SD 413.3, Program and Project Management for the Acquisition of Capital Assets
Describes the National Nuclear Security Administration (NNSA) roles, responsibilities, and authorities as they relate to capital asset project management for line item and major items of equipment projects in accordance with Department of Energy (DOE) Order (O) 413.3B, Program and Project Management for the Acquisition of Capital Assets, or successor. This Supplemental Directive (SD) will be applied in conjunction with, and may supplement, but will not supersede any requirements established by the current version of DOE O 413.3. Canceled BOP 413.7, dated 8-9-16.
Associated DOE Directive:
Version history and related documents
Superseded by
A newer version replaces this document.
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Acquisition and Project Management
https://directives.nnsa.doe.gov
printed copies are uncontrolled
SUPPLEMENTAL DIRECTIVE
Approved: 05-18-21
Expires: 05-18-24
PROGRAM AND PROJECT
MANAGEMENT FOR THE ACQUISITION
OF CAPITAL ASSETS
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Acquisition and Project Management
NNSA SD 413.3
https://directives.nnsa.doe.gov/
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 413.3 1
05-18-21
PROGRAM AND PROJECT MANAGEMENT FOR THE ACQUISITION OF CAPITAL
ASSETS
1. PURPOSE. Describes the National Nuclear Security Administration (NNSA) roles,
responsibilities, and authorities as they relate to capital asset project management for line
item and major items of equipment (MIE) projects in accordance with Department of
Energy (DOE) Order (O) 413.3B, Program and Project Management for the Acquisition
of Capital Assets, or successor (herein referred to as DOE O 413.3). This Supplemental
Directive (SD) will be applied in conjunction with, and may supplement, but will not
supersede any requirements established by the current version of DOE O 413.3.
2. AUTHORITY. DOE Order 413.3B, Chg. 6, Program and Project Management for the
Acquisition of Capital Assets, dated 1-12-21.
3. CANCELLATION. Business Operating Procedure (BOP) 413.7, Program and Project
Management for the Acquisition of Capital Assets, dated 8-9-16.
4. APPLICABILITY.
a. Federal. This SD applies to all NNSA federal organizations.
b. Contractor. This SD does not apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 United States Code sections 2406 and
2511, and to ensure consistency throughout the joint Navy/DOE Naval Nuclear
Propulsion Program, the Deputy Administrator for Naval Reactors (Director) will
implement and oversee requirements and practices pertaining to this Directive for
activities under the Director's cognizance, as deemed appropriate.
5. SUMMARY OF CHANGES. NNSA BOP 413.7, Program and Project Management for
the Acquisition of Capital Assets, was reformatted to create this SD and incorporates the
following updates:
a. Updates reflected in DOE O 413.3.
b. An increase in the General Plant Project (GPP) minor construction threshold from
$10M to $20M.
c. Key changes to ensure that project requirements and conceptual design are
managed by acquisition and project management professionals after completion
of the Analysis of Alternatives (AoA) Alternative Selection Document (ASD).
6. BACKGROUND. This document defines accountability, responsibilities, and authorities
while highlighting key factors that contribute to acquisition of capital assets across
2 NNSA SD 413.3
05-18-21
NNSA and applies to capital asset line item/MIE projects, as defined in DOE O 413.3,
Attachment 2. The current line item threshold defined by Congress begins at $20M.
This SD also reflects guidance from Office of Management and Budget (OMB) Circular
A-11, the Federal Acquisition Regulation (FAR), Office of Federal Procurement Policy
(OFPP) guidance, the DOE Acquisition Regulations (DEAR), DOE O 413.3, and the
Department’s acquisition and project management policies.
7. REQUIREMENTS.
Section 2
a. The capital asset project management process must be applied in conjunction with
the requirements established by DOE O 413.3, specifically paragraph 3.a, “for
projects having a total project cost (TPC) greater than $50M, except where the
Administrator has reduced the threshold to $10M for nuclear or complex first-of-
a-kind projects. …The project management principles, as set forth in DOE O
413.3, Appendix C, Paragraph 1.a.-l., apply to all capital asset projects.”
b. As established by the NNSA policy decision, dated July 18, 2019, the Office of
Acquisition and Project Management (NA-APM) must assume the lead role for
execution and appoint a Federal Project Director (FPD) after the completion of
the AoA Alternative Selection Document until CD-4 approval.
c. Technology readiness assessments (TRAs) must be developed in accordance with
DOE Guide (G) 413.3-4A, Technology Readiness Assessments Guide, and NNSA
Policy (NAP) 413.4, Technology Readiness Assessments.
d. NNSA’s peer review policy and independent project reviews (IPR) must be
implemented in accordance with BOP 413.4, Project Reviews.
e. Independent cost estimates and reviews must be conducted in accordance with
NAP 413.3A, Responsibilities for Independent Cost Estimates, and Government
Accountability Office (GAO)-20-195G, Cost Estimating and Assessment Guide.
f. Projects designated as Hazard Category 1, 2, or 3 nuclear facilities must comply
with design safety requirements of DOE-Standard (STD)-1189-2016, Integration
of Safety in the Design Process, DOE O 413.3 project management processes, and
other applicable Codes of Federal Regulations (CFR).
g. When approved by the NNSA Administrator, Acquisition and Project
Management Offices (APMO) for Major System Acquisition (MSA) projects
must be established by NA-APM and led by a member of the Senior Executive
Service (SES).
(1) The APMO is tailored and staffed with project management,
acquisition, quality assurance, and technical subject matter expert(s)
(SME) to ensure scaled and sufficient oversight is provided in
accordance with the DOE G 413.3-19, Staffing Guide for Project
Management.
NNSA SD 413.3 3
05-18-21
(2) The APMO Director must have the appropriate acquisition and project
management training, experience, and certification level to ensure a
sound understanding of the FAR and a broad knowledge base from
which to communicate performance expectations between Contracting
Officer(s) (CO) and contractors so that NNSA successfully delivers on
the expectations identified in its Inter-Agency Agreements (IA),
contracts, and work authorizations.
