SD 413.3-7, Project Management for Non-nuclear, Non-complex Capital Asset Acquisition
The purpose of this Directive is to describe the National Nuclear Security Administration (NNSA) roles, responsibilities, and authorities as they relate to capital asset project management for nonnuclear, non-complex construction projects, as defined in Section 6.c of this Supplemental Directive (SD), with a Total Project Cost (TPC) less than $100 Million (M) and greater than the threshold for minor construction projects, defined in 50 United States Code (U.S.C.) 2741.
NNSA-2023-004569 - SD 413_7 Project Management for Non-Nuclear Non-Complex Capital Asset Acquisition (005).pdf
Associated DOE Directive:
Related To:
New Supplemental DirectvePrivate
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
SUPPLEMENTAL DIRECTIVE
Approved: 09-08-2023
Recertification Due: 09-08-2026
PROJECT MANAGEMENT FOR NON-
NUCLEAR, NON-COMPLEX CAPITAL
ASSET ACQUISITION
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Infrastructure
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT:
https://directives.nnsa.doe.gov
Office of Infrastructure
NNSA SD 413.3-7
1 NNSA SD 413.3-7
09-08-23
PROJECT MANAGEMENT FOR NON-NUCLEAR, NON-COMPLEX CAPITAL ASSET
ACQUISITION
1. PURPOSE. Describe the National Nuclear Security Administration (NNSA) roles,
responsibilities, and authorities as they relate to capital asset project management for non-
nuclear, non-complex construction projects, as defined in Section 6.c of this Supplemental
Directive (SD), with a Total Project Cost (TPC) less than $100 Million (M) and greater
than the threshold for minor construction projects, defined in 50 United States Code
(U.S.C.) 2741. This Supplemental Directive (SD) specifies mandatory tailoring of
requirements established by Department of Energy (DOE) Order (O) 413.3B, Program
and Project Management for the Acquisition of Capital Assets, (herein referred to as DOE
O 413.3) unless the Head of NNSA Program or Field Element (Heads of NNSA
Elements) requires that the project follow DOE O 413.3. It also specifies mandatory
tailoring of requirements that apply to projects between the minor construction threshold
and the DOE O 413.3 applicability threshold.
2. AUTHORITY. DOE O 413.3B, Chg. 7, Program and Project Management for the
Acquisition of Capital Assets, dated 6/21/2023.
3. CANCELLATION. None.
4. APPLICABILITY.
a. Federal. This SD applies to all NNSA federal organizations.
b. Contractor. The Contractor Requirements Document (CRD) attached to this SD
sets forth requirements that apply to contractors performing work on behalf of
NNSA federal organizations. This CRD and Attachments shall be incorporated
into contracts and subcontracts that involve the construction of non-complex
capital assets as defined in Section 6.c. with a TPC less than $100M and greater
than the minor construction threshold.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 U.S.C. sections 2406 and 2511, and to
ensure consistency throughout the joint Navy/DOE Naval Nuclear Propulsion
Program, the Deputy Administrator for Naval Reactors (Director) will implement
and oversee requirements and practices pertaining to this Directive for activities
under the Director's cognizance, as deemed appropriate.
d. This SD or elements of this SD may be applied to other capital asset acquisitions
meeting the requirements as defined in Section 6.c that are greater than the DOE
O 413.3 applicability threshold through the established DOE O 413.3 tailoring
process. Tailoring must be documented and approved by the Project Management
Executive (PME).
5. BACKGROUND. The NNSA Enhanced Minor Construction and Commercial (EMC2) pilot
established a streamlined process for non-nuclear, non-complex real property capital asset
2 NNSA SD 413.3
09-08-23
construction. This SD was written based on the processes developed and used in the
successful execution of projects under that pilot.
6. REQUIREMENTS.
a. This capital asset project management process must be followed for non-nuclear,
non-complex projects as defined in Section 6.c. in conjunction with the
requirements established by DOE O 413.3 using the tailoring specified herein.
The project management principles, as set forth in DOE O 413.3, appendix C,
paragraph 1.a.-k., apply to all capital asset projects.
Section 2
b. An Integrated Project Team (IPT), led by a Federal Project Director (FPD), must
be established after approval of the combined Mission Need Statement and
Program Requirements Document (MNS/PRD).
c. This SD must be applied to projects meeting the following criteria.
(1) The project is not a new or major modification to a hazard category 1, 2,
or 3 nuclear, as defined by 10 Code of Federal Regulations (CFR) 830, or
radiological facility, as defined by DOE STD-1027-2018, Hazard
Categorization of DOE Nuclear Facilities.
(2) The project has no hazards above those that can be addressed using 10
CFR 851.23 safety and health standards.
(3) The project does not include critical technology elements as defined in
DOE Guide (G) 413.3-4A, Technology Readiness Assessments Guide, and
NNSA Policy (NAP) 413.4, Technology Readiness Assessments.
(4) The project is not part of a phased set of projects as defined in DOE O
413.3 Appendix C, Section 27.b nor requires integration with other
projects to provide a complete and usable product.
7. RESPONSIBILITIES.
a. Administrator. Designates a project owner before approval of the Preliminary
Project Execution Plan (PPEP) by the PME.
b. Associate Administrator for the Office of Infrastructure.
(1) Determines the project applicability for this SD and approves deviations
from this SD. This responsibility cannot be delegated.
(2) Assists the Heads of NNSA Elements in developing the combined
MNS/PRD for projects executed using this tailored approach.
3 NNSA SD 413.3-7
09-08-23
(3) Ensures NNSA follows the project management requirements specified
herein for non-complex, non-nuclear projects as defined in Section 6.c.
with a TPC less than $100M and greater than the minor construction
project threshold.
(4) Provides overall direction, strategic guidance, and management with
respect to the acquisition and management of non-nuclear, non-complex
capital asset projects as defined in Section 6.c. and ensures that NNSA
implements all applicable federal and departmental acquisition policies
and regulations.
(5) Ensures NNSA follows the DOE acquisition requirements outlined in the
DOE Acquisition Regulations (DEAR), DOE O 413.3, and DOE policies
for aligning contracts and contract incentives with taxpayer interests.
(6) Assumes the lead role in developing, administering, and awarding NNSA
directly managed design and construction contracts and Inter-Agency
Agreement(s) (IAs).
(7) Trains and develops FPDs per DOE O 361.1C, Acquisition Career
Management Program. Provides FPD upon Head of Field Element’s
(FOM) request.
(8) Issues the PME initial delegation memoranda, if required, and any
subsequent delegations that may be appropriate if material changes in the
project occur.
(9) Assigns a Headquarters Project Manager (HQPM) to the project.
c. Associate Administrator for Management and Budget.
(1) Ensures, at the discretion of the program offices and their specific budget
allocations, funds for project products and services come from the
sponsoring NNSA element’s appropriated funds, the details of which are to
be developed in accordance with the process in NAP 130.1A, Planning,
Programming, Budgeting, and Evaluation (PPBE) Process.
(2) Ensures programs comply with DOE orders, including DOE O 413.3,
during the fiscal year congressional budget process.
(3) Provides IPT representation to ensure programmatic cost estimates are
developed in accordance with NNSA policies and best practices.
Section 3
(4) Assists the Heads of NNSA Elements, if requested, with developing
Business Case Analyses (BCAs) to support the MNS/PRD selected
alternative and preliminary estimate.
4 NNSA SD 413.3
09-08-23
d. Head of NNSA Program Elements.
(1) Determines whether the project will request NA-90-1 approval to use this
SD to execute the project, or whether the project will follow DOE O 413.3
and SD 413.3 instead.
(1) Owns PME authority, consistent with TPC thresholds and delegated
authorities, but this authority should be further delegated.
(2) Leads the development of the MNS/PRD, including selecting the
alternative to close the mission gap.
(3) Manages requirements generation, develops the budget requests, funds
capital asset projects including funding for FPD support governed by DOE
O 413.3, and monitors and approves scope changes as identified in the
Project Execution Plan (PEP) change control table.
(4) Assumes responsibility for oversight of the programmatic operations of
the completed project in accordance with Beneficial Occupancy Date
(BOD) guidance.
(5) Maintains responsibility for the mission need, requirements, selection of a
solution, budgets, and funding through all phases of a capital asset project.
(6) Leads the abbreviated BCA, establishes the gaps and boundaries, and
provides support as needed.
(7) Ensures follow-on operations, waste management and maintenance funds
for the completed project are programmed.
e. Head of NNSA Field Elements.
(1) Provides or requests an FPD to lead the project from MNS/PRD approval
to project completion.
(2) Ensures the federal authorizing and accepting officials have documented
their review of the design documents against their acceptance
requirements before construction mobilization to prevent changes from
being required during project execution. Approves modifications to
federal authorizing official acceptance requirements based on field
conditions. Works with the FPD to enable occupancy and operations.
(3) Provides security; information technology; operational technology
assurance; environment, safety, and health; sustainability; waste
5 NNSA SD 413.3-7
09-08-23
management; and quality assurance technical experts to support the
project, commensurate with complexity.
(4) Provides oversight of site operations.
f. Project Management Executive (PME).
(1) Serves as the approval authority for the project and ensures that
appropriate project management policies and practices are implemented
during project execution.
(2) Approves the MNS/PRD, PPEP, and PEP.
(3) Approves in writing the selection of the FPD.
(4) Coordinates with NA-90-1 to specify additional tailoring or waive the
mandatory tailoring required by this SD.
(5) Verifies the mission need has been met at project completion.
g. Federal Project Director (FPD).
(1) Leads the IPT and serves as a single point of contact for managing the
project, beginning with the PME approval of the MNS/PRD, and
continuing through project completion, including close-out.
(2) Provides primary oversight of the Management and Operating (M&O)
Contractor project manager, IA team, or federal team executing the
project.
(3) Evaluates and verifies reported progress, provides projections for future
progress, and notifies the PME whenever project performance indicates a
likelihood of performance baseline deviation.
(4) Supports and defends the project cost, schedule, performance, and scope
baselines, and ensures that the project receives adequate resources and
expertise in all necessary areas.
Section 4
(5) Serves as the Contracting Officer’s Representative (COR), upon
appointment.
h. Headquarters Project Manager (HQPM).
(1) Serves as the project management professional in NA-90 assigned to
advise the project when the MNS/PRD begins development.
6 NNSA SD 413.3-7
09-08-23
(2) Serves as the primary advisor to the NNSA elements to ensure sufficient
development of the MNS and PRD requirements to allow the project to
proceed with conceptual design.
