SD 413.3-6, Energy Systems Acquisition Advisory Board Equivalent Process
To define the National Nuclear Security Administration (NNSA) process for initiating Departmental Energy System Acquisition Advisory Board (ESAAB) requests through the pre-ESAAB board review meeting for capital asset project decisions within the purview of NNSA. Cancels BOP 413.8, dated 9-30-2016.
Associated DOE Directive:
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
SUPPLEMENTAL DIRECTIVE
Approved: 03-01-22
Certification Due: 03-01-25
ENERGY SYSTEMS ACQUISITION
ADVISORY BOARD EQUIVALENT
PROCESS
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Acquisition and Project Management
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Enterprise Project Management
https://directives.nnsa.doe.gov
printed copies are uncontrolled
NNSA SD 413.3-6
https://directives.nnsa.doe.gov/
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 413.3-6 1
03-01-22
ENERGY SYSTEMS ACQUISITION ADVISORY BOARD EQUIVALENT PROCESS
1. PURPOSE. To define the National Nuclear Security Administration (NNSA) process for
initiating Departmental Energy System Acquisition Advisory Board (ESAAB) requests
through the pre-ESAAB board review meeting for capital asset project decisions within
the purview of NNSA. This Supplemental Directive (SD) describes NNSA roles,
responsibilities, and authorities as they relate to the NNSA Energy System Acquisition
Advisory Board Equivalent (ESAAB-E) process in accordance with Department of
Energy (DOE) Order (O) 413.3B Chg. 6 (LtdChg), Program and Project Management
for the Acquisition of Capital Assets, or successor (hereinafter referred to as DOE O
413.3B).
2. AUTHORITY. DOE O 413.3B Chg. 6 (LtdChg), Program and Project Management for
the Acquisition of Capital Assets.
3. CANCELLATION. BOP 413.8, Energy System Acquisition Advisory Board Equivalent
(ESAAB-E) Process, dated 09/30/2016.
4. APPLICABILITY.
a. Federal. This SD applies to all NNSA Federal organizations.
b. Contractors. This SD does not apply to contractors.
c. Equivalencies/Exemptions.
(1) Equivalency. In accordance with the responsibilities and authorities
assigned by Executive Order 12344, codified at 50 United States Code
(U.S.C.) sections 2406 and 2511, and to ensure consistency throughout the
joint Navy/DOE Naval Nuclear Propulsion Program, the Deputy
Administrator for Naval Reactors (Director) will implement and oversee
requirements and practices pertaining to this Directive for activities under
the Director's cognizance, as deemed appropriate.
(2) Exemption. None.
5. SUMMARY OF CHANGES.
a. Converted BOP 413.8 into this SD.
b. Incorporates updates to DOE O 413.3B, including a change in the applicability
threshold.
c. Incorporates a change to the Minor Construction/line-item threshold.
2 NNSA SD 413.3-6
03-01-22
6. BACKGROUND.
The NNSA ESAAB-E process pertains to all non-Major System line-item capital asset
projects and Major Items of Equipment (MIE) that are constructed for NNSA, or
managed by NNSA personnel on behalf of other government agencies that have an
estimated total project cost (TPC) that exceeds the minor construction and line-item
applicability thresholds, but is less than $750 million (M).
DOE O 413.3B directs the establishment of an advisory board process to conduct
functions identical to those performed by the ESAAB for Major System projects. For
NNSA, this is the ESAAB-E process.
a. The ESAAB-E is an NNSA-level board comprising senior-level experts and
stakeholders who serve as advisors to the Project Management Executive (PME)
in making decisions associated with planning, authorizing, and executing non-
Major System capital asset projects, defined as projects with TPC (and cost
ranges) less than $750M. ESAAB-E members may be selected from within the
PME's organization. The Office of Acquisition and Project Management (NA-
APM) conducts Pre-ESAAB-E and ESAAB-E reviews for non-Major System
capital asset projects.
Section 2
b. The ESAAB-E process improves project and acquisition planning and execution
through a disciplined decision-making approach that incorporates input, insight,
and recommendations on key issues from functional experts, stakeholders, and
senior-level leaders.
c. The DOE Office of Project Management (PM) will not be a Board member for
projects with a TPC less than $750M, but must be invited to attend the Advisory
Board meetings.