8. RESPONSIBILITIES.
a. Administrator (NA-1).
(1) Delegates Project Management Executive (PME) authority, as
appropriate.
(2) Designates a project owner before Critical Decision (CD)-1.
(3) Ensures that the NA-APM FPD appointed to non-major system projects
is qualified and has appropriate communication skills and leadership
characteristics prior to designation.
(4) Serves as Chair and appoints members for Acquisition Advisory
Boards.
b. Associate Administrator for Acquisition and Project Management (NA-APM-1).
(1) Assists the Heads of NNSA Elements in developing CD-0 documents.
(2) Assumes the lead role in the execution of the project beginning with the
completion of the AoA ASD and continuing through the approval of
CD-4 to include developing the project execution documentation based
on the selected alternative for the project, developing and administering
the acquisition strategy and procurement plan, and awarding and
managing design and construction contracts/Inter-Agency
Agreement(s) (IAs) to achieve the project baseline.
Section 3
(3) Ensures all CD activities post AoA approval are completed and ensures
NNSA follows DOE’s acquisition and project management
requirements outlined in the DEAR, DOE O 413.3, and the
Department’s policies for aligning contracts and contract incentives
with taxpayer interests.
(4) Provides overall direction, strategic guidance, and management with
respect to the acquisition and management of capital asset projects and
ensures that NNSA implements all applicable federal and departmental
acquisition policies and regulations.
(5) Serves as a Member of the Project Management Risk Committee
4 NNSA SD 413.3
05-18-21
(PMRC) and coordinates projects greater than $100M with the PMRC.
(6) Obtains full time equivalent (FTE) allocations for FPD billets from
NA-1, hires, trains, supervises, and develops FPDs, and writes FPD
appointment memoranda.
(7) Manages the PME initial delegation memoranda, and any subsequent
delegations that may be appropriate if material changes in the project
occur after the initial delegation, drafts all CD approval memoranda,
and obtains subsequent approvals throughout the life of the project.
c. Director, Office of Enterprise Project Management (NA-APM-20). Approves
exemptions to this SD. This responsibility cannot be delegated.
d. Director, Office of Cost Estimating and Program Evaluation (NA-1.3-1).
(1) Advises NA-1 on policies and procedures for cost analysis, estimation,
and AoAs. Conducts the independent review of the AoA as outlined in
BOP 413.6, Analysis of Alternatives, or successor policy.
(2) Performs TRA responsibilities outlined in NAP 413.4, Technology
Readiness Assessments.
(3) Manages all CD phase independent cost estimates/reviews as outlined
in NAP 413.3A, Responsibilities for Independent Cost Estimates.
e. Associate Administrator for Safety, Infrastructure and Operations (NA-50-1).
(1) Enables safe operations, ensures effective infrastructure, and provides
enterprise services to meet the 21st century nuclear security enterprise
needs.
(2) Works with the FPD in integrating safety into the design of nuclear
construction projects and ensures DOE-STD-1189-2016, Integration of
Safety in the Design Process, is implemented for Hazard Category 1, 2,
and 3 nuclear facilities.
(3) Provides Environmental, Safety & Health; Waste Management; Quality
Assurance; and Nuclear Safety technical experts to support the
Integrated Project Team (IPT) and NNSA’s Independent Project Peer
Reviews.
(4) Provides Guiding Principles for Sustainable Federal Buildings,
Leadership in Energy & Environmental Design (LEED), and LEED
Gold waiver technical experts to support project teams. Delegates
Safety Basis approval to the Field Office Manager or approves Safety
Basis documents when the Field Office Manager lacks Technical
Qualification Program certification.
NNSA SD 413.3 5
05-18-21
f. Chief and Associate Administrator for Defense Nuclear Security (NA-70-1).
Ensures the field office security representatives to the IPT implement DOE’s
security orders and policies.
g. Associate Administrator for Information Management (NA-IM-1).
(1) Ensures the Heads of NNSA Element’s and field office’s information
management representatives to the IPT communicate and implement all
DOE and NNSA Information Technology (IT) and cybersecurity orders
and policies.
(2) Approves IT components in the design and procurement to be in
compliance with the Federal Information Technology Acquisition
Reform Act (FITARA).
Section 4
h. Associate Administrator for Management and Budget (NA-MB-1).
(1) Serves as the lead for conducting NNSA initiated AoAs, in accordance
with BOP 413.6, Analysis of Alternatives.
(2) At the discretion of the program offices and their specific budget
allocations, ensures funds for NA-APM products and services come
from the sponsoring NNSA Element’s appropriated funds, the details of
which are to be developed in accordance with the process in NNSA
Policy (NAP) 130.1A, Planning, Programming, Budgeting, and
Evaluation (PPBE) Process.
(3) Ensures programs comply with Department Orders, including DOE O
413.3, during the fiscal year Congressional budget process.
(4) Provides IPT representation to ensure programmatic cost estimates are
developed in accordance with NNSA policies and best practices.
(5) Assists the Heads of NNSA Elements, if requested, in developing the
Mission Need Statement (MNS) and Program Requirements Document
(PRD) to ensure an AoA can be accomplished in accordance with
standard practices.
i. Office of Project Analysis, Oversight and Review (NA-APM-1.1).
(1) Implements NNSA’s peer review policy and conducts Independent
Project Reviews (IPR) from CD-0 through CD-4, in accordance with
DOE/NNSA requirements.
(2) Provides feedback independent of NA-APM or Heads of NNSA
Elements through direct lines of communication to the Principal Deputy
Administrator (NA-2).
6 NNSA SD 413.3
05-18-21
(3) Serves as a member of the PMRC and briefs the PMRC on its IPRs.
j. Heads of NNSA Elements.
(1) Lead the development of the Mission Need Statement (MNS) and
establish the project requirements through the PRD.