(3) Advises Heads ofNNSA Elements and FPD on the content and
completeness of the PEP.
9. DEFINITIONS. Also see DOE O 413.3.
10.
11.
12.
a. Business Case Analysis (BCA). A document that summarizes the justification for
the acquisition of a capital asset, including the supporting analysis. The BCA
should provide assurance that the project suppo1is the mission need.
b. Construction Safety and Health Plan (CSHP). A document developed by the
construction contractor that identifies management procedures for the safety and
health of all personnel on the site.
c. Designer of Record. A professional architect or engineer who seals drawings,
reports, or papers for a project. The designer of record for construction projects
assumes professional responsibility for ensuring the integrity of the design.
d. Inspection. An assessment of a specific aspect of a construction project that
ensures the installed product or practice complies with the contract or approved
plans and specifications.
e. Integrated Master Schedule (IMS). An integrated and networked multi-layered
schedule of activities for executing the scope of the project. The IMS includes all
interfaces and milestones necessary for project completion. See Attachment 2 for
further IMS content discussion.
f. OSHA+. An NNSA specific safety management system for non-nuclear, non
complex construction projects that is a tailored, graded approach to meeting both
10 CFR 851 and DOE Integrated Safety Management requirements.
ACRONYMS. See Appendix B.
REFERENCES. See Appendix C.
CONTACT. The Office of Infrastructure, (NA-90), Email: na-90@nnsa.doe.gov.
BY ORDER OF THE ADMINISTRATOR:
Vill 1�
Jill Hruby
Administrator
7 NNSA SD 413.3-7
09-08-23
Attachments:
1. Contractor Requirements Document
2. Project Process – Non-Nuclear, Non-Complex Project Execution Requirements
Appendixes:
A. Project Process – Project Acquisition Management Systems and DOE O 413.3 Crosswalk
B. Project Process – Overview of Roles and Responsibilities
C. Acronyms/Abbreviations
D. References
Attachment 1 NNSA SD 413.3-7
09-08-23 AT1-1
ATTACHMENT 1: CONTRACTOR REQUIREMENTS DOCUMENT
SD 413.3-7, PROJECT MANAGEMENT FOR NON-NUCLEAR, NON-COMPLEX
CAPITAL ASSET ACQUISITION
1. INTRODUCTION.
This Contractor Requirements Document (CRD) establishes the requirements for
National Nuclear Security Administration (NNSA) contractors who perform capital asset
project management for non-nuclear, non-complex line-item construction projects as
defined in Supplemental Directive (SD) 413.3-7, Section 6.c. with a Total Project Cost
(TPC) less than $100 Million (M) and greater than the minor construction applicability
threshold.
NNSA contractors are responsible for complying with the requirements of this CRD and
for flowing down the requirements of this CRD to subcontractors at all levels, to the
extent necessary, to verify the contractor’s compliance with the requirements.
2. REQUIREMENTS.
The contractor must comply with the requirements laid out in Attachments 2 and 3 of this
SD.
Section 5
a. General Requirements.
(1) Contractors must adjust procedures related to acceptance of work
performed using the SD’s risk, design, and submittal review, quality
control, commissioning, and inspection reforms without an acceptance
review prior to operating the facility to enable acceptance of capital assets
under this SD.
(2) Contractors must adjust procedures related to project schedule and
reporting requirements, safety, risk, quality, commissioning, and
inspections to enable execution of capital assets using this SD.
(3) Contractors must identify conflicts between this SD and the existing
Management and Operating Contract requirements, if applicable, and
resolve them with the NNSA Contracting Officer.
b. Specific Requirements.
(1) Contractor Project Manager. Capital asset projects must be executed in
compliance with Attachments 2 and 3 of this SD.
(2) Contractor Contracting Officer. Ensures the Management and Operating
contract or Interagency Agreement does not conflict with Attachments 2
and 3 of this SD.
Attachment 2 NNSA SD 413.3-7
09-08-23 AT2-1
ATTACHMENT 2: PROJECT PROCESS – NON-NUCLEAR, NON-COMPLEX
PROJECT EXECUTION REQUIREMENTS
Note: This attachment applies to NNSA federal employees, contractors and federal
organizations executing work in compliance with this NNSA Supplemental Directive 413.3,
Project Management for Non-nuclear, Non-complex Capital Asset Acquisition on behalf of the
NNSA.
1. INTRODUCTION.
This document establishes the project tailoring requirements for non-nuclear, non-
complex line-item construction projects as defined in this Supplemental Directive (SD)
Section 6.c with a Total Project Cost (TPC) less than $100 Million (M) and greater than
the minor construction threshold.
2. REQUIREMENTS.
a. Major tailored elements of the federal project management process identified in
NNSA SD 413.3, Program and Project Management for the Acquisition of
Capital Assets, are as follows.
(1) Project scope and alternative selection must be performed during the
project planning and initiation phase in accordance with Office of
Management and Budget (OMB) Circular No. A-11, Preparation,
Submission, And Execution of the Budget. An Analysis of Alternatives
(AoA) is not conducted for a low complexity project. An abbreviated
Business Case Analysis (BCA) is performed to a level of detail that is
commensurate with the complexity of the project.
(2) Formal Energy Systems Acquisition Advisory Board Equivalent (ESAAB-
E) hold points are replaced by Project Management Executive (PME)
approval of key documents which correspond to Department of Energy
(DOE) Order (O) 413.3B, Chg. 7, Program and Project Management for
the Acquisition of Capital Assets (DOE O 413.3) critical decisions (CDs):
(a) The Mission Need Statement/Program Requirements Document
(MNS/PRD) as CD-0 Approve Mission Need.
(b) The Preliminary Project Execution Plan (PPEP) as CD-1 Approve
Alternative Selection and Cost Range.
(c) The Project Execution Plan (PEP) as CD-2/3 Approve
Performance Baseline/Start of Construction or Execution.
(d) Federal Project Director (FPD) notification to the PME that the
project is complete as CD-4 Approve Start of Operations or Project
Completion.
Attachment 2
AT2-2
NNSA SD 413.3-7
09-08-23
(3) The DOE Project Assessment and Reporting System (PARS) reporting
requirements for acquisitions with TPCs greater than the DOE O 413.3
applicability threshold but less than $100M consist of the following:
Section 6
(a) A monthly narrative, TPC and project completion forecasts, project
status color assessment as defined in PARS, the native file of the
Integrated Master Schedule (IMS) Baseline and Status schedules,
and a similar report to the Contract Performance Report (CPR)
Format 1.
Note: The IMS is an integration of the Firm Fixed Price (FFP)
contract schedule of values-based cost-loaded schedule and the
Cost-Plus (e.g., Management and Operating Contractor [M&O])
resource-loaded schedule; FFP contractors should not provide
resource-loaded schedules to assist in creating an IMS.
(b) The approved MNS/PRD, PPEP, PEP, conceptual, preliminary,
and final design reports, and project completion report must be
uploaded to PARS. The content of these documents should be
consistent with the requirements of DOE O 413.3.
(4) The requirements in SD 413.3-1 for Independent Project Reviews (IPRs) or
Annual Project Reviews (APRs) by the Office of Infrastructure (NA-90)
are superseded. All reviews required by DOE O 413.3 are delegated to the
FPD. This will be a tailored project review, using support as necessary,
limited to reviewing the project documents to determine if the scope and
project requirements are defined well enough to award the design,
construction, and/or design-build contract, confirming that the Key
Performance Parameters (KPPs) and other Program Requirements are
being met, the contractor level of effort activities are appropriate, and the
overall cost and schedule. The PME may request or grant additional
independent reviews.
(5) A qualitative risk analysis must be used instead of a quantitative risk-based
approach to establishing contingency and management reserve.
(6) Streamline federal and M&O functional oversight to align with commercial
standards. Safety, quality, environmental, and security inspection
frequencies – should be reduced to a minimum, to the greatest extent
possible. Additional inspections may be authorized by the FPD in
instances where significant issues are found. The FPD will notify the
PME, within 30 days of initiation, if additional inspections are performed.
Inspection frequencies will subsequently revert to a minimal amount, per
functional area, after the issues are resolved. All inspections will be
conducted concurrently to the maximum extent practicable to minimize
disruption of on-site activities.
Attachment 2 NNSA SD 413.3-7
09-08-23 AT2-3
b. Major tailored and exempted elements of the work activities are as follows.
(1) The use of an IMS with Baseline and Status schedules is crucial to
effective project management and must consist of the following items. The
resource-loaded IMS must include and integrate both the work directly
performed by the M&O contractor personnel and the schedule of values
based, cost-loaded schedules for FFP subcontracts.
(a) For acquisitions greater than the DOE O 413.3 applicability
threshold, resource-loaded schedules are only required for work
directly performed by M&O contractor personnel or using cost-
plus subcontracts.
(b) FFP contracts must implement and submit a schedule of values-
based, cost-loaded schedules instead of resource-loaded schedules
to the FPD. The schedules must be cost loaded on major
deliverable activities with measurable scope to develop a time-
phased cost profile.
(2) The use of commonly referenced standards and avoidance of citing DOE
Orders in procurement documents to the greatest extent possible.
Section 7
(3) Design reviews are restricted to ensure code compliance, that functional
requirements are met, federal authorizing and accepting official
requirements are met, and connections to external infrastructure are
adequate.
(4) Reduce functional oversight to align with commercial standards. Safety,
quality, environmental, and security inspection frequencies are reduced to
a maximum of twice monthly per functional area. Additional inspections
may be authorized by the FPD in instances where significant issues are
found. The FPD will notify the PME, within 30 days of initiation, if
additional inspections are performed. Inspection frequencies will
subsequently revert to a maximum of twice monthly per functional area
after the issues are resolved. This requirement for reduced inspections
does not apply to inspections required by code or project specification.
All inspections will be conducted concurrently to the maximum extent
practicable to minimize disruption of on-site activities.
(5) Construction submittal reviews must be performed by Title III
architectural/engineering support, with no systematic duplicate reviews by
the M&O contractor or federal team. A review of the submittals to ensure
compliance with functional requirements is allowed. For example, the site
requires a specific manufacturer of mechanical equipment for maintenance
purposes and wants to confirm this manufacturer was submitted – but the
review should stop after the manufacturer’s name is confirmed and not
continue by reviewing the features included on the units.
Attachment 2
AT2-4
NNSA SD 413.3-7
09-08-23
(6) The use of the designer of record’s quality control, submittal, testing,
commissioning, and inspection requirements and their inclusion in the
construction specifications.
