is a commitment that all
Integrated Safety Management, Integrated Safeguards and Security
Management, and quality assurance requirements have been met, and that
auditable records and files on this project are available for review.
Funding for this work will be obligated through a funding modification issued by
the Contracting Officer as specified in the most recent Approved Funding
Program (AFP).
4.0 DEAR 970.5232-4 Obligation of Funds, flow down to Work Authorizations
This contract clause is hereby flowed down to this Work Authorization. The
Contractor must segregate, allocate, and account for all costs incurred under this
specific WA. Such cost data must be made available to the Contracting Officer
Appendix A NNSA SD 412.1A
APA-18 11-20-24
upon request. In addition, the Contractor must notify the Contracting Officer, in
writing, when they recognize that they will exceed the fixed price by 10 percent,
insufficient actual and expected funding is available to continue work, or if their
actual funding is insufficient to operate until further expected funding.
Contractor
[Insert authorized individual
Title
Phone number
email]
[signature]
Date:
Contracting Officer
[insert name
Title
Phone number email]
[signature]
Date:
NNSA SD 412.1A Appendix A
11-20-24 APA-19
<PROGRAM/PROJECT NAME>
IMPLEMENTATION PLAN (Statement of Work)
Version <1.0>
<mm/dd/yyyy>
Appendix A NNSA SD 412.1A
APA-20 11-20-24
VERSION HISTORY
Version
#
Implemented
By
Revision
Date
Approved
By
Approval
Date
Reason
1.0 Author name mm/dd/yy name mm/dd/yy <reason>
NNSA SD 412.1A Appendix A
11-20-24 APA-21
Table of Contents
I. OVERVIEW [REQUIRED] ............................................................................................................................ 18
II. CORPORATE PROGRAM GOAL(S) [REQUIRED] ....................................................................................... 18
III. MAJOR ACTIVITIES [REQUIRED] ............................................................................................................... 18
IV. FUNDING GUIDANCE [REQUIRED] ........................................................................................................... 18
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED] ............................................................................. 19
VI. REPORTING REQUIREMENTS [REQUIRED] ............................................................................................... 20
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED] .............................................................. 20
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL] ..................................................................... 20
IX. POINTS OF CONTACT [REQUIRED] .......................................................................................................... 20
Section 11
XI. APPROVALS ............................................................................................................................................... 22
APPENDIX A: KEY TERMS [OPTIONAL] ............................................................................................................... 23
Appendix A NNSA SD 412.1A
APA-22 11-20-24
I. OVERVIEW [REQUIRED]
This section:
• Describes the purpose of the program/project and is sourced
by the most recent Congressional Budget Request; and
• Provides clear strategic alignment for the program/project to the most
current DOE and NNSA Strategic Plans by strategic goal and objective.
Optional: A table is optional in this subsection if the Work Authorization
(WA) supports multiple strategic objectives.
Required boilerplate language: “Specific work activities and scope
contained herein are consistent with: ( 1) the Department’s Base Table when
operating under a Continuing Resolution (CR); and (2) the final appropriation
or full-year CR once enacted.”
II. Corporate Program Goal(s) [Required]
This section is required by Government Performance and Results Act
Modernization Act of 2010. Information to include: Program Name,
Performance Measure/Indicator Title and Description, Fiscal Year Target and,
where applicable, End Point Target. Source: Most current Congressional
Budget Request performance table(s).
Program or Project
Name
Performance
Measure/Indicator Title
and Description
FY201X
Target
Endpoint Target
Required boilerplate language: “Preliminary targets are subject to change
based on a final, enacted budget.”
III. MAJOR ACTIVITIES [REQUIRED]
This section provides a description of the program/project major activities
that are not site-specific, but general program priorities during the period of
performance. These major activities are traceable to the most current
NNSA SD 412.1A Appendix A
11-20-24 APA-23
Congressional Budget Request.
IV. FUNDING GUIDANCE [REQUIRED]
This section describes Program and Fiscal Guidance such as, including the
negotiated Firm-Fixed-Price (FFP) and incremental Not-to-Exceed (NTE)
funding amounts for each M&O Contractor. The table below (or some
variation as directed by NA-PAS) must be completed for inclusion in the WA.