(2) Participates in the AoA process in accordance with BOP 413.6,
Analysis of Alternatives.
(3) Manage requirements generation, develop the budget requests, fund
capital asset projects, including funding for FPD support governed by
DOE O 413.3, and monitor and approve scope changes as identified in
the Project Execution Plan (PEP) change control table.
(4) Upon project completion, assume responsibility for oversight of
operations of the completed project in accordance with Beneficial
Occupancy Date (BOD) guidance and verify that the mission need has
been met.
(5) As a capital asset project progresses through the various CD phases, is
responsible for the mission need, requirements, technical alternative
selection, budgets, and funding of capital asset projects governed by
DOE O 413.3.
k. Field Office Managers.
(1) If the authority has been delegated, approve the Documented Safety
Analysis and the Safety Evaluation Report.
(2) Upon project completion, provide oversight of operations of the
completed project in accordance with BOD guidance and verify that the
mission need was met.
l. Acquisition and Project Management Office Directors (APMOs). Provide overall
direction, strategic guidance, and management of the project office in
performance of all functions necessary to deliver the project in accordance with
its original approved performance management baseline.
m. Federal Project Director (FPD).
(1) Leads the IPT comprised of NNSA Elements and contractor personnel
(when appropriate but not required) and serves as the single point of
contact responsible for the overall execution of the project immediately
after completion of the AoA ASD through CD-4.
(2) Evaluates and verifies reported progress, provides project execution
metrics in accordance with guidance provided by NA-APM, provides
NNSA SD 413.3 7
05-18-21
Section 5
projections for future progress, and notifies senior management
whenever project performance indicates a likelihood of performance
baseline deviation.
(3) Serves to support and defend the project cost, schedule, performance,
and scope baselines, and ensures that the project receives adequate
resources and expertise in all necessary areas.
(4) Manages the CD-X performance baseline through monthly meetings
and invites representatives from the NNSA Elements and NNSA field
offices to attend to maintain situational awareness of project
performance.
(5) Serves as the Contracting Officer’s Representative (COR), upon
appointment.
n. Headquarters Project Manager (HQPM).
(1) Serves as the project management professional in NA-APM assigned to
a project when an MNS and PRD begin development.
(2) Serves as the primary advisor to the NNSA Elements to ensure that the
effort approved at CD-0 has sufficiently developed requirements to
proceed through pre-conceptual design to support the AoA. Helps
ensure that the MNS and PRD requirements are sufficiently developed
to allow the project to proceed with conceptual design if the selected
alternative were to become a capital asset line item/MIE project.
(3) Serves as the FPD after the completion of the AoA Alternative
Selection Document until one is assigned, and acts as the FPD in the
absence of the FPD throughout the life of the project. Remains with the
project through CD-4 and is the most knowledgeable on all aspects of
project management policies and procedures at every stage of the
project.
(4) Ensures communication flows swiftly through HQ Elements, that
decisions and actions are well documented, and are executed on a
schedule.
o. Senior Management Team (SMT).
(1) Comprised of SES representatives from the NNSA Elements identified
in the CD-X Preliminary Project Execution Plan (PPEP).
(2) Provides monitoring of the federal IPT, including providing input to
complex issues and making decisions based on recommendations,
through regular monthly meetings.
8 NNSA SD 413.3
05-18-21
(3) SMTs apply to all projects where the PME requests one be chartered.
p. Project Management Risk Committee (PMRC).
(1) Reviews CD packages with values greater than or equal to $750M for
CD-0.
(2) Reviews all CDs and makes recommendations to the pertinent PMEs
and the Energy System Acquisition Advisory Board (ESAAB) for
projects with a TPC greater than or equal to $1 00M, for CD-1 through
CD-4.
(3) Receives out-briefs on all independent project peer reviews.
9. ACRONYMS. See Appendix F.
10. REFERENCES. See Appendix G.
11. CONTACT. The Office of Enterprise Project Management, NA-APM-20, 202-586-
9814, NA-APM-20@nnsa.doe.gov.
BY ORDER OF THE ADMINISTRATOR:
Appendices:
�r.v�
Charles P. Verdon
Acting Administrator
A. Project Process - Critical Decision Requirements
B. Project Process - Overview of Roles and Responsibilities
C. Project Process - DOE Acquisition Management System for Line Item Capital Asset Projects
D. Conceptual and Preliminary Design Guidance
E. Beneficial Occupancy Guidance
F. Acronyms/ Abbreviations
G. References
NNSA SD 413.3 Appendix A
05-18-21 APA-1
APPENDIX A: PROJECT PROCESS – CRITICAL DECISION REQUIREMENTS
In order to apply project management best practices to capital asset projects post Analysis of
Alternatives (AoA) approval, a performance baseline must be established. This performance
baseline is defined as all cost, schedule, and scope required to complete all Critical Decision
(CD) activities between each of the CD phase approvals (CD-X, where X is 1, 2, or 2/3, as
applicable). Reporting progress for all phases of the project will be done following the
applicable Office of Acquisition and Project Management (NA-APM) standard practices.
Section 6
1. Pre CD-0: Prepare Mission Need for Approval.
a. Develop Mission Need. When a credible performance gap is identified between
current capabilities and those required to achieve the mission, the Heads of NNSA
Elements lead the development of a Mission Need Statement (MNS) that
translates mission need into functional requirements. The MNS must not be
written to assume any particular solution, whether material or non-material. It is
important that the Heads of NNSA Elements engage NA-APM at this phase so a
Headquarters Project Manager (HQPM) can be added to the project team. The
HQPM provides assistance to ensure applicable standard practices, policies, and
strategic guidance are followed to get the project off to a good start. Also see
Department of Energy (DOE) Guide (G) 413.3-17, Mission Need Statement.
b. Prepare the Program Requirements Document (PRD). The Heads of NNSA
Elements must develop and maintain the PRD during the life of the project, as
required by Business Operating Procedure (BOP) 413.2 Admin Chg. 1, Program
Requirements Document for Construction Projects. Before CD-1, the PRD
provides the framework from a program perspective for NA-APM’s development
of the acquisition strategy.
c. Identify and Provide Funding. The responsible Heads of NNSA Elements
establish the Rough Order of Magnitude cost range and provide funding for
capital asset projects from appropriated funds. The Heads of NNSA Elements
formulate the budget details in accordance with NAP 130.1A, Planning,
Programming, Budgeting, and Evaluation (PPBE) Process. The Heads of NNSA
Elements are responsible for ensuring adequate resources, including Other Direct
Costs to support the FPD, are provided throughout the CD process.