7. REQUIREMENTS.
a. The ESAAB-E Process described in Appendix A must be followed.
b. NNSA must establish an advisory board or the ESAAB-E for non-Major System
capital asset projects (defined as projects under $750M) as required by DOE O
413.3B.
c. An ESAAB-E must occur at every Critical Decision (CD) in the life of a non-
Major System capital asset project. A Departmental ESAAB is required for non-
Major System projects when an increase to the cost baseline occurs upon the
excess of the lesser of $100M or 50% (cumulative) of the original CD-2.
8. RESPONSIBILITIES.
a. Administrator (NA-1). Acts as PME on projects in accordance with Figure 1,
Appendix A.
b. Associate Administrator for Acquisition and Project Management (NA-APM-1).
NNSA SD 413.3-6 3
03-01-22
(1) Conducts the NA-APM-1 Dry Run with the Federal Project Director
(FPD) or equivalent, providing comments and recommendations.
(2) Chairs pre-ESAAB-E meetings to decide the approach and strategy for
moving a capital asset project forward in the process. At ESAAB-E
meetings advocates for the approach and strategy that the pre-ESAAB-E
concurred upon.
(3) Coordinates all ESAAB-E briefs with the PME.
(4) Acts as the principal advisor to the PME in each ESAAB-E meeting.
c. Project Management Executive.
(1) Makes decisions for capital asset project CDs and Baseline Change
Proposals (BCPs) that change the project’s TPC, or CD-4 date, except
CD-0, which cannot be delegated below the Program Secretarial Officer
(PSO) level.
(2) Chairs ESAAB-E meetings and solicits advice from ESAAB-E members.
(3) Approves the cost, scope, and schedule for the project at each CD and
BCP that change the project baseline.
d. Federal Project Director (FPD) or equivalent for CD-0.
(1) Serves as the Integrated Project Team (IPT) lead and spokesperson at pre-
ESAAB-E and ESAAB-E meetings. Provides comments on draft meeting
minutes prepared by the ESAAB-E Secretariat and the project’s
Headquarters Project Manager (HQPM).
(2) Supplies key CD documents requiring PME approval in advance of the
NA-APM-1 Dry Run so all HQ concurrences can be achieved prior to the
NA-APM-1 Dry Run, with the exception being the CD Decision Memo,
which is generated by the project’s HQPM, but is not finalized until the
project nears the ESAAB-E event date.
e. Integrated Project Team Members. Along with the team lead, provide comments
on draft meeting minutes prepared by the ESAAB-E Secretariat and the HQPM.
f. Contracting Officer (CO). Participates as a member of the project’s IPT in
support of ESAAB-E efforts.
g. Subject Matter Experts (SMEs). Participate in IPT meetings as well as ESAAB-E
related meetings and provide objective analyses and assessments when called
upon by an FPD, project stakeholder, board member, or PME.
4 NNSA SD 413.3-6
03-01-22
h. Pre-ESAAB-E Members.
(1) Serve as representatives of the organizational principals identified in
Appendix C, who as functional experts, stakeholders, or senior-level
managers support the ESAAB-E process and project.
Section 3
(2) Advise Pre-ESAAB-E chairpersons and provide insight, assessments, and
recommendations in their areas of expertise pertaining to execution
strategies.
(3) Brief their ESAAB-E organization principal on any issues or concerns
from the Pre-ESAAB-E to prepare for the upcoming ESAAB-E.
i. ESAAB-E Members. Advise the PME in matters pertaining to execution
strategies at each CD.
j. ESAAB-E Secretariat.
(1) Provides administrative support to the FPD and the IPT in preparing for
and conducting Dry Runs, pre-ESAAB-E meetings, and ESAAB-E
meetings.
(2) Schedules Dry Runs, pre-ESAAB-E meetings, and ESAAB-E
meetings and ensures participation of appropriate representatives.
(3) Conducts the Office of Enterprise Project Management (NA-APM-
20) Dry Run with the FPD or equivalent. Invites the HQPM, CO,
Program Office Representative (POR), and if the project is over
$100M, the DOE PM analyst.