Program/OCL
President’s
FY20XX
Budget
Request
FY20XX CR
Operating
Target
FY20XX
Enacted/Full-Year
CR
Difference between
Request vs. Enacted
The initial NTE funding amount is equal to the Department’s Base Table and
should reflect 100 percent completion of the work activities as described in
Section V, Description of Planned Activities. Once an appropriation or full-year
CR is enacted the NTE funding amount must be updated to reflect the full-year
appropriation amount.
Required language: “To support the scope of work contained in this Work
Authorization (WA), funding will be distributed through the existing Approved
Funding Program (AFP) process described in DOE Order 130.1A and NNSA Policy
(NAP) 130.1C, or successor Order/NAP, as applicable. The AFP is adjusted on an
as-needed basis for the execution of congressionally approved programs,
projects, or activities. Specific work activities are authorized via this document,
with incremental funding plans for each site authorized via the AFP and obligated
via formal contract modification. The work contained herein will be funded on
an incremental basis. The Contractor is hereby authorized to expend up to the
Section 12
dollar amount indicated in the Program/Obligation Control Level (OCL) funding
table or as otherwise noted in the AFP allotment, whichever is less, and subject to
the availability of funds in the M&O contract.
Note: As indicated in Section 4.0, the Contractor is required to notify the
Contracting Officer in writing when they recognize that they will exceed the
estimated cost by 10%, insufficient actual and expected funding is available to
continue work, or if their actual funding is insufficient to operate until further
expected funding.”
Appendix A NNSA SD 412.1A
APA-24 11-20-24
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED]
This subsection provides the information referenced under the Scope Section
of the WA cover sheet and must be in sufficient detail to meet the
requirements of DEAR 970.5211-1. At a minimum, the planned activities
must replicate the Congressional Budget Request (budget narrative), be
written to the site-specific level, and include a general description of the work,
primary deliverables or performance expectations, a schedule of key
deliverables as shown in the table below, or a specific reference where the
work and FFP price information can be found.
Required language: “The purpose of this WA is to outline key work
requirements to be performed and to control individual work activities within
the scope of work. Contractors must not deviate from this plan without a
revised WA.”
Required language (for NNSA M&O Contracts only): “Annual
performance expectations for each M&O Contractor outlined in this
document may be considered by the Government in developing the
Contractor’s annual evaluation that is reported in the Contractor Performance
Assessment Reporting System. There will be no fee earned or paid on this
FFP WA.”
Note: The level of detail must provide sufficient information to the site to
enable mission execution at a level of performance needed to support the
appropriate CPEP evaluation or appraisal/assessment requirements.
Note: If the type of work is considered a level of effort (LOE), performance
criteria can be either quantitative or qualitative, yet it must be measurable. It
is appropriate to think of criteria as “entry” and “exit” criteria (i.e., the current
state of the planned activities and the expected state of the planned activities
at completion of the LOE) that supports mission accomplishment of
deliverables. Exit criteria should reflect what must be done to clearly
ascertain if the event has been successfully completed. The Implementation
Plan/Work Authorization includes the approval of work at designated site(s).
VI. Reporting Requirements [Required]
This subsection must contain sufficient detail on any applicable reporting
expectations or include reference to applicable document(s) with detailed
NNSA SD 412.1A Appendix A
11-20-24 APA-25
reporting expectations.
Examples:
• All sites (M&Os Contractor and non-M&Os Contractor sites) must
report cost data at the project level on or before the 10th day of the
month.
• Monthly performance reporting for completed activities is required on
or before the 5th workday of the month.
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED]
Required language: “The following documents are incorporated by reference:”
This subsection is in bullet format and should include key execution year
reference documents, which may include:
• X Strategic Plan (Month, Year)
• X Integrated Master Plan and Integrated Master Schedule
Section 13
• X Program Management Plan (PMP) (Month, Year, Version)
• Portfolio Work Plans (PWPs)
• Approved Funding Program Explanation of Changes (AFP) and
regular monthly financial plan adjustments.
• Other (references to detailed Statements of Work (SOW), work
proposals, project plans or similar documents).
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL]
This subsection can be used to outline programmatic risk associated with the
authorized scope. If needed, the Program should provide details here that
will help manage expectations to ensure accomplishment of mission scope
and deliverables absent of unanticipated barriers or reference a document
that discusses risk management (e.g., PMP).