2. Post CD-0/Pre CD-1: Prepare Alternative Selection and Cost Range for Approval.
a. Establish and Manage the Integrated Project Team (IPT). Upon approval of the
mission need for a capital asset project, the Heads of NNSA Elements establish an
IPT comprising NNSA field office personnel, NNSA Element personnel, project
and acquisition professionals, subject matter experts, and contractors (when
appropriate but not required) and other federal organizations. Leadership of the
IPT transitions to the NA-APM Federal Project Director (FPD) after completion
of the AoA Alternative Selection Document (ASD). NA-APM assigns project
and acquisition professionals to the IPT to support the development of all project
requirements. It is important to include representatives from the Office of Safety,
Appendix A NNSA SD 413.3
APA-2 05-18-21
Infrastructure, and Operations (NA-50) to advise on nuclear safety and
infrastructure issues; the Office of Defense Nuclear Security (NA-70) to advise on
safeguards and security; the Office of Information Management (NA-IM) to
advise on IT Standards, Enterprise Architecture, and Cybersecurity; and
Management and Budget (NA-MB) to advise on AoA’s and cost estimation, as
well as other subject matter experts who would contribute to the success of the
project. Also see DOE G 413.3-18A, IPT Guide for Formation and
Implementation.
b. FPD Appointment. NA-APM identifies the appropriately certified FPDs who can
be assigned to specific projects. The FPD is assigned after completion of the
AoA ASD.
Section 7
c. Develop Alternatives and Finalize AoA. For projects seeking CD-1 approval,
NA-MB conducts an AoA that is independent of the contractor organization that
would benefit from the proposed project (e.g., Management and Operating
Contractor, [M&O]). The AoA must be conducted in accordance with BOP
413.6, Analysis of Alternatives. For additional information, see GAO-16-22,
AMPHIBIOUS COMBAT VEHICLE: Some Acquisition Activities Demonstrate
Best Practices; Attainment of Amphibious Capability to be Determined. It is
important that the Heads of NNSA Elements engage early with NA-MB to
understand the requirements for the AoA, both in terms of process and products.
NA-1.3 will conduct an independent review of the completed AoA.
d. Develop the Acquisition Strategy. NA-APM develops the acquisition strategy, in
consultation with the Heads of NNSA Elements, to identify the high-level plan for
satisfying the mission need in the most effective, economical, and timely manner.
The Acquisition Strategy must be approved by the Program Secretarial Officer
(PSO) prior to the CD-1 Energy System Acquisition Advisory Board (ESAAB)
(or Equivalent Energy Systems Acquisition Advisory Board Equivalent (ESAAB-
E) meeting. After approval of the Acquisition Strategy and CD-1, the responsible
Contracting Officer (CO) develops and documents the Acquisition Plan to specify
the contract type in accordance with sound business practices, statutory,
regulatory, and policy requirements, which is approved by the Senior
Procurement Executive or designee. For additional information, see NA-APM
Standard Practice 02, Acquisition Strategy; DOE G 413.3-13, Acquisition Strategy
Guide for Capital Asset Projects; DOE Acquisition Guide, Chapter 7; and Federal
Acquisition Regulation (FAR) parts 7 and 34.
e. Develop the CD-1 Preliminary Project Execution Plan (PPEP). NA-APM leads
the development of the CD-1 PPEP, which describes the organizational
framework and overall management system for the project from AoA approval to
CD-1 approval. The CD-1 PPEP should be submitted for approval within 30 days
of the AoA approval. Concurrent with initiating the development of the CD-1
PPEP, NA-APM leads the development of the Design Management Plan (DMP).
After the CD-1 PPEP is approved, NA-APM must develop the project’s safety
basis and CD-1 performance baseline to manage the cost, schedule, and scope to
NNSA SD 413.3 Appendix A
05-18-21 APA-3
CD-1 approval. NA-APM, the program manager, and the Project Management
Executive (PME) approve scope changes in accordance with the change control
thresholds in the approved CD-1 PPEP. The CD-1 PPEP must include
preliminary key performance parameters. For additional information see DOE G
413.3-15A, Project Execution Plans.
f. Develop the DMP. NA-APM leads the development of the DMP, which
establishes the anticipated levels of design maturity at each CD phase. The DMP
must be developed as early as possible after approval of the AoA to ensure that
design activities are executed to the defined plan. The main purpose of the DMP
is to define the approach for execution of design activities and to ensure that
quality and consistency are maintained throughout the design process. The DMP
includes the appropriate CD-1 and CD-2 performance baselines to manage the
cost, schedule, and scope of the design effort. The DMP is tailored to both
design-bid-build and design-build projects. For additional information see DOE
G 413.3-1, Managing Design and Construction Using Systems Engineering.
Section 8
g. Develop the Conceptual Design. The NA-APM FPD leads the conceptual design
team. As a part of this effort, the FPD prepares a CD-1 PPEP that defines roles
and responsibilities, a DMP, and implements a CD-1 performance baseline with
change control protocols. Development of the conceptual design is an iterative
process to define, analyze, and refine project concepts using a systems
engineering methodology. The conceptual design conforms to the design
guidance in Appendix D, (Conceptual and Preliminary Design Guidance).