(4) Distributes, with the assistance of the FPD and HQPM,
presentation materials as a read-ahead in pre-ESAAB-E and
ESAAB-E meetings.
(5) Generates and distributes, with the assistance of the FPD and
HQPM, minutes, joint comments, recommendations, and action
items for Dry Runs, pre-ESAAB-E and ESAAB-E meetings.
(6) For an NA-1 ESAAB-E Meeting coordinates with the HQPM to
take meeting minutes. (The ESAAB-E Secretariat is not in
attendance at the NA-1 ESAAB-E Meetings.)
k. Headquarters Project Managers.
(1) Work with the FPD/IPT and the ESAAB-E Secretariat to plan and
schedule the various ESAAB-E related events.
NNSA SD 413.3-6 5
03-01-22
(2) Support the generation and review of primary CD documents needing
Headquarters’ concurrence prior to PME’s signature. Start drafting the
CD Decision Memo before the NA-APM-20 Dry Run. Provide value with
clarification comments and make the documents more concise, such as
referencing ancillary documents. Submit related documents jointly to
economize the review process.
(3) Review draft ESAAB-E presentations as a project specialist, and generate
the CD Decision Memo with the assistance of the FPD prior to the
ESAAB-E.
(4) Assist in the generation of draft pre-ESAAB-E and ESAAB-E meeting
minutes.
(5) Invite the DOE Office of Project Management to attend the Advisory
Board meetings.
9. DEFINITIONS. See Appendix D.
10. ACRONYMS. See Appendix E.
11. REFERENCES. See Appendix F.
12. CONTACT. Office of Enterprise Project Management, NA-APM-20, (202) 586-9814.
BY ORDER OF THE ADMINISTRATOR:
Jill Hruby
Administrator
Appendixes:
A. NNSA Energy Systems Acquisition Advisory Board Equivalent (ESAAB-E) Process
(ESAAB-E Process Flow Diagram included).
B. ESAAB-E Request Form.
C. Pre-Energy Systems Acquisitions Advisory Board-Equivalent (PRE-ESAAB-E),
ESAAB-Equivalent, and ESAAB-E Members and Represented Organizations. (Non-
Major Systems Projects, i.e., Below $750 Million [M]).
D. Definitions.
E. Acronyms/Abbreviations.
F. References.
NNSA SD 413.3-6 Appendix A
03-01-22 APA-1
APPENDIX A: NATIONAL NUCLEAR SECURITY ADMINISTRATION (NNSA)
ENERGY SYSTEMS ACQUISITION ADVISORY BOARD EQUIVALENT (ESAAB-E)
PROCESS
1. BACKGROUND. Department of Energy (DOE) Order (O) 413.3B, Program and
Project Management for the Acquisition of Capital Assets, provides latitude for a
streamlined ESAAB process. The ESAAB-E process has similar latitude (e.g., not
convening the board for non-controversial, low risk projects). Paper ESAAB-E requests
are coordinated with the Project Management Executive (PME) by the Office of
Enterprise Project Management (NA-APM-20) ESAAB-E Secretariat. If the PME
approves the Paper ESAAB-E process, comments and concurrences related to the project
are to be processed through the Electronic Document Online Correspondence and
Concurrence System (eDOCS).
Section 4
2. PROCESS.
a. DOE and NNSA Thresholds and Approval Authority.
(1) DOE and NNSA thresholds and approval authority, as specified in DOE O
413.3, are shown in Figure 1 below, (NNSA ESAAB-E requirements and
related documents for Critical Decision CD-0, Approve Mission Need,
through CD-4, Approve Start of Operations or Project Completion, can be
found in DOE O 413.3B, Appendix A, Tables 2.0-2.4.)
Critical
Decision
Authority
Total Project Cost Thresholds
Deputy
Secretary
≥ $750M
(or any project on an exception basis when designated by the Deputy Secretary)
Further delegation is allowed.
Under
Secretaries
≥ $100M and < $750M
(or any project on an exception basis when designated by the Under Secretaries)
Further delegation is allowed.
Program
Secretarial
Officer
> Minor Construction and Line-item applicability thresholds < $100M
Further delegation is allowed.