IX. POINTS OF CONTACT [REQUIRED]
This subsection identifies responsible organization(s), titles, e-mail addresses, and
telephone numbers of the staff who serve as key implementation points of
contact. These contacts must include the HQ Federal Program Manager, Project
Manager, or other managers and representatives with responsibilities related to
implementation. If the applicable team members are listed in the Project
Appendix A NNSA SD 412.1A
APA-26 11-20-24
Management Plan, reference the appropriate section within that document.
HQ Programmatic Point of Contact List (Name, Title, Organization, Email, Phone)
Name, Title
Organization
XXX@nnsa.doe.gov
202-586-XXXX
HQ Programmatic Point of Contact List (Name, Title, Organization, Email, Phone)
Name, Title
Organization
XXX@nnsa.doe.gov
202-586-XXXX
HQ Programmatic Point of Contact List (Name, Title, Organization, Email, Phone)
Name, Title
Organization
XXX@nnsa.doe.gov
202-586-XXXX
mailto:XXX@nnsa.doe.gov
mailto:XXX@nnsa.doe.gov
mailto:XXX@nnsa.doe.gov
NNSA SD 412.1A Appendix A
11-20-24 APA-27
X. APPROVALS
The undersigned acknowledge that they have reviewed the
<Program/Project Name> Implementation Plan and agree with the
information presented within this document. Changes to this
Program/Project Implementation Plan will be coordinated with, and
approved by, the undersigned, or their designated representatives.
Signature: Date:
Print Name:
Title:
Role:
Signature: Date:
Print Name:
Title:
Role:
Signature: Date:
Print Name:
Title:
Role:
Appendix A NNSA SD 412.1A
APA-28 11-20-24
APPENDIX A: KEY TERMS [OPTIONAL]
The following table provides definitions and explanations for terms and acronyms
relevant to the content presented within this document.
Term Definition
[Insert Term] <Provide definition of term and acronyms used in this
document.>
NNSA SD 412.1A Appendix B
11-20-24 APB-1
APPENDIX B: WORK AUTHORIZATION PROCESS MAP
Work Authorization
Pr
og
ra
m
O
ff
ic
e
N
A
-M
B
Fi
el
d
O
ff
ic
e
N
A
-P
A
S
M
&
O
C
o
n
tr
a
ct
o
r
Provides base table
and budget
execution guidance
Develops and sends
initial IP and funding
changes to NA-MB.
Reviews program
AFP input and
changes. Inputs
values into BFADS.
Sends final AFP to
Field Office
NA-PAS randomly audits
WAs for completeness,
conformity. Provides
feedback to program and
NA-MB if changes are
needed
Confirms fund
availability. Sends to
M&O contractor for
signature
Reviews WA, signs
and returns to Field
CO
Signs/approves WA.
Distributes to
Program, NA-MB,
and NA-PAS mailbox
Archives WA
documents as
necessary
Completes WA and
issues with IP to
field CO and NA-PAS
WAEOC mailbox
Changes
Required
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 412.1A Appendix C
Section 14
11-20-24 APC-1
APPENDIX C: DEFINITIONS
a. Approved Funding Program (AFP). A process that distributes funding for obligation
through contract funding modifications.
b. Contracting Officer (CO). A person with the authority to enter into, administer, or
terminate contracts and make related determinations and findings within the limits of
their delegated authority.
c. Contracting Officer’s Representative (COR). A Federal employee designated in writing by
the Contracting Officer to assist in the technical monitoring or administration of a contract.
d. Implementation Plan (IP). The program document attached to the work authorization that
describes the scope of work to be performed and serves as the statement of work for the
work authorization.
e. Technical Direction. Written direction to the Contractor within the scope of work, estimated
cost, and schedule of the work authorization by an authorized COR.
f. Work Authorization (WA). The document, approved by a CO, that describes the scope of
work, estimated cost, and schedule of work activities performed within the larger contract
scope of work. Work authorizations must be issued prior to the commencement of the work
and incurrence of any costs.
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 412.1A Appendix D
11-20-24 APD-1
APPENDIX D: REFERENCES
a. Regulatory Requirement DEAR 970.1170-1, Work Authorization
b. Contract Clause DEAR 970.5211-1, Work Authorization
c. Department of Energy Order 412.1, Work Authorization System, current version.