Progress updates and design development status are provided to senior leaders
through monthly briefings.
h. Develop the CD-2 PPEP. The FPD is responsible for updating the CD-1 PPEP to
describe the organizational framework and overall management system for the
project from CD-1 approval to CD-2 approval. The CD-2 PPEP must be
approved prior to CD-1 approval. Included in the update to the PPEP, NA-APM
must identify the CD-2 performance baseline to manage the cost, schedule, and
scope to CD-2 approval. NA-APM, the program manager, and PME approve
scope changes in accordance with the change control thresholds in the approved
CD-2 PPEP. For additional information see DOE G 413.3-15A, Project
Execution Plans.
i. Exemptions, Equivalencies, and Waivers. A project may seek exemptions or
equivalencies to the requirements in DOE directives in accordance with the
process described in DOE O 251.1D, Departmental Directives Program,
Appendix E. Examples include an equivalency for fire protection system
requirements, an exemption from a natural phenomenon hazard requirement, a
waiver from meeting Leadership in Energy & Environmental Design (LEED)
Gold certification as required by DOE 413.3, etc. Such exemptions,
equivalencies, and waivers represent a risk to the project until approved. Projects
requesting an exemption, equivalency, or waiver should place a high priority on
having the request approved before the final conceptual design report. If they are
Appendix A NNSA SD 413.3
APA-4 05-18-21
not approved prior to the final conceptual design report, the associated risk
item(s) should be carried in the risk register and the project estimate should
include the unrealized risk value. The Associate Administrator for Acquisition
and Project Management (NA-APM-1) may allow requests that have not been
approved beyond the final conceptual design report under special circumstances
and such items should be discussed as major issues in the monthly project reviews
until disposition is completed.
3. Post CD-1/Pre CD-2: Prepare Performance Baseline for Approval.
a. Baseline Development. NA-APM formalizes the cost, schedule, and scope of a
project at CD-2, and measures success against this baseline at project completion,
including key performance parameters. The project requirements, identified in
the approved PRD, and proposed funding profile are used to develop the project
cost and schedule baseline. The FPD is responsible for developing the total
project performance baseline, which is validated by NA-APM or the DOE Office
of Project Management (DOE-PM) based on the dollar threshold outlined in DOE
O 413.3. The FPD obtains concurrence of the project baseline from the Heads of
NNSA Elements, through concurrence on the Project Execution Plan (PEP), and
obtains approval from the PME through the ESAAB process. The preliminary
design must conform to the design guidance in Appendix D. Prior to baseline
approval, nuclear project designs must conform to the design criteria specified in
DOE O 413.3. During the period between CD-1 and CD-2, the FPD monitors the
CD-2 performance baseline performance using project management principles
and Earned Value Management (EVM) methodologies and techniques, in
preparation for approval of CD-2, Approve Performance Baseline.
Section 9
b. Establish a Project Management Office (PMO), if applicable. A PMO provides a
full-time team dedicated to the project to ensure project delivery is in accordance
with the established cost, schedule, and scope baselines. For a Major System
Acquisition (MSA) project, NA-APM determines if a PMO should be established.
Establishment of a PMO must be approved by the Administrator (NA-1).
c. Develop the PEP. The FPD is responsible for drafting and updating the PEP prior
to CD-2 approval. The PEP is a living document that is based on the CD-2 PPEP
and must be updated to capture changes to project systems, processes, procedures,
and personnel. The FPD, program manager, NA-APM, and PME approve scope
changes in accordance with the change control thresholds in the approved PPEP
or PEP.
d. Plan for Site Integration. The FPD, Heads of NNSA Elements, through the IPT,
establish a plan for site integration. Planning for site integration involves
identifying site interface issues and infrastructure requirements in order to
mitigate barriers to construction execution. Clear organizational interface and
responsibilities need to be documented and agreed upon by all involved parties, as
codified in the PPEP or PEP, Commissioning Plan, and Startup Plan, or as a
standalone plan.
NNSA SD 413.3 Appendix A
05-18-21 APA-5
e. Award and Administer Design Contracts or Interagency Agreements (IAs).
Design contracts or IAs are awarded and managed according to the DMP. NA-
APM or its agent awards design contracts, work authorizations, and IAs to
support project requirements. To ensure successful outcomes, close coordination
is expected between acquisition staff across the enterprise. Design progress and
performance is measured against the CD-2 performance baseline.
f. For conventional, non-nuclear construction, the design can be less than 90%
complete prior to CD-2. Through an IPR, NA-APM ensures that adequate
definition exists to provide a budget quality cost and schedule estimate for the
total project performance baseline. Projects designated as Hazard Category 1, 2,
or 3 nuclear facilities must achieve at least 90% design maturity before CD-2.
4. Pre CD-3A: Long Lead Procurements. A CD-3A package can be submitted in
conjunction with another CD or separately. Some potential reasons to pursue a CD-3A
authorization include the following:
a. Purchasing long-lead materials or long-lead equipment.
b. Fabrication requirements.
c. Limited site preparations — Some examples include removal of existing equipment
or acquiring the lay-down area.
5. Pre CD-2/3: Approve Performance Baseline and Start of Construction Execution. The
preparations for a CD-2/3 submittal package include all the activities necessary for both
the CD-2 and CD-3 submission combined in the same submittal package. A CD-2/3
approval is particularly useful when pursuing design-build.
6. Post CD-2/Pre CD-3: Prepare for Construction Execution Start.
a. Complete Project Design. After the Project Baseline is approved, the FPD
completes the project definition/design, begins to execute the Acquisition
Strategy, and initiates early procurements.
b. Manage the Project Baseline. The FPD manages the project baseline by
overseeing and evaluating the progress of the project through CD-4. The FPD
evaluates performance against cost, schedule, and scope. NA-APM monitors
performance through monthly meetings and invites representatives from the
Heads of NNSA Elements to attend to maintain situational awareness of project
performance.
Section 10
Appendix A NNSA SD 413.3
APA-6 05-18-21
c. The FPD updates the baseline in accordance with the change control thresholds in
the PEP when there is a new requirement or a change to the cost, schedule, or
scope.