(7) For work not directly performed by the M&O contractor or other federal
agency personnel, including subcontractors to these entities:
(a) The construction contractor will develop and use a project-specific
Construction Safety and Health Plan (CSHP) that is aligned with
the OSHA+ model.
(b) The CSHP must include the core elements identified in the
Occupational Safety and Health Administration’s (OSHA)
Recommended Practices for Safety & Health Programs in
Construction (OSHA 3886) and must be approved by the agent –
M&O Contractor, Interagency Agreement partner, NNSA Federal
Project Director, etc. – who is the counterparty to the construction
contractor’s contract. In addition, the CSHP must address the use
of respiratory protection, lasers, welding/brazing, and American
Conference of Government Industrial Hygienists Threshold Limit
Values for controlling worker exposure hazards to construction
activities commensurate with the project.
(c) The construction contractor must have a designated competent
person responsible for safety on site during the performance of all
physical work activities, and M&O contractor or federal agency
personnel shall not perform nor provide oversight of this function,
unless approved by the FPD to resolve significant issues.
(d) This safety management system is a tailored, graded approach to
meeting both 10 CFR 851 and DOE O 450.2, Integrated Safety
Management requirements and is hereafter referred to as OHSA+.
3. PROCESS.
a. Planning: Prepare combined MNS/PRD for Approval.
Section 8
(1) Develop combined MNS/PRD. When a credible performance gap is
identified between current capabilities and those required to achieve the
mission, the Heads of NNSA Program or Field Elements (Heads of NNSA
Elements) will lead the development of a combined MNS/PRD that
translates mission needs into functional requirements. This document
includes content typically found within the MNS and the PRD. The MNS
portion describes the mission gap and must not be written to assume any
particular solution, whether material or non-material, although the PRD
portion does include the specific solution to close the mission performance
gap. The Heads of NNSA Elements must develop and maintain the
MNS/PRD during the life of the project. The Heads of NNSA Elements
Attachment 2 NNSA SD 413.3-7
09-08-23 AT2-5
also engage the Office of Design and Construction (NA-92) at this phase
to add a Headquarters Project Manager (HQPM) to the Integrated Project
Team (IPT) to act as a project management advisor.
(2) Perform an Abbreviated BCA and/or PRD Estimate. When several
credible means of closing the mission gap exist, the Heads of NNSA
Elements shall determine, via an abbreviated BCA, the appropriate means
to establish a specific solution to close the mission need gap. The level of
analysis in the BCA should be commensurate with the complexity of the
project. The development of the MNS/PRD preliminary project cost
estimate range, based on the selected solution, must be performed by the
Office of Management and Budget (NA-MB) in accordance with NNSA
Policy 413.5. This upper end of the project cost estimate range ascertains
whether the project will remain less than the $100M threshold for the
application of this SD.
(3) FPD Appointment. The Head of NNSA Field Element (FOM) identifies a
FPD to manage the project’s execution. If an FPD is not available, the
FOM collaborates with NA-90 to identify an available FPD. The FPD is
assigned to the project through identification in the PRD and formally
appointed with the PME’s approval of the PRD. The FPD remains within
their existing organization. Any change in FPD appointment will be
recorded and approved with PME approval of the PPEP/PEP. FPD
appointments are made based on an evaluation of an individual’s project
management training/experience and the project size. The appointed FPD
initially may not be fully certified, but the FPD must be working towards
Project Management Career Development Program (PMCDP) certification
at the appropriate level. This plan to attain the appropriate level of
certification should be documented in the PRD or PPEP/PEP.
(4) Identify and Provide Funding. The responsible Heads of NNSA Elements
use the cost estimate developed by NA-MB to establish the rough-order of
magnitude (ROM) cost range and request funding for capital asset
projects. The Heads of NNSA Elements formulate the budget details in
accordance with NNSA Policy (NAP) 130.1A, Planning, Programming,
Budgeting, and Evaluation (PPBE) Process. The Heads of NNSA
Elements will ensure adequate resources are provided throughout the
project.
b. Post MNS/PRD Approval: Prepare PPEP Defining Project Cost Estimate Range.
(1) Establish an IPT. Upon approval of the combined MNS/PRD for a capital
asset project, the Heads of NNSA Elements will establish a matrixed IPT
comprising of NNSA Field Office personnel, NNSA Program Office
personnel, project and acquisition professionals, subject matter experts,
contractors, and other federal personnel. An FPD is selected to lead the
IPT after PME approval of the MNS/PRD. The IPT includes:
Section 9
Attachment 2
AT2-6
NNSA SD 413.3-7
09-08-23
• NA-90 to advise on infrastructure issues;
• The Office of the Associate Administrator for Information
Management and Chief Information Officer (NA-IM) to advise on
IT standards, enterprise architecture, cybersecurity, and operational
technology assurance;
• Safeguards and security to advise on security requirements;
• The Office of Environmental, Safety, and Health (NA-ESH) to
advise on environment, safety, and health and sustainability
requirements; and
• NA-MB to develop all cost estimates, and
• Other subject matter experts who would contribute to the success
of the project.
IPT members are responsible for ensuring their headquarters organizations
concur with the advice provided to the FPD. (See DOE G 413.3-18A, IPT
Guide for Formation and Implementation).
(2) Develop the Acquisition Strategy. The FPD develops the Acquisition
Strategy in consultation with the Heads of NNSA Elements and the entity
issuing the procurement contract, NA-90 for projects directly managed by
NNSA, or the M&O contractor or other executing federal agency for
projects indirectly managed by NNSA. The Acquisition Strategy,
including the details of the contractor’s Acquisition Plan, must be included
in the PPEP. (For additional information, see NA-92 Standard Practice
02, Acquisition Strategy; DOE G 413.3-13 Chg 1 (Admin Chg), U.S.
Department of Energy Acquisition Strategy Guide for Capital Asset
Projects; DOE Acquisition Guide, chapter 7; and Federal Acquisition
Regulation [FAR] parts 7 and 34).
(3) Develop the PPEP. The FPD leads the development of the PPEP, which
describes the preliminary scope, schedule, and cost range estimates,
organizational framework, and overall management system for the project,
including the detailed approach for the execution of design activities. The
high end of the cost range established at PPEP approval determines the
maximum total estimated cost (TEC) funding which will be provided to
the project. (For additional information see DOE G 413.3-15A, Project
Execution Plans). The PPEP must include the tailoring specified in this
SD unless a waiver is obtained from the PME. If planned, the PPEP also
includes detailed plans for long-lead procurements or early site
preparation work. The FPD, Head of NNSA Elements, and PME approve
scope changes in accordance with the change control thresholds in the
approved PPEP. The Acquisition Strategy must be predominately FFP
subcontracts. After removal of management reserve and contingency from
Attachment 2 NNSA SD 413.3-7
09-08-23 AT2-7
the TEC funding total, the goal is for 85% of the remaining TEC balance
to be allocated to those subcontracts when the performance baseline is
later approved. PME approval of the PPEP is required before TEC funds
may be committed or spent for design only. The FPD manages PPEP
under change control protocols after its approval by the PME.
(4) Develop the Conceptual Design. The FPD oversees the conceptual design
team. The conceptual design shall conform to the design guidance in
Appendix D, Conceptual and Preliminary Design Guidance, of SD 413.3,
Program and Project Management for the Acquisition of Capital Assets.
The FPD and Program Manager approve the Conceptual Design Report to
ensure that it conforms to all project requirements in the MNS/PRD.
Progress updates and conceptual design development statuses are provided
in PARS to senior leaders. NA-MB’s Federal Cost Lead will assist with
reviewing the conceptual design cost estimate. The federal and M&O
contractor authorizing/accepting authorities for security, cybersecurity,
operational technology assurance, information technology, and safety
(especially fire protection) will review the conceptual design to ensure it
conforms to their requirements to occupy and operate the facility.
Section 10
(5) Development Initial Risk Management Plan. Develop a risk management
plan and complete an initial risk assessment for the selected alternative as
part of the PPEP. Use a Qualitative Risk Analysis Matrix (See Figure 3 in
DOE G 413.3-7A, Risk Management Guide) to identify an individual risk
rating based on the assigned probability and consequence of a risk based
on the simplicity of non-complex construction. Each of these risk ratings
categorizes each risk as low, moderate, or high. Integrate individual risk
ratings determine an overall project risk rating. The goal is for
management reserve and contingency to be 15% of the TEC costs when
the performance baseline is later approved.
(6) Exemptions, Equivalencies, and Waivers. The FPD may seek exemptions
or equivalencies to the requirements in DOE directives in accordance with
the process described in Appendix E of DOE O 251.1D, Departmental
Directives Program. Examples include an equivalency for fire protection
system requirements or an exemption from a natural phenomenon hazard
requirement. Such exemptions, equivalencies, and waivers represent a
risk to the project until approved. Projects requesting an exemption,
equivalency, or waiver should place a high priority on having the request
approved before the final conceptual design report.
c. Post PPEP Approval: Complete Design and Develop Performance Baseline.
(1) Award and Administer Design Subcontracts or Inter-Agency
Agreement(s) (IAs). The FPD oversees the award and management of
design or design-build subcontracts or IAs to support project requirements,
according to the design approach identified in the PPEP. To ensure
Attachment 2
AT2-8
NNSA SD 413.3-7
09-08-23
successful outcomes, close coordination is expected between acquisition
staff across the enterprise.
(2) Complete Project Design. The FPD ensures the preliminary design
conforms to the design guidance in Appendix D, Conceptual and
Preliminary Design Guidance, of NNSA SD 413.3, Program and Project
Management for the Acquisition of Capital Assets. Preliminary changes
to scope and schedule and cost estimate ranges included in the PPEP are
approved in accordance with the change control thresholds in the approved
PPEP. The FPD measures and evaluates performance against the
preliminary scope, schedule, and cost estimate ranges included in the
PPEP. The designer of record’s quality control, submittal, testing,
commissioning, and inspection requirements must be used and included in
the project’s construction specifications. The Federal and M&O
contractor authorizing/accepting authorities for security, cybersecurity,
operational technology assurance, information technology, and safety
(especially fire protection) will review the design to ensure it conforms
with their requirements to occupy and operate the facility.
(3) Long Lead Procurements. If identified in the PPEP, pursue the acquisition
of long-lead materials or equipment and incidental site preparations.