Figure 1: Critical Decision Authority Thresholds
(2) Following from the DOE O 413.3B authority thresholds, the
Administrator is the PME for NNSA capital asset projects with estimated
total project cost or cost ranges greater than $100 Million (M) and less
Appendix A NNSA SD 413.3-6
APA-2 03-01-22
than $750M but may delegate PME authority. When requesting a
delegation of authority, consider the following:
(a) Is the project low-risk and non-controversial, e.g., standard
commercial type facilities or capital equipment?
(b) Is Headquarters (HQ) coordination (due to, e.g., safety or
environmental issues or funding uncertainty), expected to be
prolonged?
(c) Has the proposed delegate served as PME on successfully
completed projects of similar size and complexity in the past?
b. NNSA ESAAB-E Requests.
(1) The Program Office Representative (POR) and the Federal Project
Director (FPD) (or equivalent) must submit an ESAAB-Equivalent
Request to the ESAAB-E Secretariat at least a month before the project’s
Dry Run by NA-APM-20. The request form identifies primary project
members and additional attendees within the project team. It also
identifies the weeks that the pre-ESAAB-E and the ESAAB-E are
requested. The ESAAB-E Request form is signed by both the POR and
FPD. The email address to request these documents is
ESAAB- E@nnsa.doe.gov. At this time, the POR and FPD should also
request the most current ESAAB-E Presentation Template for the
applicable CD or Baseline Change Proposal (BCP).
(2) Immediately after an Independent Project Review, the project’s
Headquarters Project Manager (HQPM) contacts the FPD or equivalent
and requests the primary documents that will require HQ review and
comment. The HQPM and the FPD must work jointly to finalize these
documents. This process is critical and will affect the time to schedule
ESAAB-E related briefings. The project cannot move forward through the
ESAAB-E process for an Associate Administrator for Acquisition and
Project Management (APM-1) Dry Run until all primary documents are
signed.
c. Dry Runs and PRE-ESAAB-E Meetings.
(1) The Office of Acquisition and Project Management (NA-APM) Dry Runs.
(a) NA-APM Dry Runs are an essential part of the ESAAB-E process
to refine the presentation, ensure it is comprehensive, and ensure
the presentation’s message is clear and concise. Close and early
coordination between the FPD, HQPM, and ESAAB-E Secretariat
is necessary. The FPD is responsible for generating the ESAAB-E
presentations with the assistance of the Integrated Project Team
Section 5
mailto:ESAAB-E@nnsa.doe.gov
mailto:ESAAB-E@nnsa.doe.gov
NNSA SD 413.3-6 Appendix A
03-01-22 APA-3
(IPT). The project HQPM and the ESAAB-E Secretariat
participate early in the process, providing recommendations and
comments on the ESAAB-E Presentation. The ESAAB-E
Secretariat maintains slide presentation templates for each required
briefing (CD-0 through CD-4). The ESAAB-E Secretariat
(ESAAB-E@nnsa.doe.gov) can provide a recent example of an
ESAAB-E presentation for the subject CD. Each CD template is
also available on the NA-APM-20 Max.gov site at:
https://community.max.gov/display/DOEExternal/NA-APM-
20+Approval+Package+Templates
(b) A minimum of 1 month prior to a CD ESAAB-E, the FPD or
equivalent must use the Request Form for an NNSA ESAAB-E
Review to begin the scheduling process. Prior to the Dry Run, the
HQPM begins drafting the Decision Memo in coordination with
the FPD. The draft Decision Memo is entered into the formal
correspondence system for routing to various NA-APM levels for
formal review.
(c) An initial NA-APM-20 Dry Run is held with the POR, FPD or
equivalent, the project’s HQPM, and the Contracting Officer (CO).
For CD-0 Dry Runs, the POR or designee makes the presentation,
for other CDs or BCPs the FPD or designee present. The DOE
Office of Project Management (DOE-PM) analyst is included for
projects over $100M. The FPD must provide any read-ahead
materials, including the ESAAB-E presentation, at least 5 business
days before the Dry Run. After the Dry Run, action items are
provided by the ESAAB-E Secretariat to the FPD and IPT team for
execution.