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 412.1A Appendix E
11-20-24 APE-1
APPENDIX E: ACRONYMS/ABBREVIATIONS
a. AFP Approved Funding Program
b. B&R Budget and Report
c. BFAD Budget Formulation and Distribution System
d. CO Contracting Officer
e. COR Contracting Officer’s Representative
f. CR Continuing Resolution
g. DOE Department of Energy
h. FY Fiscal Year
i. FYNSP Future Years Nuclear Security Program
j. GPRA Government Performance and Results Act
k. IP Implementation Plan
l. ISM Integrated Safety Management
m. ISMM Integrated Safeguards and Security Management
n. NA-MB Management and Budget
o. NA-PAS Partnership and Acquisition Services
p. NAP NNSA Policy
q. NNSA National Nuclear Security Administration
r. OCL Obligation Control Level
s. OPI Office of Primary Interest
t. SD Supplemental Directive
u. SIB Strategic Initiatives Branch
v. STRIPES Strategic Integrated Procurement Enterprise System
w. WA Work Authorization
x. WAEOC Work Authorization Expense Object Coding
1. PURPOSE.
2. CANCELLATION.
3. APPLICABILITY
Untitled
1. PURPOSE. To supplement Department of Energy (DOE) Order 412.1A, Work Authorization System, for the purpose of establishing procedures to administer National Nuclear Security Administration (NNSA)-sponsored work authorizations (WA) with greater efficiency.
2. CANCELLATION. NNSA SD 412.1, Work Authorizations, Dated 1-18-17.
3. APPLICABILITY.
4. SUMMARY OF CHANGES. Implements requirements for storing executed WAs and a schedule for completing draft WAs. This revision also updates responsibilities to reflect organizational changes, incorporates changes to clarify the content of implementation plans, and includes editorial changes for clarity.
5. BACKGROUND. Department of Energy Acquisition Regulation (DEAR) 970.1170-1 states:
6. REQUIREMENTS.
7. RESPONSIBILITIES.
8. DEFINITIONS. See Appendix C.
9. REFERENCES. See Appendix D.
10. CONTACT. Office of Partnership and Acquisition Services, 202-586-4921.
APPENDIX A: WORK AUTHORIZATION TEMPLATES
I. OVERVIEW [REQUIRED]
II. CORPORATE PROGRAM GOAL(S) [REQUIRED]
III. MAJOR ACTIVITIES [REQUIRED]
IV. FUNDING GUIDANCE [REQUIRED]
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED]
VI. REPORTING REQUIREMENTS [REQUIRED]
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED]
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL]
IX. POINTS OF CONTACT [REQUIRED]
X. APPROVALS
APPENDIX A: KEY TERMS [OPTIONAL]
WORK AUTHORIZATION TEMPLATE (FIRM-FIXED-PRICE)
Section 15
Untitled
1. PURPOSE. To supplement Department of Energy (DOE) Order 412.1A, Work Authorization System, for the purpose of establishing procedures to administer National Nuclear Security Administration (NNSA)-sponsored work authorizations (WA) with greater efficiency.
a. This Supplemental Directive (SD):
b. Any inconsistency in this SD must be resolved in the following order of priority:
2. CANCELLATION. NNSA SD 412.1, Work Authorizations, Dated 1-18-17.
3. APPLICABILITY.
a. Federal. The provisions of this directive apply to all NNSA programs and NNSA-funded work.
b. Contractors. Does not apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by Executive Order 12344, codified at 50 United States Code (U.S.C.) sections 2406 and 2511, and to ensure consistency throughout the joint Navy/DOE Naval Nuclear Propulsion Program, the Deputy Administrator for Naval Reactors (Director) will implement and oversee requirements and practices pertaining to this SD for activities under the Director’s cognizance, as deemed appropriate.
d. Exemption. Work involving Strategic Partnership Projects; and services, products, or materials regularly produced for sale at scheduled rates under DOE programs (e.g., routine irradiation services, radioisotopes, production or transmission of electricity).