Examples of incidental site preparation work includes clearing, grubbing
and stabilization of the site; relocation of roads and utilities; contractor
office and parking spaces; new construction site fence lines and
relocations; concrete batch plants; and temporary work and storage
facilities. It does not include any permanent segment of construction of
the project/facility and will not be used to proceed with construction
incrementally.
Section 11
(4) Performance Baseline and PEP Development. The FPD drafts the PEP
based on the most recent PPEP and develops the performance baseline,
reflective of identified and assessed risks and uncertainties, to include
scope, total project cost, and planned project completion date, and KPPs
(if applicable). Use a Qualitative Risk Analysis Matrix (See Figure 3 in
DOE G 413.3-7A, Risk Management Guide) to identify an individual risk
rating based on the assigned probability and consequence of a risk based
on the simplicity of non-complex construction. Each of these risk ratings
categorizes each risk as low, moderate, or high. Use of individual risk
ratings determine an overall project risk rating. This overall project rating
is used to determine whether less than 15% of the design and construction
point estimates should be used for management reserve and contingency.
An amount more than 15% must be clearly justified. If the total project
cost exceeds the upper end of the project cost estimate range identified in
the approved PPEP by greater than 50%, the PME must reassess the
approved project solution and either approve a new solution or reaffirm
the current solution with an updated project cost estimate range. After the
receipt of subcontractor bids, the FPD requests PME approval of the PEP.
Attachment 2 NNSA SD 413.3-7
09-08-23 AT2-9
The FPD independently validates this updated baseline, and the PME
should receive advice from appropriate Heads of NNSA Elements prior to
the approval of the PEP. Project success will be measured at project
completion against this original approved performance baseline scope,
project completion date, and total project cost, which includes confirming
that the baselined KPPs and other program requirements within the PRD
were met.
(5) Plan for Site Integration. The FPD and Heads of NNSA Elements,
through the IPT, establish a plan for site integration. Planning for site
integration involves identifying site interface needs and infrastructure
requirements to mitigate barriers to construction execution. The Plan
should have agreed upon and clearly documented organizational interfaces
and responsibilities by all involved parties, as codified in the PPEP or
PEP, commissioning plan, startup plan, or as a standalone plan.
(6) Earned Value Management System (EVMS). EVMS system certification
is not required. Alternative project controls will be documented in the
PEP and used in lieu of compliant EVMS. Alternative project control
methods to be used must include at a minimum a work breakdown
structure (WBS), integrated master schedule showing critical path, account
of planned versus actual work and cost, and EAC.
d. Post PEP approval: Construction Execution.
(1) Award and Administer Construction Subcontracts or IAs. The FPD
oversees the award and management of construction subcontracts or IAs to
support project requirements and the baseline scope, cost, and schedule
included in the PEP. To ensure successful outcomes, close coordination is
expected between contracting staff across the enterprise.
Section 12
(2) Manage the Project Baseline. The FPD manages the project performance
baseline by overseeing and evaluating the progress of the project through
project completion. The FPD measures and evaluates performance against
the performance baseline scope, project completion date, and total project
cost in the approved PEP. The FPD, contractor or IA Project Manager,
and the Head of NNSA Program and Field Element’s Program Managers
monitor progress and performance through monthly communications.
Tailored reporting in PARS will be completed as described in section
2.a.3. Baseline changes are processed and approved in accordance with
the change control thresholds in the approved PEP. The FPD executes
changes in accordance with thresholds for scope, schedule, and cost as
defined in the PEP. Changes impacting the project performance baseline
must be approved by the PME.
Attachment 2
AT2-10
NNSA SD 413.3-7
09-08-23
(3) Manage Site Integration Issues. The FPD takes the lead role in managing
site integration activities, in support of construction activities, with the
NNSA elements.
(4) Prepare for Transition to Operations. In close coordination with Head of
NNSA Program and Field Elements, the FPD supports the contractor
Project Manager during the startup, turnover, and closeout of the project.
Activities include checkout, testing, and operations, completing a
transition to operations plan. The Head of NNSA Program and Field
Elements’ involvement in these activities is essential for project success.
(5) Establish Beneficial Occupancy Date (BOD). Before final completion of
a building or facility construction, the BOD establishes when users can
occupy it for the purpose for which it was constructed. The BOD is the
date that follow-on contracts/activities (if any), such as information
technology, operational technology assurance, or furniture installations,
may begin in accordance with Appendix E, Beneficial Occupancy
Guidance, of SD 413.3, Program and Project Management for the
Acquisition of Capital Assets.
(6) Accept Project for Operations. The PME verifies that the mission needs
and project requirements were met and accepts the project for operation in
accordance with the PEP.
(7) Transition to Operations and Conduct Closeout Activities. Upon
acceptance, the FPD provides updates through monthly communications
with matrixed IPT members until closeout activities are completed. This
includes completing punch list items, managing warranty issues,
completing contracts/IAs, and conducting closeout activities.
(8) Notify PME of Project Completion. The FPD confirms that the baseline
scope from the PEP was achieved and develops a summary report for
notification to the PME of project completion. This report must include
the final scope, cost, and schedule of the project and verification that the
project completion criteria were satisfied. The FPD uploads the report
into PARS to officially close the project.
Appendix A NNSA SD 413.3-7
09-08-23 APA-1
APPENDIX A: PROJECT PROCESS – PROJECT ACQUISITION MANAGEMENT SYSTEMS AND DOE O 413.3
CROSSWALK
The graphic below presents the non-nuclear, non-complex project acquisition management system for line-item capital asset projects in
comparison to the Department of Energy (DOE) acquisition management system for line-item capital asset projects to show the
similarities and differences between the two systems.
Appendix A
APA-2
NNSA SD 413.3-7
09-08-23
Section 13
The following tables identify the mandatory tailoring for projects that qualify for project
management under this Supplemental Directive (SD) unless a waiver is granted by the Project
Management Executive (PME). Project processes as defined in DOE Order (O) 413.3B Chg. 7
(LtdChg), Program and Project Management for the Acquisition of Capital Assets are stated in
column 1, with the tailoring for that requirement (if any) in column 2. Critical Decision (CD)
equivalencies or substitutions are also indicated in column 2.
DOE O 413.3B Table 2.0: CD-0 Requirements Crosswalk
Prior to CD-0 Tailoring
Perform Pre-Conceptual Planning activities that focus on the
Program Offices’ strategic goals and objectives, safety planning,
design, development of capability gaps, high-level project
parameters, a ROM cost range, and schedule estimates.
None – no change to the current process.
Perform a Mission Validation Independent Review on all major
system projects. (Refer to DOE G 413.3-9, current version).
N/A – does not apply to this class of
projects.
Approve a Mission Need Statement Document with
recommendation from PM for projects with a TPC ≥ $100M.
(Refer to DOE G 413.3-17, current version).
The approval authority is the PME instead
of Program Secretarial Officer (PSO).
Combine the Mission Need Statement
(MNS) and Program Requirements
Document (PRD) into one document.
For Major System Projects, or for projects as designated by the CE,
PM will conduct an Independent Cost Review (ICR).
N/A. Substitute the independent cost
estimate (ICE) performed by the Office of
Cost Estimating and Program Evaluation
(NA-1.3) with a cost estimate on the
alternative within the combined
MNS/PRD performed by the Office of
Management and Budget (NA-MB).
For Major System Projects, the Project Management Risk
Committee (PMRC) will review and analyze the CD and make
recommendations to the ESAAB, CE, or PME, as applicable, before
approval.
N/A – does not apply to this class of
projects.
For NNSA only, prepare a Program Requirements Document that
defines the ultimate goals that the project must satisfy. (Refer to
NNSA Business and Operating Policy).
The approval authority is the PME instead
of PSO. Combine the MNS and PRD into
one document. NA-MB must perform the
PRD alternative cost.
For Hazard Category 1, 2, and 3 nuclear facilities, and to the
specificity possible, document DOE expectations for Safety-in-
Design. (Refer to DOE-STD-1189-2016).
N/A – does not apply to this class of
projects.
Appendix A NNSA SD 413.3-7
09-08-23 APA-3
Post CD-0 Approval CD-0 approval is substituted with the
PME approval of the combined
MNS/PRD.
Submit all CD documents to PM. Document is a PDF upload of the PME-
approved MNS/PRD.
Develop a Project Data Sheet (PDS) for Line-Item Projects to
request Project Engineering and Design (PED) funds. Develop
funding documents for MIE or OE projects for the design, and
OMB A-11 business cases. (Refer to DOE CFO Budget Call for
PDS and Business Case Template).
None – no change to the current process.
Initiate monthly PARS reporting (excluding earned value data).
FPD, Program Manager, and PM will provide monthly assessments,
as appropriate.
None – no change to the current process.
Initiate Quarterly Project Reviews (QPRs) with the PME or their
designee.
None – no change to the current process.
Conduct a project peer review of active projects when the top-end
range is $100M or greater.
N/A – does not apply to this class of
projects.
Section 14
Proceed with conceptual planning and design used to develop
alternative concepts and functional requirements using operating
funds.
Develop alternative concepts and perform
associated, abbreviated Business Case
Analyses (BCAs) prior to MNS/PRD
approval.
DOE O 413.3B Table 2.1: CD-1 Requirements Crosswalk
Prior to CD-1 Tailoring
Approve an Acquisition Strategy (AS) with endorsement from PM
for Major System Projects. (Refer to DOE G 413.3-13, current
version).
The AS approval authority is the PME
instead of the PSO. Include the AS in the
preliminary project execution plan
(PPEP) as part of PPEP approval.
Approve a preliminary Project Execution Plan (PEP). The Tailoring
Strategy, if required, can be included in the PEP, or placed in a
separate document. (Refer to DOE G 413.3-15, current version.)
None – no change to the current process.
Approve appointment of the Federal Project Director considering the
requirements in DOE O 361.1C, current version.
The Federal Project Director (FPD) is
identified in the PPEP and appointed with
PPEP approval. The FPD is matrixed to
the project and remains an employee of
their home office.
Establish and charter an Integrated Project Team (IPT) to include a
responsibility assignment matrix. The Charter may be included in
the PEP. (Refer to DOE G 413.3-18, current version).
No independent IPT charter; the matrixed
IPT members are identified in the PPEP’s
roles and responsibilities section.
Appendix A
APA-4
NNSA SD 413.3-7
09-08-23
Develop a Risk Management Plan (RMP) and complete an initial
risk assessment of a recommended alternative. This may be
included in the PEP. For evaluating the Safety-in-Design strategy,
prepare Risk and Opportunity Assessments for input to the RMP.