7. Post CD-3/Pre CD-4: Prepare for Start of Operations or Project Completion.
a. Award Construction Contracts and IAs. NA-APM or its agent awards
construction contracts, work authorizations, and IAs to support project
requirements. To ensure successful outcomes, close coordination is expected
between contracting staff across the enterprise.
b. Manage Construction Contracts and IAs. NA-APM or its agent oversees and
manages construction services through contracts and IAs to achieve the project
baseline.
c. Manage Site Integration Issues. The FPD takes the lead role in managing any site
integration issues, in support of construction activities, with the NNSA Elements,
Nuclear construction projects must also comply with design safety requirements
of DOE-STD-1189-2016, Integration of Safety in the Design Process.
d. Prepare for Transition to Operations. In close coordination with Heads of NNSA
Elements, the FPD is responsible for developing and managing startup, turnover,
and closeout plans in accordance with DOE O 413.3. Activities include checkout,
testing, and operations acceptance; completing a transition to operations plan;
performing final project inspections; conducting a commissioning evaluation; and
preparing for an Operational Readiness Review, a Readiness Assessment, or a
Readiness to Operate Assessment. Heads of NNSA Element’s involvement in
these activities is essential for project success.
e. Establish Beneficial Occupancy Date (BOD). The stage of construction of a
building or facility, before final completion, at which its user can occupy it for the
purpose for which it was constructed. Beneficial occupancy does not imply that a
project has reached CD-4. The BOD is the date that follow-on contracts/activities
(if any) such as information technology or furniture installations may begin. For
large projects there may be multiple BODs and the BOD does not replace CD-4.
A construction schedule identifying the BOD is developed and used as the basis
for establishing reasonable contract duration(s) at CD-2. The scheduled BOD is
reviewed in conjunction with routine monthly project reporting and adjusted as
required to reflect the best estimate for when the BOD actually occurs. Revisions
to the scheduled BOD must be reviewed and coordinated with the FPD and
customer prior to being entered into the change control process.
8. Post CD-4: Prepare for Project Closeout.
a. Accept Project for Operations. Heads of NNSA Elements verify the mission need
and project requirements are met and accept the project for operation in
accordance with the PEP.
https://nnsaportal.energy.gov/intranet/na-apm/NA-APM-20/ShortCuts/DID-PRG-0001-CheckoutTestingandOperationsAcceptance.aspx
NNSA SD 413.3 Appendix A
05-18-21 APA-7
b. Turnover to Operations and Conduct Closeout Activities. Upon acceptance, the
FPD continues to provide monthly project reviews with all IPT members until
closeout activities are completed. This includes completing any punch list items,
managing warranty issues, completing contracts/IAs, and conducting closeout
activities.
c. Project Closeout. The FPD prepares the project documents for PME approval,
schedules the ESAAB or ESAAB-E, and officially closes the project out in the
DOE Project Assessment and Reporting System. Also see BOP 413.8, Energy
Systems Acquisition Advisory Board Equivalent (ESAAB-E) Process for more
information on the ESAAB process.
Section 11
NNSA SD 413.3 Appendix B
05-18-21 APB-1
APPENDIX B: PROJECT PROCESS – OVERVIEW OF ROLES AND
RESPONSIBILITIES
Project Phase Office of Acquisition and Project
Management (NA-APM) Roles &
Responsibilities
Heads of NNSA Elements Roles &
Responsibilities
Pre CD-0:
Approve
Mission Need
Support: Be aware of the need for a
capital asset project and appoint a
Headquarters Project Manager (HQPM) to
provide assistance, as needed. Review and
support the development of the cost range.
Lead: Generate mission need and program
requirements. Finalize the Mission Need
Statement (MNS) and Program Requirements
Document (PRD). Identify and provide
funding. Establish the Rough Order of
Magnitude cost range.
Pre CD-1:
Approve
Alternative
Selection and
Cost Range
Lead: After completion of the Analysis of
Alternatives (AoA) Alternative Selection
Document (ASD): Assign the NA-APM
Federal Project Director (FPD). Manage
the conceptual design with change control
discipline. Ensure that project
requirements are met. Develop the
acquisition strategy and procurement plan.
Develop the Preliminary Project Execution
Plan (PPEP). Develop the Design
Management Plan. Develop the Critical
Decision (CD)-1 performance baseline
with protocols for change control. Assign
acquisition professionals to the Integrated
Project Team (IPT).
Support: Prior to completion of the AoA
ASD.
Assist in AoA development and analysis.
Identify the FPD that will be assigned to
manage the project.
Lead: Prior to completion of the AoA ASD:
Establish and manage the Integrated Project
Team (IPT). Conduct the AoA. Develop project
budget and supporting Project Data Sheets.
Identify and provide funding.
Support: After completion of the AoA ASD:
Review the Design Management Plan (DMP)
and the CD-1 performance baseline. Assist in
preparation and approval of the PPEP. Approve
scope changes per the change control table in the
PPEP. Review conceptual design deliverables
and approve any deviations from the DMP or
CD-1 performance baseline.
Pre CD-2:
Approve
Performance
Baseline
Lead: Agree to a cost based on approved
scope and schedule. Award design
contracts/IAs to support project
requirements. Develop the CD-2
performance baseline. Complete project
design and begin/manage design and
development of project execution
documentation on the selected alternative for
the project. Develop the Project Execution
Plan (PEP). Develop project baseline.
Prepare request to the Project Management
Executive (PME) for approval of project
baseline.
Lead: Manage/adjust project requirements, as
necessary, to meet mission needs. Concur with
proposed baseline and manage/establish project
budget accordingly.
Support: Review design deliverables. Assist
in the preparation and development of the
CD-2 performance baseline, PEP, and
acquisition strategy and, ultimately, provide
concurrence/approval of the final products.