4. SUMMARY OF CHANGES. Implements requirements for storing executed WAs and a schedule for completing draft WAs. This revision also updates responsibilities to reflect organizational changes, incorporates changes to clarify the content of implementation plans, and includes editorial changes for clarity.
5. BACKGROUND. Department of Energy Acquisition Regulation (DEAR) 970.1170-1 states:
6. REQUIREMENTS.
a. In accordance with DEAR 970.5211-1, activities must not be authorized nor costs incurred prior to the Contracting Officer (CO) issuance of a WA or direction concerning continuation of activities of the contract. Therefore, WAs must be generated and issued to the Contractor before the start of the fiscal year (FY) or as early in the FY as possible, subject to programmatic needs.
b. Initial WAs must be submitted to the field offices for review on or before August 15 of the preceding FY. The program office must communicate any delays and extenuating circumstances to the field office if this date will not be met. The program office and the field office will determine if an interim WA is needed until the final WA can be executed.
c. If one or more parties do not approve of the scope of work, schedule, or estimated cost requirements identified in the WA, the parties must find a resolution. In the event a resolution cannot be reached, the CO has the ultimate authority to resolve the conflict and may issue WAs unilaterally in accordance with DEAR 970.5211-1.
d. In the case of new work requirements, or changes during the course of the FY, a WA must be generated or revised as soon as the requirement is identified, accepted by the Contractor(s), and approved by the CO prior to the commencement of the work and incurrence of any cost. All changes to a WA must be made using a formal change control process that is the same as the generation and distribution process of the initial WA.
e. If operating under a Continuing Resolution (CR) at the start of the FY, the WA must be issued to align with and not exceed the Department’s Base Table. Within 30 calendar days of final appropriation or full-year CR enactment, the WA must be updated to reflect any necessary change(s) in scope, schedule, or estimated cost (price if a fixed price WA) to align with the signed enactment.
7. RESPONSIBILITIES.
a. Office of Partnership and Acquisition Services, Strategic Initiatives Branch.
b. Program Office.
c. Management and Budget (NA-MB).
d. Contracting Officers.
Section 16
8. DEFINITIONS. See Appendix C.
9. REFERENCES. See Appendix D.
10. CONTACT. Office of Partnership and Acquisition Services, 202-586-4921.
APPENDIX A: WORK AUTHORIZATION TEMPLATES
WORK AUTHORIZATION TEMPLATE (COST REIMBURSEMENT)
1.0 Scope
2.0 Changes
3.0 Agreements
4.0 DEAR 970.5232-4 Obligation of Funds, flow down to Work Authorizations
IMPLEMENTATION PLAN (Statement of Work)
VERSION HISTORY
Table of Contents
I. OVERVIEW [REQUIRED]
II. CORPORATE PROGRAM GOAL(S) [REQUIRED]
III. MAJOR ACTIVITIES [REQUIRED]
IV. FUNDING GUIDANCE [REQUIRED]
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED]
VI. REPORTING REQUIREMENTS [REQUIRED]
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED]
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL]
IX. POINTS OF CONTACT [REQUIRED]
X. APPROVALS
APPENDIX A: KEY TERMS [OPTIONAL]
WORK AUTHORIZATION TEMPLATE (FIRM-FIXED-PRICE)
1.0 Scope
2.0 Changes
3.0 Agreements
4.0 DEAR 970.5232-4 Obligation of Funds, flow down to Work Authorizations
IMPLEMENTATION PLAN (Statement of Work)
VERSION HISTORY
Table of Contents
I. OVERVIEW [REQUIRED]
II. Corporate Program Goal(s) [Required]
III. MAJOR ACTIVITIES [REQUIRED]
IV. FUNDING GUIDANCE [REQUIRED]
V. DESCRIPTION OF PLANNED ACTIVITIES [REQUIRED]
VI. Reporting Requirements [Required]
VII. KEY EXECUTION YEAR REFERENCE DOCUMENTS [REQUIRED]
VIII. MAJOR RISKS AND HANDLING STRATEGIES [OPTIONAL]
X. APPROVALS
APPENDIX A: KEY TERMS [OPTIONAL]
APPENDIX B: WORK AUTHORIZATION PROCESS MAP
APPENDIX C: DEFINITIONS
APPENDIX D: REFERENCES
APPENDIX E: ACRONYMS/ABBREVIATIONS