(Refer to DOE G 413.3-7, current version, and DOE-STD-1189-
2016.)
The RMP is included in the PPEP, and a
qualitative risk analysis shall assess
whether the current upper end of the
range will encompass the expected
management reserve or contingency
within the 15% goal.
For projects with a TPC > $100M, PM will develop an Independent
Cost Estimate and/or conduct an Independent Cost Review, as they
deem appropriate.
N/A – does not apply to this class of
projects.
For projects with a TPC ≥ $100M, the PMRC will review and
analyze the CD and make recommendations to the ESAAB, CE, or
PME, as applicable, before approval.
N/A – does not apply to this class of
projects.
Comply with the One-for-One Replacement legislation (excess
space/offset requirement) as mandated in House Report 109-86.
Include the one-for-one replacement plan
mandated by House Report 109-86 in the
PPEP.
For Major System Projects, develop a Design Management Plan that
establishes design maturity targets at critical milestones through
final design.
N/A – does not apply to this class of
projects.
Complete a Conceptual Design. None – no change to the current process.
Incorporate and document compliance with climate adaptation,
resilience, and sustainability requirements (refer to Appendix C,
Paragraph 5.), support for the Site Sustainability Plan(s) per DOE O
436.1 (current version) and/or other high performance and
sustainable building considerations (refer to DOE G 413.3-6, current
version, and Guiding Principles for Sustainable Federal Building) in
the PEP, Conceptual Design Report and Acquisition Strategy as
appropriate.
Include the sustainability plan in the
PPEP.
Appendix A NNSA SD 413.3-7
09-08-23 APA-5
Section 15
Conduct a Design Review of the conceptual design with reviewers
external to the project.
The FPD leads the review using support,
as necessary, after the conceptual design
is completed. This project review
consists of reviewing the project
documents to determine if the scope and
project requirements are defined well
enough to award the design or design-
build contract, confirming that the Key
Performance Parameters (KPPs) and other
Program Requirements are being met, the
contractor level of effort, and the overall
cost and schedule. SD 413.3-1, Project
Reviews does not apply. Design review
support may use Management and
Operating contractor (M&O), Inter-
Agency Agreement (IA) or other project
personnel instead of reviewers external to
the project. The federal and M&O
contractor authorizing/accepting
authorities for security, cybersecurity,
operational technology assurance,
information technology, environment and
sustainability, and safety (especially fire
protection) will review the design to
ensure it conforms with their
requirements to occupy and operate the
facility.
For Hazard Category 1, 2, and 3 nuclear facilities, a Code of
Record must be initiated during the conceptual design.
N/A – does not apply to this class of
projects.
Complete a Conceptual Design Report. Refer to Appendix C,
Paragraph 8.
The conceptual design report does not
include a section on the alternatives
analyzed nor the basis for the selected
alternative, as this was performed prior to
MNS/PRD approval.
Conduct an Analysis of Alternatives (AoA) that is independent of
the contractor organization responsible for managing the
construction or constructing the capital asset project, for projects
with an estimated TPC greater than $50M. (Refer to GAO-16-22).
No AoA is performed; the necessary
alternative evaluation and selection was
performed with an abbreviated BCA prior
to MNS/PRD approval.
For Major System Projects, or first-of-a-kind engineering endeavors,
conduct a Technology Readiness Assessment and develop a
Technology Maturation Plan, as appropriate. At this stage, each
critical technology item or system must achieve a Technology
Readiness Level-4 (TRL-4). (Refer to DOE G 413.3-4, current
version).
N/A – does not apply to this class of
projects.
Prepare a Preliminary Hazard Analysis Report (PHAR) for facilities
that are below the Hazard Category 3 nuclear facility threshold as
defined in 10 CFR Part 830, Subpart B.
None – no change to the current process.
Appendix A
APA-6
NNSA SD 413.3-7
09-08-23
Develop and implement an Integrated Safety Management Plan into
management and work process planning at all levels per DOE G
450.4-1 (current version).
Include the Integrated Safety
Management (ISM) plan in the PPEP.
Restricting all functional oversight –
safety, quality, environmental, and
security – inspection frequencies to a
maximum of twice monthly per functional
area unless inspectors find significant
issues. For work directly performed by
Management and Operating Contractor
(M&O) personnel, refer to the M&O’s
approved DOE Integrated Safety
Management plan. For work not directly
performed by M&O personnel (i.e.,
construction contractor) use approved
Construction Safety and Health Plan
incorporating OSHA+ approach (see
Attachment 2, section 2.b.(7)).
Establish a Quality Assurance Program (QAP). (Refer to 10 CFR
Part 830, Subpart A, DOE O 414.1, current version and DOE G
413.3-2, current version). For nuclear facilities, the applicable
national consensus standard shall be NQA-1-2008 (Edition) and
NQA-1a-2009 (Addenda).
Section 16
Include the QAP plan in the PPEP.
Reduce functional oversight to align with
commercial standards. Safety, quality,
environmental, and security inspection
frequencies are reduced to a maximum of
twice monthly per functional area. If
significant issues are found, additional
inspections may be performed after
coordination with the FPD. Inspection
frequencies will subsequently revert to a
maximum of twice monthly per functional
area after the issues are resolved. All
inspections will be conducted
concurrently to the maximum extent
practicable to minimize disruption of on-
site activities.
Identify general Safeguards and Security requirements for the
recommended alternative. (Refer to DOE O 470.4, current version
and DOE G 413.3-3, current version).
Include safeguards and security
requirements included in the PPEP.
Reduce functional oversight to align with
commercial standards. Safety, quality,
environmental, and security inspection
frequencies are reduced to a maximum of
twice monthly per functional area. If
significant issues are found, additional
inspections may be performed after
coordination with the FPD. Inspection
frequencies will subsequently revert to a
maximum of twice monthly per functional
area after the issues are resolved. All
inspections will be conducted
concurrently to the maximum extent
practicable to minimize disruption of on-
site activities.
Appendix A NNSA SD 413.3-7
09-08-23 APA-7
Complete a National Environmental Policy Act (NEPA) Strategy by
issuing a determination (e.g., Environmental Assessment), as
required by DOE P 451.1, current version. Prepare an
Environmental Compliance Strategy, including a schedule for timely
acquisition of required permits and licenses.
NEPA strategy included in the PPEP.
Update Project Data Sheet, or other funding documents for MIE and
OE projects, and A-11 Business Case, if applicable. This must
contain an estimate of the required amount of PED funds to execute
the planning and design portion of a project (period from CD-1 to
completion of the project’s design). (Refer to DOE CFO Budget
Call for PDS and Business Case Template).
None – no change to the current process.
Conduct a Preliminary Security Risk Assessment, if necessary.
(Refer to DOE O 470.4, current version and DOE G 413.3-3, current
version).
None – no change to the current process.
For Hazard Category 1, 2, and 3 nuclear facilities, prepare a
Safety Design Strategy (SDS) to guide the development of the
conceptual design, with the concurrence of the CNS or with written
advice of the CDNS, as appropriate, for projects subject to DOE-
STD-1189-2016.
N/A – does not apply to this class of
projects.
For Hazard Category 1, 2, and 3 nuclear facilities, conduct an
Independent Project Review (IPR) to ensure early integration of
safety into the design process. (Refer to DOE G 413.3-9, current
version and DOE-STD-1189-2016).
N/A – does not apply to this class of
projects.
Prepare a Conceptual Safety Design Report (CSDR) for Hazard
Category 1, 2, and 3 nuclear facilities, including preliminary
hazard analysis. For a project involving a major modification of an
existing facility, the SDS must address the need for a CSDR, as well
as the required PDSA. (Refer to DOE-STD-1189-2016).
N/A – does not apply to this class of
projects.
Prepare a Safety Review Letter, with concurrence from the FPD, on
the DOE review of the CSDR for Hazard Category 1, 2, and 3
nuclear facilities. (Refer to DOE-STD-1189-2016 and DOE-STD-
1104-2016).
Section 17
N/A – does not apply to this class of
projects.
Post CD-1 Approval CD-1 approval is consistent with PME
approval of the PPEP and is required to
authorize the use of TEC funding.
Submit all CD documents to PM. Documents submitted to the Department
of Energy Project Management (DOE-
PM) is a pdf upload of the PME-approved
PPEP and conceptual design report.
Begin expenditure of PED, MIE, or OE funds for the project design. None – no change to the current process.
Appendix A
APA-8
NNSA SD 413.3-7
09-08-23
Develop an Acquisition Plan, if applicable. Include the acquisition plan in the Project
Execution Plan (PEP), following the
acquisition strategy.
Continue monthly PARS reporting (excluding earned value). FPD,
Program Manager and PM will provide monthly assessments, as
appropriate.
Reporting consists of a progress narrative,
TPC and project completion date
forecasts, a progress color assessment
rating as defined in DOE Project
Assessment and Reporting System
(PARS), the native file of the Integrated
Master Schedule (IMS) Baseline and
Status schedules, and a similar report to
the Contractor Performance Report (CPR)
Format 1.
Annually conduct project peer reviews of active projects when the
top-end range is $100M or greater. Individuals leading project peer
reviews, or other reviews intended to meet the project peer review
requirements in this Order, shall elicit lessons learned with potential
Department-wide implications and submit them into DOE lessons
learned system of record, as described in DOE O 210.2 (current
version).
N/A – does not apply to this class of
projects.
Continue QPRs with the PME of their designee. None – no change to the current process.
For nuclear facilities, develop a Checkout, Testing and
Commissioning Plan in preparation for acceptance and turnover of
the structures, systems and components at CD-4. (Refer to
DOE-STD-1189-2016).
N/A – does not apply to this class of
projects.
DOE O 413.3B Table 2.2 CD-2 Requirements Crosswalk
Prior to CD-2 Tailoring
Approve an updated Acquisition Strategy if there are any major
changes to the acquisition approach. Obtain endorsement from PM
for Major System Projects. (Refer to DOE G 413.3-13, current
version).
If necessary, update the acquisition
strategy in the PEP and obtain approval
from the PME.
Establish a Performance Baseline, reflective of identified and
assessed risks and uncertainties, to include scope, TPC, CD-4 date,
and minimum KPPs (if applicable). The key project milestones and
completion dates must be stated no less specific than month and
year. The scope will be stated in quantity, size and other parameters
that give shape and form to the project. The funding assumptions
upon which the PB is predicated will be clearly documented and
approved. (Refer to DOE G 413.3-5, current version).