(d) An NA-APM-1 Dry Run is also performed with the FPD, NA-
APM-20 Director, and the project HQPM. The NA-APM-1 Dry
Run will not be scheduled until all key CD documents required for
PME approval are fully concurred upon, except for the CD
Decision Memo. The NA-APM-1 Dry Run is a limited access
session allowing the FPD to Dry Run the CD presentation as if it
was being presented to the PME. After the Dry Run, NA-APM-1
makes the decision as to whether the project is ready to proceed, or
whether additional actions are required.
(2) Pre-ESAAB-Equivalent Meetings.
(a) Prior to an ESAAB-E, a pre-ESAAB-E meeting must be held for
all NNSA capital asset projects unless waived, in writing or via
email, by the ESAAB-E Secretariat or designee.
mailto:ESAAB-E@nnsa.doe.gov
https://community.max.gov/display/DOEExternal/NA-APM-20%2BApproval%2BPackage%2BTemplates
https://community.max.gov/display/DOEExternal/NA-APM-20%2BApproval%2BPackage%2BTemplates
Appendix A NNSA SD 413.3-6
APA-4 03-01-22
(b) The FPD or designee, with the assistance of the IPT, must
organize, present, and facilitate the pre-ESAAB-E at every CD.
An exception is at CD-0, when a field office individual, or a POR
can perform these tasks because an FPD is not assigned. The
ESAAB-E Secretariat generates a listing of pre-ESAAB-E invitees.
Each pre-ESAAB-E meeting is co-chaired by NA-APM-1 and the
POR. Board members must include representatives of the
principals from the organizations listed in Appendix C, who serve
as advisors to the chairpersons and to the POR. Contractor
participation in pre-ESAAB-E meetings should be limited to
subjects where they have specific expertise to offer, and only with
concurrence of the chairpersons. The FPD or designee, with the
assistance of the IPT, provides and distributes required pre-
ESAAB-E Review Materials.
Section 6
(c) All required CD documents must be provided to NA-APM and
distributed to the pre-ESAAB-E members.
(d) For a given CD, these documents can be found in the requirements
section of the related pre-ESAAB-E Presentation Template and can
be found on the APM-20 Max.gov site under the “References,
Templates and Checklists” section, “Presentation and Briefings”
sub-section.
(e) For a complete set of CD Requirements please refer to DOE O
413.3B Tables 2.0 through 2.4.
(3) Pre-ESAAB-E Review Meeting and Document Meeting Outcomes.
(a) The ESAAB-E Secretariat and HQPM collect and share pre-
ESAAB-E action items with the FPD and IPT members within 2
business days. Draft meeting minutes are shared with pre-
ESAAB-E attendees within 5 business days of the pre-ESAAB-E
meeting to clarify content. The meeting minutes are then provided
to NA-APM-20 for final review and comment. The ESAAB-E
Secretariat submits the pre-ESAAB-E meeting minutes for
inclusion in the project’s Max.gov folder. The meeting minutes
are also to be stored in the project’s record repository. NA-APM,
with the input of board members, including the POR, must concur
or non-concur on the critical decision information to be presented
to the PME at the ESAAB-E, or on the need for further work to
resolve open issues before seeking PME approval.
(b) If necessary, the ESAAB-E Secretariat schedules a follow-up
meeting to close issues and obtain final concurrence.
NNSA SD 413.3-6 Appendix A
03-01-22 APA-5
(c) If the project is under $100M, and with the concurrence of the
chairpersons, the ESAAB-E Secretariat proceeds with arranging
the ESAAB-E meeting. The pre-ESAAB-E chairpersons
recommend the agreed upon approach or strategy at the ESAAB-E.
(d) If subsequent events lead to a significant divergence from the
project’s acquisition or execution strategy, the FPD then obtains
PME approval using the process described herein, including
convening another pre-ESAAB-E meeting. The HQPM prepares
an amended CD Decision Memorandum for internal review and
approval in advance of the pre-ESAAB-E. In the CD Decision
Memo, the final ESAAB-E date might be to be determined (TBD),
especially if the PME is at the Administrator (NA-1) level, as NA-
1’s schedule is subject to change based on arising priorities. After
the ESAAB-E, the IPT amends project documentation to
incorporate any PME-approved changes.