Appendix B NNSA SD 413.3
APB-2 05-18-21
Support: Incorporate any changes in
project requirements identified by the
Heads of NNSA Elements.
Pre CD-3:
Approve Start
of
Construction
Execution
Lead: Initiate acquisition award construction
contracts/Inter-Agency Agreement(s) (IAs).
Through IPT, identify and plan for site
integration. Initiate early procurements.
Manage project baseline.
Support: Work with Heads of NNSA Elements
to mitigate barriers to construction execution.
Develop and adjust requirements to
accommodate any changes to the project
identified by the Heads of NNSA Elements.
Provide information necessary for trade-off
analysis and decisions.
Section 12
Lead: Make trade-off decisions during design
that impact project requirements or costs.
Identify any changes required to meet mission
needs. Identify site integration issues. Provide
funding in accordance with approved baseline.
Support: Participate in monthly project reviews
to ensure project requirements are met.
Pre CD-4:
Approve Start
of Operations
or Project
Completion
Lead: Manage construction contract(s)/IAs to
achieve project baseline. Manage site
integration issues. Identify and request baseline
changes for any unforeseen changes or project
requirement changes identified by the Heads of
NNSA Elements.
Perform project final inspections and
commissioning evaluation. Initiate and execute
pre-operational readiness evaluations.
Implement approved changes identified by the
Heads of NNSA Elements.
Lead: Identify any changes required to meet
mission needs/project requirements. Approve
Documented Safety Analysis and Safety
Evaluation Report, if applicable. Manage
project budget. Initiate plan for future
operations of completed project.
Support: The Chief of Defense Nuclear Safety
(NA-70-1) is responsible for ensuring DOE-
STD-1189-2016 is integrated into the project.
The Field Office Manager is responsible for
approving the Documented Safety Analysis and
the Safety Evaluation Report, if applicable.
Defense Nuclear Security (NA-70) is
responsible for integrating security into the
project.
Post CD-4:
Project Closeout
Lead: Turnover completed project to
operations. Complete any punch list items and
manage warranty issues. Complete contract(s)
and project closeout activities.
Lead: Evaluate/accept project for operations and
verify mission need/requirements are met.
*This table is a summary with specific roles and responsibilities outlined in accordance with
the PPEP/PEP.
NNSA SD 413.3 Appendix C
05-18-21 APC-1
APPENDIX C: DOE ACQUISITION MANAGEMENT SYSTEM FOR LINE ITEM
CAPITAL ASSET PROJECTS
The DOE Acquisition Management System for Line Item Capital Asset Projects Illustration is
provided for context to explain NNSA’s Capital Asset Acquisition and Project Management
process.
NNSA SD 413.3 Appendix D
05-18-21 APD-1
APPENDIX D: CONCEPTUAL AND PRELIMINARY DESIGN GUIDANCE
Appendix D NNSA SD 413.3
APD-2 05-18-21
Conceptual and Preliminary Design General Guidance
Item Project Type Conceptual Design Preliminary Design
General Definition
Hazard Category 1, 2, or 3
Nuclear Facility
A design milestone at which
efforts are refocused from
alternative comparisons and
selection to the production of
an initial design that
integrates safety-in-design in
accordance with DOE-STD-
1189 and DOE Order 413.3
project management
processes.
A design milestone that occurs
between conceptual design and the
final design. Preliminary design
advances the conceptual design to
reflect a more mature safety basis
in accordance with DOE-STD-1189
and other DOE Order 413.3 project
management processes. The
preliminary design transitions to
formal configuration control to
ensure the final design fulfills the
mission need.
All Other Facilities
The design milestone at
which efforts are refocused
from alternative comparisons
and selection to the
production of an initial design
that integrates project
requirements and DOE
Order 413.3 project
management processes.
The design milestone that occurs
between conceptual design and the
final design. Preliminary design
advances the conceptual design
complying with project
requirements, DOE Order 413.3
project management processes,
and transitions to formal
configuration control to ensure the
final design fulfills the mission
need.
Section 13
Design Maturity
Hazard Category 1, 2, or 3
Nuclear Facility 30% 60%
All Other Facilities 15% 40%
Estimate Class1
Hazard Category 1, 2, or 3
Nuclear Facility
Association for the
Advancement of Cost
Engineering International
(AACEI) Class 4
AACEI Class 3
All Other Facilities AACEI Class 3 AACEI Class 2
Design Cost Relationships2
As a percentage of
total project cost
Hazard Category 1, 2, or 3
Nuclear Facility 5% 15%
All Other Facilities 1% 2%
As a percentage of
total construction
costs
Hazard Category 1, 2, or 3
Nuclear Facility 7% 20%
All Other Facilities 1% 3%
As a percentage of
total design costs
Hazard Category 1, 2, or 3
Nuclear Facility 25% 75%
All Other Facilities 15% 30%
1. Reference AACEI Recommended Practice 18-R-97, Cost Estimate Classification System – As Applied in Engineering, Procurement, and
Construction for the Process Industries, dated 1 March 2016, for additional information on AACEI estimating classes.
2. Design cost relationships include “all-in” costs except for the DOE-held contingency and DOE other direct costs. The cost relationships for
preliminary design are cumulative values.
NNSA SD 413.3 Appendix D
05-18-21 APD-3
Conceptual Design Deliverables for Capital Line Item Projects
All deliverables are assumed to be based on best available information and unsuitable for
issuance for final design, procurement, or construction. The degree of completion for the
deliverables are defined as outlined below.
• N/A – Deliverable is not applicable or required.
• Conceptual – Work on the deliverable is not advanced with interim and cross-functional
reviews typically completed. Often the deliverable is assigned an alpha revision number
rather than a numeric revision number to designate that it is not under a formal configuration
control system.
• Complete – Work on the deliverable is complete and the final configuration has been
reviewed (both intra- and inter-discipline) and approved. The deliverable is assigned a
numeric revision number to designate that it is under a formal configuration management
process because changes to the deliverable may result in major schedule and cost impacts.