In the PEP, include the scope, cost, and
schedule performance baselines; KPPs
and any other project completion criteria;
and Future Years Nuclear Security Plan
(FYNSP) funding profile.
Approve updated Project Execution Plan. (Refer to DOE G 413.3-
15, current version).
None – no change to the current process.
Appendix A NNSA SD 413.3-7
09-08-23 APA-9
Prepare a Funding Profile to support the execution of the PB and
reflect in the budget document. The funding profile may be
included in the PEP.
None – no change to the current process.
Approve Long-Lead Item Procurements, if necessary. Approval may
be concurrent with (or prior to) CD-2 approval. (Long-lead item
procurement approval will be designated as CD-3A).
Section 18
The plan for the acquisition of long-lead
materials and equipment and incidental
site preparations is included in the PPEP
and approved with that document.
Develop a Project Management Plan, if applicable. (Refer to
Attachment 1).
None – no change to the current process.
Perform a Performance Baseline External Independent Review (EIR)
or an Independent Project Review (IPR). PM will conduct EIRs to
validate the PB for projects with a TPC ≥ $100M. PM must issue a
Performance Baseline Validation Letter to the PSO that describes
the cost, schedule, and scope being validated. PMSO will conduct
IPRs to validate the PB for projects with a TPC < $100M. (Refer to
DOE G 413.3-9, current version).
For projects with a TPC ≥ $100M, PM will develop an Independent
Cost Estimate (ICE). The ICE will support validation of the PB.
IPR and performance baseline (PB)
validation is delegated to the FPD in lieu
of a project management support office
(PMSO). FPD leads project review, using
support, as necessary, prior to the PEP
approval. This project review consists of
reviewing the project documents,
confirming that the KPPs and other
Program Requirements are being met,
transition to operations requirements is
defined, the contractor level of effort, and
the overall cost and schedule.
Complete a Preliminary and/or Final Design. Hazard Category 1, 2,
and 3 nuclear facilities shall achieve at least 90% design
completion prior to CD-2 approval. Non-nuclear project designs
shall be sufficiently mature to prepare a project baseline with 70-
90% confidence prior to CD-2 approval. (See Appendix C,
paragraph 7a for definition of 90% design complete).
The designer of record’s quality control,
submittal, testing, commissioning, and
inspection requirements must be included
in the design’s construction
specifications.
Incorporate and document compliance with climate adaptation,
resilience, and sustainability requirements (refer to Appendix C,
Paragraph 5.), support for the Site Sustainability Plan(s) per DOE O
436.1 (current version) and/or other high performance and
sustainable building considerations (refer to DOE G 413.3-6, current
version, and Guiding Principles for Sustainable Federal Buildings)
in the PEP, preliminary and/or final designs, and design review
reports as appropriate.
None – no change to the current process.
Appendix A
APA-10
NNSA SD 413.3-7
09-08-23
Conduct a Design Review of the preliminary and final designs. The agent managing the design contract
performs the design review of the
preliminary and final designs. The review
confirms that the design satisfies the
project’s KPPs and other
program/functional requirements and that
the designer of record’s quality control,
submittal, testing, commissioning, and
inspection requirements have been
included in the construction
specifications. The Federal and M&O
contractor authorizing and accepting
authorities for security, cybersecurity,
operational technology assurance,
information technology, environment and
sustainability, and safety (especially fire
protection) will review the design to
ensure it conforms with their
requirements to occupy and operate the
facility.
For Hazard Category 1, 2, and 3 nuclear facilities, design reviews
should include a focus on safety and security systems. Additionally,
the Code of Record shall be placed under configuration control
during preliminary design. It is controlled during final design and
construction with a process for reviewing and evaluating new and
revised requirements. New or modified requirements are
implemented if technical evaluations determine that there is a
substantial increase in the overall protection of the worker, public
or environment, and that the direct and indirect costs of
implementation are justified in view of this increased protection.
Section 19
N/A – does not apply to this class of
projects.
Complete a Preliminary Design Report. None – no change to the current process.
For projects with a TPC ≥ $100M, the PMRC will review and
analyze the CD and make recommendations to the ESAAB, CE, or
PME, as applicable, before approval.
N/A – does not apply to this class of
projects.
Conduct a Project Definition Rating Index Analysis, as appropriate,
for projects with a TPC ≥ $100M. PM will review as part of the EIR.
(Refer to DOE G 413.3-12, current version).
N/A – does not apply to this class of
projects.
For Major System Projects, or first-of-a-kind engineering endeavors,
conduct a Technology Readiness Assessment and develop a
Technology Maturation Plan, as appropriate. At this stage, each
critical technology item or system shall achieve a Technology
Readiness Level-7 (TRL-7). (Refer to DOE G 413.3-4, current
version.)
N/A – does not apply to this class of
projects.
Appendix A NNSA SD 413.3-7
09-08-23 APA-11
Employ an Earned Value Management System compliant with EIA-
748 (current version), or as required by the contract. This is
performed by the contractor. (Refer to DOE G 413.3-10, current
version.)
Earned Value Management System
(EVMS) certification is not required.
Substituted for EVMS reporting in PARS
is the native file of the IMS Baseline and
Status schedules, and a similar report to
the CPR Format 1.
Prepare a Hazard Analysis Report for facilities that are below the
Hazard Category 3 nuclear facility threshold as defined in 10 CFR
Part 830, Subpart B by updating the PHAR based on new hazards
and design information.
None – no change to the current process.
Determine that the Quality Assurance Program is acceptable and
continues to apply. (Refer to 10 CFR Part 830, Subpart A, DOE O
414.1, current version, and DOE G 413.3-2, current version.)
Include QAP updates in the PEP. Reduce
functional oversight to align with
commercial standards. Safety, quality,
environmental, and security inspection
frequencies are reduced to a maximum of
twice monthly per functional area. If
significant issues are found, additional
inspections may be performed after
coordination with the FPD. Inspection
frequencies will subsequently revert to a
maximum of twice monthly per functional
area after the issues are resolved. All
inspections will be conducted
concurrently to the maximum extent
practicable to minimize disruption of on-
site activities.
Issue the final Environmental Impact Statement or Environmental
Assessment and Finding of No Significant Impact, as required by
10 CFR Part 1021. For an Environmental Impact Statement, the
appropriate authority shall issue the Record of Decision after CD-2
is granted, but prior to CD-3 approval. (Refer to DOE P 451.1,
current version.)
None – no change to the current process.
Update Project Data Sheet, or other funding documents for MIE and
OE projects, and A-11 Business Case, if applicable. (Refer to DOE
CFO Budget Call for PDS and Business Case Template).
None – no change to the current process.
For Hazard Category 1, 2, and 3 nuclear facilities, conduct a
Technical Independent Project Review (TIPR). The TIPR is
required at or near the completion of the preliminary design. The
TIPR is not required for non-nuclear facilities. (Refer to DOE G
413.3-9, current version).
N/A – does not apply to this class of
projects.
For Hazard Category 1, 2, and 3 nuclear facilities, update the
Safety Design Strategy, with the concurrence of CNS or with written
advice from CDNS, as appropriate, for projects subject to DOE-
STD-1189-2016.
Section 20
N/A – does not apply to this class of
projects.
Appendix A
APA-12
NNSA SD 413.3-7
09-08-23
Prepare Preliminary Safety and Design Results that update the
CSDR for Hazard Category 1, 2, and 3 nuclear facilities based on
updated hazard analysis and design information. These results
complete the preliminary design phase and allow for DOE review
prior to completing the final design phase. (Refer to DOE-STD-
1189-2016).
N/A – does not apply to this class of
projects.
Prepare a Safety Review Letter, with concurrence from the FPD,
based on a DOE review of the Preliminary Safety and Design
Results for Hazard Category 1, 2, and 3 nuclear facilities. This
DOE review should be scheduled as early as practicable, after
contractor completion of the preliminary design, to minimize project
risk. (Refer to DOE-STD-1189-2016 and DOE-STD- 1104-2016).
N/A – does not apply to this class of
projects.
Prepare the PDSA for newly planned Hazard Category 1, 2, and 3
nuclear facilities based on updated hazard analysis and design
information; also for major modifications of existing facilities.
(Refer to 10 CFR Part 830, Subpart B, and DOE-STD-1189-2016).
N/A – does not apply to this class of
projects.
Prepare a Safety Evaluation Report, with concurrence from the
FPD, based on review of the PDSA for Hazard Category 1, 2, and 3
nuclear facilities. (Refer to 10 CFR Part 830, Subpart B, and DOE-
STD-1104-2016).
N/A – does not apply to this class of
projects.
Post CD-2 Approval CD-2 approval is combined with CD-3
approval and is substituted with PME
approval of the PEP, which is necessary
to authorize construction mobilization.
Submit all CD documents, and if there are changes to the PB, submit
BCP documents to PM.
Documents submitted to DOE-PM are a
pdf upload of the PME-approved PEP and
the final design report.
For projects with a TPC ≥ $100M, the PMRC will review and
analyze the PB deviation disposition request and make
recommendations to the ESAAB, CE, or PME, as applicable, before
approval. The resulting BCP must also be presented to the PMRC
before convening an ESAAB.
N/A – does not apply to this class of
projects.
Obtain PME endorsement on any changes to the approved funding
profile that negatively impacts the project.
None – no change to the current process.
Continue monthly PARS reporting (including earned value data).
FPD, Program Manager and PM will provide monthly assessments.
Reporting consists of the requirements
described in DOE O 413.3B Table 2.1:
CD-1 Requirements Crosswalk, Post CD-
1 Approval, Row 4, Column 2.
Continue QPRs with the PME or their designee. None – no change to the current process.
Appendix A NNSA SD 413.3-7
09-08-23 APA-13
Annually conduct project peer reviews for projects with a TPC >
$100M. Individuals leading project peer reviews, or other reviews
intended to meet the project peer review requirements in
this Order, shall elicit lessons learned with potential Department-
wide implications and submit them into DOE lessons learned system
of record, as described in DOE O 210.2 (current version).
N/A – does not apply to this class of
projects.
DOE O 413.3B Table 2.3: CD-3 Requirements Crosswalk
Prior to CD-3 Tailoring
Approve updated CD-2 Project Documentation that reflects major
changes from Final Design, the PEP, PB, AS, and PDS/funding
documents for MIE and OE funds.
None – no change to the current process.
Complete and review the Final Design for non-nuclear facilities and
less than Hazard Category 3 nuclear facilities.