(4) ESAAB-E Meetings.
(a) Invite Attendees.
(1) The ESAAB-E Secretariat generates a proposed list of the
ESAAB-E invitees, which is reviewed and approved by
NA-APM-1. The PME chairs the ESAAB-E board
meeting. The principals of the organizations listed in
Appendix C serve on the board as advisors. Board
membership is tailored based on project complexity and
nature.
(2) The ESAAB-E members provide advice and
recommendations regarding project CDs. The
implementing documentation composition of each
Advisory Board along with meeting agendas and minutes
will be provided to the PM.
(b) Coordinate ESAAB-E Meeting.
The strategy and approach agreed upon at each pre-ESAAB-E
meeting are presented by the FPD or equivalent to the PME for
approval at the ESAAB-E. The FPD, with the assistance of the
IPT, organizes, presents, and facilitates the ESAAB-E board
meeting at every CD.
(c) Update Presentation.
The FPD, or equivalent for CD-0, prepares updated presentations
incorporating changes from pre-ESAAB-E meetings as necessary
Appendix A NNSA SD 413.3-6
APA-6 03-01-22
Section 7
and provides read-ahead materials to the ESAAB-E Secretariat for
distribution not more than 5 business days before the meeting.
Presentations for ESAAB-E should mirror those of the pre-
ESAAB-E meetings, updated as necessary for action items from
the pre-ESAAB-E meeting.
(d) Provide/Distribute Required Read-Ahead Materials.
(1) The FPD, or equivalent for CD-0, is responsible for
providing the board with the necessary information and
analyses to assist the PME in making informed decisions
throughout a project’s lifecycle. CD documents requiring
PME approval are to be provided to the PME far enough in
advance such that the PME and staff have ample time to
review them. The more senior the level of the PME, the
more lead time is needed to secure concurrences prior to
the ESAAB-E meeting. An NA-1 ESAAB-E is an example
of briefings that indicate that extra lead time will be
required.
(e) Provide/Distribute Required ESAAB-E Review Materials.
The ESAAB-E Secretariat, in conjunction with the FPD, or
equivalent, and HQPM, distributes the review materials. Program
and functional offices (i.e., organizations represented on the
ESAAB-E) are encouraged to work closely with these three
entities to request specific documents and reports. If additional
information is needed, such as Pre-ESAAB-E Meeting Minutes,
contact the ESAAB-E Secretariat at ESAAB-E@nnsa.doe.gov.
(f) Conduct ESAAB-E and Document Meeting Outcomes.
(1) The PME, with input from board members, approves the
proposed approach and strategy for moving forward to the
next CD, or requires further work to resolve open issues
before approving. If necessary, a follow-up meeting occurs
to close issues and obtain final approval. The ESAAB-E
Secretariat ensures the CD Decision Memorandum is
available for PME signature at the ESAAB-E.
(2) Meeting minutes, including open items, are taken by the
ESAAB-E Secretariat and the HQPM. The ESAAB-E
Secretariat and the HQPM collect and share action items
with the FPD and IPT members within 2 business days.
Draft meeting minutes are shared with ESAAB-E attendees
within 2 to 3 additional business days to clarify comments.
The meeting minutes are then provided to NA-APM-20 for
mailto:ESAAB-E@nnsa.doe.gov
NNSA SD 413.3-6 Appendix A
03-01-22 APA-7
final review and comment. The ESAAB-E Secretariat
uploads the ESAAB-E meeting minutes into the project’s
Max.gov folder and shares them with the FPD for inclusion
in the project’s repository.
(3) The FPD, or equivalent, must ensure CDs are documented
in project and contract files. FPDs are to note that required
CD documents must be sent to DOE-PM per DOE O
413.3B.
(4) The HQPM must ensure that CD documentation is
uploaded to the NA-APM-20 Max.gov website for the
applicable project.