Section 21
The FPD leads a final design review,
using support, as necessary, prior to the
PEP approval. The review confirms that
the design satisfies the project’s KPPs and
other program/functional requirements
and that the designer of record’s quality
control, submittal, testing,
commissioning, and inspection
requirements have been included in the
construction specifications. The Federal
and M&O contractor authorizing and
accepting authorities for security,
cybersecurity, operational technology
assurance, information technology, and
safety (especially fire protection) will
review the design to ensure it conforms
with their requirements to occupy and
operate the facility.
Incorporate and document compliance with climate adaptation,
resilience, and sustainability requirements (refer to Appendix C,
Paragraph 5.), support for the Site Sustainability Plan(s) per DOE O
436.1 (current version) and/or other high performance and
sustainable building considerations (refer to DOE G 413.3-6, current
version, and Guiding Principles for Sustainable Federal Building) in
the PEP, Conceptual Design Report and Acquisition Strategy as
appropriate.
None – no change to the current process.
Employ a certified Earned Value Management System compliant
with EIA-748 (current version), or as required by the contract.
(Refer to DOE G 413.3-10, current version.)
EVMS system certification is not
required. Alternative project controls will
be used in lieu of compliant EVMS.
Appendix A
APA-14
NNSA SD 413.3-7
09-08-23
Perform an External Independent Review by PM for Construction or
Execution Readiness on all Major System Projects. (Refer to DOE
G 413.3-9, current version.)
Perform an Independent Project Review by the appropriate PMSO
for Non-Major System Projects unless justification is provided and a
waiver is granted by the PME.
For projects with a TPC ≥ $100M, PM will develop an Independent
Cost Estimate.
IPR delegated to FPD in lieu of PMSO.
FPD leads project review, using support,
as necessary, prior to the PEP approval.
This project review consists of reviewing
the project documents, confirming that
the KPPs and other Program
Requirements are being met, transition to
operations requirements are defined, the
contractor level of effort, and the overall
cost and schedule.
For projects with a TPC ≥ $100M, the PMRC will review and
analyze the CD and make recommendations to the ESAAB, CE, or
PME, as appropriate, before approval.
N/A – does not apply to this class of
projects.
For Major System Projects where a significant critical technology
element modification occurs subsequent to CD-2, conduct a
Technology Readiness Assessment, as appropriate. (Refer to DOE
G 413.3-4, current version.)
N/A – does not apply to this class of
projects.
Update the Hazard Analysis Report for facilities that are below the
Hazard Category 3 nuclear facility threshold as defined in 10 CFR
Part 830, Subpart B, based on new hazards and design information.
None – no change to the current process.
Prior to start of construction, prepare a Construction Project Safety
and Health Plan in accordance with 10 CFR Part 851, Appendix A,
Section 1(d). This plan must be kept current during construction.
Reduce functional oversight to align with
commercial standards. For work not
directly performed by Management and
Operating contractor personnel (i.e.,
construction contractor) use approved
Construction Safety and Health Plan
incorporating OSHA+ approach (see
Attachment 2, section 2.b.(7)). This
satisfies 10 Code of Federal Regulations
851, Appendix A, section 1(d).
Section 22
Update the Quality Assurance Program for construction, field design
changes, and procurement activities. (Refer to 10 CFR Part 830,
Subpart A, DOE O 414.1, current version, and DOE G 413.3-2,
current version.)
Include QAP updates in the PEP. Reduce
functional oversight to align with
commercial standards. Safety, quality,
environmental, and security inspection
frequencies are reduced to a maximum of
twice monthly per functional area. If
significant issues are found, additional
inspections may be performed after
coordination with the FPD. Inspection
frequencies will subsequently revert to a
maximum of twice monthly per functional
area after the issues are resolved. All
inspections will be conducted
concurrently to the maximum extent
practicable to minimize disruption of on-
site activities.
Appendix A NNSA SD 413.3-7
09-08-23 APA-15
Finalize the Security Risk Assessment Report, if necessary. (Refer to
DOE O 470.4, current version and DOE G 413.3-3, current version.)
None. Reduce functional oversight to
align with commercial standards. Safety,
quality, environmental, and security
inspection frequencies are reduced to a
maximum of twice monthly per functional
area. If significant issues are found,
additional inspections may be performed
after coordination with the FPD.
Inspection frequencies will subsequently
revert to a maximum of twice monthly per
functional area after the issues are
resolved. All inspections will be
conducted concurrently to the maximum
extent practicable to minimize disruption
of on-site activities.
Post CD-3 Approval CD-3 approval is combined with CD-2
approval and is substituted with PME
approval of the PEP, which is necessary
to authorize construction mobilization.
Submit all CD documents to PM. Documents submitted to DOE-PM are a
pdf upload of the updated PEP and the
final design report.
Commit all the resources necessary, within the funds provided and
within the TPC, to execute the project.
None – no change to the current process.
For projects with a TPC ≥ $100M, the PMRC will review and
analyze the PB deviation disposition request and make
recommendations to the ESAAB, CE, or PME, as applicable, before
approval. The resulting BCP must also be presented to the PMRC
before convening an ESAAB.
N/A – does not apply to this class of
projects.
Within 90 days, submit Lessons Learned not previously recognized
regarding up-front project planning and design int the DOE lessons
learned system of record, as described in DOE O 201.2 (current
version) for projects with a TPC ≥ $100M.
Submit project lessons learned into the
lessons learned repository in DOE
OPEXShare at the time of project
closeout only.
Update PDS, or other funding documents for MIE and OE, and A-11
Business Case, if applicable. (Refer to DOE CFO Budget Call for
PDS and Business Case Template).
None – no change to the current process.
Conduct EVMS surveillance to ensure compliance with EIA-748
(current version), or as defined in the contract. Contractor must
conduct the surveillance annually.
EVMS system certification is not
required. Alternative project controls will
be used in lieu of compliant EVMS.
Continue monthly PARS reporting (including earned value data).
FPD, Program Manager and PM will provide monthly assessments.
Reporting consists of the requirements
described in DOE O 413.3B Table 2.1:
CD-1 Requirements Crosswalk, Post CD-
1 Approval, Row 4, Column 2.
Continue QPRs with the PME or their designee. None – no change to the current process.
Section 23
Appendix A
APA-16
NNSA SD 413.3-7
09-08-23
Continue annual project peer reviews for projects with a TPC >
$100M. Individuals leading project peer reviews, or other reviews
intended to meet the project peer review requirements in
this Order, shall elicit lessons learned with potential Department-
wide implications and submit them into the DOE lessons learned
system of record, as described in DOE O 210.2 (current version).
N/A – does not apply to this class of
projects.
DOE O 413.3B Table 2.4: CD-4 Requirements Crosswalk
Prior to CD-4 Tailoring
Verify that Key Performance Parameters and Project Completion
Criteria have been met and that mission requirements have been
achieved. The FPD will verify and document the scope
accomplished, TPC, KPPs met, and the completion date as it relates
to the original CD-2 performance baseline and the latest approved
baseline change.
None – no change to the current process.
Issue a Project Transition to Operations Plan³ that clearly defines the
basis for attaining initial operating capability, full operating
capability, or project closeout, as applicable. The plan will include
documentation, training, interfaces, and draft schedules. (Refer to
DOE G 413.3-16, current version.)
Include the transition to operations plan in
the PEP.
For non-nuclear projects, conduct a formal assessment of the
project's Readiness to Operate, as appropriate. Determine the basis
for DOE acceptance of the asset and if the facility or area can be
occupied from both a regulatory and a work function standpoint.
Establish a beneficial occupancy/utilization date for the facility
and/or equipment.
Contractors must adjust procedures
related to acceptance of work performed
using the SD’s risk, design & submittal
review, quality control, commissioning,
and inspection reforms without an
acceptance review prior to operating the
facility to enable acceptance of capital
assets performed using this SD.
Finalize the Hazard Analysis Report for facilities that are below the
Hazard Category 3 threshold as defined in 10 CFR Part 830, Subpart
B.
None – no change to the current process.
Revise the Environmental Management System in accordance with
DOE O 436.1 (current version), as appropriate.
None – no change to the current process.
If applicable, complete and submit Contractor Evaluation
Documents to the PME, the appropriate PSO, Federal procurement
office, and PM in accordance with FAR 42.15.
None – no change to the current process.
For projects with a TPC ≥ $100M, the PMRC will review and
analyze the CD and make recommendations to the ESAAB, CE, or
PME, as applicable, before approval.
N/A – does not apply to this class of
projects.
Conduct an Operational Readiness Review (ORR) or Readiness
Assessment (RA) for Hazard Category 1, 2, and 3 nuclear facilities
in accordance with DOE O 425.1, current version.
N/A – does not apply to this class of
projects.
Appendix A NNSA SD 413.3-7
09-08-23 APA-17
Prepare the Documented Safety Analysis with Technical Safety
Requirements for Hazard Category 1, 2, and 3 nuclear facilities.
(Refer to 10 CFR Part 830, Subpart B).
N/A – does not apply to this class of
projects.
Prepare a Safety Evaluation Report (SER) based on a review of the
Documented Safety Analysis and Technical Safety Requirements for
Hazard Category 1, 2, and 3 nuclear facilities. (Refer to 10 CFR
Part 830, Subpart B, and DOE-STD-1104-2016).
N/A – does not apply to this class of
projects.
Section 24
For nuclear facilities, the Code of Record must be included as part
of the turnover documentation from a design and construction phase
contractor to the operating phase contractor; from an operating
phase contractor to the decommissioning phase contractor; and
when a change in contractor occurs during any single life-cycle
phase and is maintained under configuration control. (Refer to
DOE-STD-1189-2016)
N/A – does not apply to this class of
projects.
Post CD-4 Approval CD-4 approval is consistent with the
submission by the FPD of the report to
the PME, verifying that the KPPs and
Project Completion Criteria have been
met, the scope accomplished, TPC, and
completion date.
Submit all CD documents to PM. Documents submitted to DOE-PM are the
FPD report verifying that the KPPs and
Project Completion Criteria have been
met, the scope accomplished, TPC, and
completion date.
Finalize PARS reporting (including reporting earned value data
through completion of the PMB).
Reporting consists of the requirements
described in DOE O 413.3B Table 2.1:
CD-1 Requirements Crosswalk, Post CD-
1 Approval, Row 4, Column 2.
Within 90 days, submit Lessons Learned not previously recognized
regarding project execution and facility start-up into the DOE
lessons learned system of record, as described in DOE O 210.2
(current version).
Submit project lessons learned into the
lessons learned repository in DOE
OPEXShare at project completion only.
Within 90 days, submit an Initial Project Closeout Report. None – no change to the current process.
Appendix A
APA-18
NNSA SD 413.3-7
09-08-23
DOE O 413.3B Table 2.5: Project Closeout Requirements Crosswalk
Prior to Project Closeout Tailoring
Perform final administrative and financial closeout. Prepare the
final Project Closeout Report once all project costs are incurred
and invoiced and all contracts are closed. The report includes final
cost details as required to include claims and claims settlement
strategy where appropriate. (Refer to DOE G 413.3-16, current
version.)
None – no change to the current process.
Complete and document achievement of climate adaptation,
resilience, and sustainability requirements (refer to Appendix C,
Paragraph 5.), support for the Site Sustainability Plan(s) per DOE O
436.1 (current version), and/or other high performance and
sustainable building considerations (refer to DOE G 413.3 6, current
version, and Guiding Principles for Sustainable Federal Buildings)
which were documented in the PEP, as applicable.
None – no change to the current process.
Establish and/or update the property record in the Facilities
Information Management System (FIMS) for all construction of or
modifications to real property. (Refer to DOE O 430.1, current
version.)
None – no change to the current process.
Appendix B NNSA SD 413.3-7
09-08-23 APB-1
APPENDIX B: PROJECT PROCESS – OVERVIEW OF ROLES AND
RESPONSIBILITIES
Project Phase FPD Roles & Responsibilities Heads of NNSA Program or Field Elements
(Heads of NNSA Elements) Roles &
Responsibilities
Planning:
Approve
Mission Need
Statement
(MNS) &
Program
Requirements
Document
(PRD)
Support: Be aware of the need for a capital
asset project.
Lead: Generate mission needs and program
requirements. Finalize the MNS/PRD.
Identify and provide funding. Determine
method to close the mission gap, including any
necessary business case analyses. Establish the
rough order of magnitude (ROM) cost range.
Section 25
Pre-
Preliminary
Project
Execution Plan
(PPEP):
Approve
Preliminary
Performance
Baselines
Lead: Lead the matrixed Integrated Project
Team (IPT). Develop the PPEP, including
preliminary scope, cost, and schedule baselines.
Oversee the conceptual design with change
control discipline. Ensure that project
requirements are met. Develop the acquisition
strategy and oversee the procurement plan.
Oversee the qualitative risk analysis. After
Project Management Executive (PME)
approval, maintain the PPEP with change
control.
Lead: Establish a matrixed IPT. Develop
project budget and provide funding.
Manage/adjust program requirements, as
necessary, to meet mission needs. Concur with
proposed preliminary baselines and
manage/establish project budget accordingly.
Support: Assist in preparation and approval of
the PPEP, including preliminary performance
baselines and acquisition strategy. Approve
scope changes per the change control table in
the PPEP. Review conceptual design
deliverables.
Pre- Project
Execution Plan
(PEP):
Performance
Baseline
Lead: Develop the PEP. Oversee design
contracts/IAs to support project requirements.
Obtain PME approval of the performance
baseline after receipt of bids. Oversee any long
lead procurements. After PME approval,
maintain PEP under change control.
Support: Incorporate any changes in project
requirements identified by the Head of NNSA
Program and Field Elements.
Lead: Make trade-off decisions during design
that impact project requirements or costs.
Manage/adjust project requirements, as
necessary, to meet mission needs. Concur with
project baselines and manage/establish project
budget accordingly.
Support: Review design deliverables. Assist in
the preparation and development of the updated
PEP, including performance baseline and
acquisition strategy.
Appendix A
APB-2
NNSA SD 413.3-7
09-08-23
Post PEP:
Prepare for
Project
Completion
Lead: Oversee the award of construction
contracts/ Inter-Agency Agreements (IAs) to
achieve project baseline. Identify and manage
site integration issues. Manage the project
baseline. Identify and request baseline changes
for any unforeseen changes or project
requirement changes identified by the Head of
NNSA Program and Field Elements.
Implement approved changes identified by the
Heads of NNSA Elements. Manage change
control in accordance with the PEP. Oversee
final inspections and commissioning. Manage
punch list items and warranty issues. Accept
the project and establish the Beneficial
Occupancy Date (BOD). Turnover completed
project to operations. Complete contract(s) and
project closeout activities.
Support: Work with Heads of NNSA Elements
to mitigate barriers to construction execution.
Develop and adjust requirements to
accommodate any changes to the project
identified by the Heads of NNSA Elements.
Provide information necessary for trade-off
analysis and decisions.
Lead: Identify any changes required to meet
mission needs. Identify site integration issues.
Provide funding in accordance with approved
baseline. Manage project budget. Initiate plan
for future operations of completed project.
Support: Review monthly project
communications to ensure project requirements
are being met. Evaluate/accept project for
operations and verify mission
need/requirements were met.
*This table is a summary with specific roles and responsibilities outlined in accordance with the
PPEP/PEP.
Appendix C NNSA SD 413.3-7
09-08-23 APC-1
Section 26
APPENDIX C: ACRONYMS/ABBREVIATIONS
a. AoA Analysis of Alternatives
b. APR Annual Project Review
c. AS Acquisition Strategy
d. BCA Business Case Analysis
e. BOD Beneficial Occupancy Date
f. CD Critical Decision
g. CE Chief Executive for Project Management
h. CFO Chief Financial Officer
i. CFR Code of Federal Regulations
j. CO Contracting Officer
k. COR Contracting Officer’s Representative
l. CPR Contract Performance Report
m. CRD Contractor Requirements Document
n. DEAR DOE Acquisition Regulations
o. DMP Design Management Plan
p. DOE Department of Energy
q. DOE-PM Department of Energy’s Office of Project Management
r. EIR External Independent Review
s. EMC² Enhanced Minor Construction and Commercial
t. ESAAB-E Energy Systems Acquisition Advisory Board Equivalent
u. EVMS Earned Value Management System
v. FAR Federal Acquisition Regulation
w. FFP Firm Fixed Price
x. FOM Head of NNSA Field Element
y. FPD Federal Project Director
z. FYNSP Future Years Nuclear Security Plan
aa. G Guide
bb. GAO Government Accountability Office
cc. HQPM Headquarters Project Manager
Appendix C
APC-2
NNSA SD 413.3-7
09-08-23
dd. IA Inter-Agency Agreement
ee. ICE/R Independent Cost Estimate/Review
ff. IMS Integrated Master Schedule
gg. IPR Independent Project Review
hh. IPT Integrated Project Team
ii. ISM Integrated Safety Management
jj. KPP Key Performance Parameter
kk. LEED Leadership in Energy and Environmental Design
ll. M Million
mm. M&O Management and Operating Contractor
nn. MIE Major Items of Equipment
oo. MNS Mission Need Statement
pp. NA-1.3 Office of Cost Estimating and Program Evaluation
qq. NA-90 Office of Infrastructure
rr. NA-ESH Office of Environmental, Safety, and Health
ss. NA-IM Office of the Associate Administrator for Information Management
and Chief Information Officer
tt. NA-MB Office of Management and Budget
uu. NAP NNSA Policy
vv. NEPA National Environmental Policy Act
ww. OE Operating Expense
xx. OSHA Occupational Safety and Health Administration
yy. PARS Project Assessment and Reporting System
zz. PB Performance Baseline
aaa. PED Project Engineering and Design
bbb. PEP Project Execution Plan
ccc. PDS Project Data Sheet
ddd. PM Project Management
eee. PMCDP Project Management Career Development Program
fff. PME Project Management Executive
ggg. PMRC Project Management Risk Committee
Appendix C NNSA SD 413.3-7
09-08-23 APC-3
hhh. PMSO Project Management Support Office
iii. PPBE Planning, Programming, Budgeting, and Evaluation
jjj. PPEP Preliminary Project Execution Plan
kkk. PRD Program Requirements Document
lll. PSO Program Secretarial Officer
mmm.QAP Quality Assurance Program
nnn. RMP Risk Management Plan
ooo. ROM Rough-Order of Magnitude
ppp. SD Supplemental Directive
qqq. SIH Standard Industrial Hazards
rrr. STD Standard
sss. TPC Total Project Cost
Appendix D NNSA SD 413.3-7
09-08-23 APD-1
APPENDIX D: REFERENCES
a. Federal Acquisitions Regulation and Office of Federal Procurement Policy guidance.
b. Department of Energy (DOE) Acquisition Regulations (DEAR).
c. Office of Management and Budget (OMB) Circular A-11 for Capital Acquisition Projects
and its associated Capital Programming Guide.
d. DOE Order 413.3B, Program and Project Management for the Acquisition of Capital
Assets, dated 1-12-21.
e. DOE Order 450.2, Integrated Safety Management, dated 01-17-17.
Section 27
f. DOE Guide (G) 413.3-1, Managing Design and Construction Using Systems Engineering,
dated 10-22-15.
g. DOE G 413.3-4A, Technology Readiness Assessments Guide, dated 10-22-15.
h. DOE G 413.3-7A, Risk Management Guide, dated 11-22-21.
i. DOE G 413.3-13, U.S. Department of Energy Acquisition Strategy Guide for Capital
Asset Projects, dated 10-22-15.
j. DOE G 413.3-15A, Project Execution Plans, dated 09-14-18.
k. DOE G 413.3-17, Mission Need Statement, dated 10-22-15.
l. DOE G 413.3-18A, Integrated Project Team Guide for Formation and Implementation,
dated 10-22-15.
m. Government Accountability Office (GAO) Best Practices GAO-20-195G, Cost
Estimating and Assessment Guide, dated 03-12-20.
n. NNSA Policy (NAP) 130.1A, Planning, Programming, Budgeting, and Evaluation
(PPBE) Process, dated 12-09-19.
o. NAP 413.3A, Responsibilities for Independent Cost Estimates, dated 04-30-21.
p. NAP 413.4, Technology Readiness Assessment, dated 12-22-16.
q. NNSA Supplemental Directive (SD) 413.3, Program and Project Management for the
Acquisition of Capital Assets, dated 05-18-21.
r. NNSA SD 413.3-1, Project Reviews, dated 05-10-21.
s. NNSA SD 413.3-4, Program Requirements Document, dated 09-15-21.
t. NNSA SD 413.3-6, Energy Systems Acquisition Advisory Board Equivalent (ESAAB-E)
Process, dated 03-01-22.
NNSA SD 413.3-7
09-08-23
Appendix D
APD-2