Appendix A NNSA SD 413.3-6
APA-8 03-01-22
APPENDIX A: FIGURE 2 - ESAAB-E PROCESS FLOW DIAGRAM
NNSA SD 413.3-6 Appendix B
03-01-22 APB-1
APPENDIX B: ENERGY SYSTEMS ACQUISITIONS ADVISORY BOARD
EQUIVALENT (ESAAB-E) REQUEST FORM
The ESAAB-E Request Form is available for download and use from the NA-APM-20 Max.gov site.
https://community.max.gov/download/attachments/1352860962/ESAAB-E_Request_Form_.doc?api=v2
Appendix B NNSA SD 413.3-6
APB-2 03-01-22
NNSA SD 413.3-6 Appendix C
03-01-22 APC-1
APPENDIX C: PRE-ENERGY SYSTEMS ACQUISITION ADVISORY BOARD-
EQUIVALENT (PRE-ESAAB-E), ESAAB-EQUIVALENT, AND ESAAB-E MEMBERS
AND REPRESENTED ORGANIZATIONS (NON-MAJOR SYSTEMS PROJECTS, I.E.,
Section 8
BELOW $750 MILLION (M))
• Associate Administrator for Acquisition and Project Management (NA-APM-1) *
• Director, Office of Enterprise Project Management (NA-APM-20)/NNSA ESAAB-E
Secretariat *
• Federal Project Director (FPD) or equivalent *
• Head of the Contracting Activity (NA-APM-10)
• Project Contracting Officer *
• Small Business Administration Representative
• Headquarters Project Manager (HQPM) (NA-APM-20)
• Director, Office of Project Analysis, Oversight and Review (NA-APM-1.1)
• Program Office Representative *
• Field Office Manager
• Office of Management and Budget (NA-MB) *
• Office of Defense Nuclear Security (NA-70) *
• Office of Safety (NA-51) *
• Management & Operating contractors and Enterprise Construction Management Services
contractors (as authorized to attend by a chairperson through a request to the FPD to HQPM
via the ESAAB-E Secretariat)
• Office of General Counsel (NA-GC) *
• Office of External Affairs (NA-EA)
• Department of Energy's Office of Project Management Oversight and Assessments/PMOA
(DOE-PM)
• Office of Cost Estimating and Program Evaluation (CEPE) (NA-1.3) *
• Office of the Associate Administrator for Information Management and Chief Information
Officer (NA-IM) *
* Required ESAAB-E members and organizations.
The required board members may be tailored based on the complexity and nature of the project.
NNSA SD 413.3-6 Appendix D
03-01-22 APD-1
APPENDIX D: DEFINITIONS
Any terms used in this Supplemental Directive (SD) coincide in meaning to terms defined by
DOE O 413.3B, Program and Project Management for the Acquisition of Capital Assets.
Additional terms used in this SD are defined below.
a. Energy Systems Acquisition Advisory Board (ESAAB). The ESAAB process improves
project and acquisition planning and execution through a disciplined decision-making
approach and incorporating input, insight, and recommendations on key issues from
functional experts, stakeholders, and senior-level leaders. The ESAAB is a Department-
level (i.e., Department of Energy (DOE) board comprised of senior-level experts and
stakeholders who serve as advisors to the Chief Executive (CE) for project management
in making decisions associated with planning, authorizing, and executing Major System
capital asset projects, defined as projects greater than $750 Million (M).
b. Energy Systems Acquisition Advisory Board Equivalent (ESAAB-E). For non-Major
System capital asset projects, defined as projects under $750M, DOE O 413.3 directs the
establishment of an advisory board process, or ESAAB-E, to conduct functions identical
to those performed by the ESAAB for Major System projects. The ESAAB-E members
provide advice and recommendations regarding Critical Decisions (CDs). The ESAAB-E,
or the NNSA equivalent of a Departmental ESAAB, is conducted for capital asset
projects above $20M and under $750M.
c. ESAAB-E Members. Directors of the organizations and offices identified in Appendix
C.
d. Headquarters Project Managers. A unique position to support an assigned project, and as
such has clear responsibilities to support the FPD and IPT in the ESAAB-E process
e. Independent Project Review (IPR). A project management tool that serves to verify the
project mission, organization, development, processes, technical requirements, baselines,
progress, or readiness to proceed to the next successive phase in DOE's Acquisition
Management System.
Section 9
f. Project Data Sheet (PDS). A document that contains summary project data and the
justification required to include the entire project effort as a part of the Departmental
budget.
g. Subject Matter Expert (SME). Functional and organizational specialists brought into the
ESAAB-E process to participate in IPT meetings as well as ESAAB-E related meetings
and provide objective analyses and assessments when called upon by an FPD, project
stakeholder, board member, or PME.
NNSA SD 413.3-6 Appendix E
03-01-22 APE-1
APPENDIX E: ACRONYMS/ABBREVIATIONS
a. AoA Analysis of Alternatives
b. BCP Baseline Change Proposal
c. CD Critical Decision
d. CE Chief Executive
e. CO Contract Officer
f. DOE-PM U.S. Department of Energy Office of Project Management
g. EDOCS Electronic Document Online Correspondence and Concurrence
System
h. EO Executive Order
i. ESAAB Energy Systems Acquisition Advisory Board
j. ESAAB-E Energy Systems Acquisition Advisory Board – Equivalent
k. FPD Federal Project Director
l. HQ Headquarters
m. HQPM Headquarters Project Manager
n. IPR Independent Project Review
o. M Million
p. PB Performance Baseline
q. PDS Project Data Sheet
r. PEP Project Execution Plan
s. PME Project Management Executive
t. PMO Project Management Office
u. POR Program Office Representative
v. PSO Program Secretarial Officer
w. SME Subject Matter Expert
x. TPC Total Project Cost
NNSA SD 413.3-6 Appendix F
03-01-22 APF-1
APPENDIX F: REFERENCES
a. DOE O 413.3B, Chg6 (LtdChg), Program and Project Management for the Acquisition
of Capital Assets, dated 01-12-21.
b. NA-APM-20 references can be found on MAX.gov:
https://community.max.gov/pages/viewpage.action?pageId=1344080637
c. NNSA Policy (NAP) 130.1B, Planning, Programming, Budgeting, and Evaluation
(PPBE) Process, dated 05-25-21
https://community.max.gov/pages/viewpage.action?pageId=1344080637
1. PURPOSE.
2. AUTHORITY.
3. CANCELLATION.
4. APPLICABILITY.
5. SUMMARY OF CHANGES.
6. BACKGROUND.
7. REQUIREMENTS.
8. RESPONSIBILITIES.
a. Administrator (NA-1).
b. Associate Administrator for Acquisition and Project Management (NA-APM-1).
c. Project Management Executive.
d. Federal Project Director (FPD) or equivalent for CD-0.
e. Integrated Project Team Members.
f. Contracting Officer (CO).
g. Subject Matter Experts (SMEs).
h. Pre-ESAAB-E Members.
i. ESAAB-E Members.
j. ESAAB-E Secretariat.
k.Headquarters Project Managers.
9. DEFINITIONS.
10. ACRONYMS.
11. REFERENCES.
12. CONTACT.
APPENDIX A: NATIONAL NUCLEAR SECURITY ADMINISTRATION (NNSA) ENERGY SYSTEMS ACQUISITION ADVISORY BOARD EQUIVALENT (ESAAB-E) PROCESS
1. BACKGROUND.
2. PROCESS.
a. DOE and NNSA Thresholds and Approval Authority.
b. NNSA ESAAB-E Requests.
c. Dry Runs and PRE-ESAAB-E Meetings.
APPENDIX A: FIGURE 2 - ESAAB-E PROCESS FLOW DIAGRAM
APPENDIX B: ENERGY SYSTEMS ACQUISITIONS ADVISORY BOARD EQUIVALENT (ESAAB-E) REQUEST FORM
APPENDIX C: PRE-ENERGY SYSTEMS ACQUISITION ADVISORY BOARD- EQUIVALENT (PRE-ESAAB-E), ESAAB-EQUIVALENT, AND ESAAB-E MEMBERS AND REPRESENTED ORGANIZATIONS (NON-MAJOR SYSTEMS PROJECTS, I.E., BELOW $750 MILLION (M))
APPENDIX D: DEFINITIONS
APPENDIX E: ACRONYMS/ABBREVIATIONS
APPENDIX F: REFERENCES