The deliverable will continue to be revised under a formal configuration management process
as the design matures to 100%.
Conceptual Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
Architectural • Elevation drawings
• General (finished floor plan, reflected ceiling plan, finish schedule)
• Life safety plan/reports/drawings
• Plan and section drawings
• Select typical details
Conceptual Conceptual
Basis of Design • Code of Record
• System design descriptions (or alternative)
Conceptual N/A
• Design criteria
• Operations, maintenance, and radiation protection requirements
• Scope of facilities/interface control documents
• Security design requirements document
• System requirements identified
Conceptual Conceptual
Civil • Construction specifications
• Excavation and structural fill plan
Studies/analyses/drawings/plans
Conceptual Conceptual
• Qualitative geotechnical comparison of site alternatives
• Geotechnical review and evaluation of past projects and proposed
use area
Complete Complete
• Geotechnical Report Complete Conceptual
Appendix D NNSA SD 413.3
APD-4 05-18-21
Conceptual Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
Section 14
Electrical • Drawings and plans
• Electrical load list
• Identify applicable codes and standards
• One-line diagram
• Power distribution system layout (load centers, switchgear, Motor
Control Centers (MCCs) panel boards. Substation layout
drawings (as applicable, include distribution system to new facility
duct bank, overhead lines)
Conceptual Conceptual
Environmental
Management
• Environmental compliance strategy
• National Environmental Policy Act strategy determination
Complete Complete
Fire Protection • Identify applicable codes and standards
• Commodity lists (e.g., valve list, equipment list)
• Major equipment sizing design analysis calculations
• Piping and instrumentation diagram (P&IDs)
• Piping diagrams (including sprinkler heads)
Conceptual Conceptual
• System design descriptions Complete Complete
Heating,
Ventilation, and
Air Conditioning
(HVAC)
• Identify applicable codes and standards
• Air flow diagrams
• Preliminary duct routing (major runs)
• Preliminary equipment list
• Preliminary heating/cooling loads
• Ventilation and instrument diagrams
Conceptual Conceptual
• System design description Complete Complete
Instrumentation &
Controls (I&C)
• Control requirement general strategy (manual, semi, automatic)
for safety instrumented system (SIS) & basic process control
system (BPCS) requirements
Conceptual
(BPCS & SIS)
Conceptual
(BPCS only)
• Control system architecture
(implementation strategy for compliance with requirements)
• Input/output list
• Identify applicable codes and standards
• Issue drawings depicting I&C sensors and end devices. These
may be drawings that are owned by others (e.g., process
engineering, mechanical, HVAC)
Conceptual Conceptual
Mechanical,
Process, Piping
• Calculations/ analyses/reviews for commodities such as
gloveboxes, skids
• Identify applicable codes and standards
• Major equipment sizing design analysis calculations
• Mechanical equipment list (MEL)
• Preliminary P&IDs
• Process flow diagrams (PFDs); material and energy balance,
utility flow diagrams
• Reliability, availability, and maintainability parameters identified
for key systems
• Throughput analysis
• Utility demand
Conceptual Conceptual
Mechanical,
Process, Piping
• System design descriptions Complete Complete
NNSA SD 413.3 Appendix D
05-18-21 APD-5
Conceptual Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
Plant Design • 3D model software
• 3D model: major commodities
• Space allocation plan implemented
• General arrangement drawings
• Plot plan
• Select piping specifications/piping class sheets
Conceptual Conceptual
Safety in Design
and Safety Basis
• Conceptual Design Report
• Configuration management process
• Integrated Safety Management Plan
• Major modification determination
(for any modification requiring design)
• Preliminary Fire Hazard Analysis for the preferred alternative
• Risk and opportunities assessments
Complete Complete
• Preliminary security vulnerability assessment
• Conceptual Safety Design Report
• Criticality safety program document and studies/analyses
(e.g., nuclear criticality safety assessments/evaluations and
criticality safety process studies)
• DOE prepares a Conceptual Safety Validation Report
• Safety design strategy
• Specify safety functions & classifications for structures and facility
level systems
Complete N/A
• Preliminary Hazard Analysis Report N/A Complete
Section 15
Structural • Base mat drawings
• Concrete/steel drawings
• Framing plans/sections
• Preliminary finite element model for structural analysis
• Scoping calculations (preliminary)
• Structural design drawings/plans
Conceptual Conceptual
Appendix D NNSA SD 413.3
APD-6 05-18-21
Preliminary Design Deliverables for Capital Line Item Projects
All deliverables are based on best available information and unsuitable for issuance for final
design, procurement, or construction. The degree of completion for the deliverables are defined
as outlined below.
• N/A – Deliverable is not applicable or required.
• Preliminary – Work on the deliverable has matured beyond conceptual with interim and
cross-functional reviews typically completed, but not approved as final. A minimum of two
reviews is typical if the deliverable was initially developed in the conceptual design phase.
Some deliverables (e.g., selected enlarged floor plans, lightning protection drawings, etc.) may
be issued for the first time in preliminary design. The deliverable is assigned a numeric
revision identifier to designate that it is under a formal configuration management process
because changes to the deliverable may result in major schedule and cost impacts. This is
particularly true for design media and safety basis documents. Deliverable will continue to be
revised, under a formal configuration management process, as the design matures to 100%.
• Complete – Work on the deliverable is complete and has been reviewed (both intra- and inter-
discipline) and approved as final. The deliverable is assigned a numeric revision identifier to
designate that it is under a formal configuration management process because changes to the
deliverable may result in major schedule and cost impacts. The deliverable will continue to be
revised under a formal configuration management process as the design matures to 100%.
Preliminary Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
Architectural • Leadership in Energy & Environmental Design (LEED) scorecards Complete Complete
• Drawings (general)
• Finish schedule; door schedule
• Interior design
• Life safety plans/reports/drawings
• Major floor plans
• Major sections and elevation drawings
• Remaining typical detail and select specific detail drawings,
if required
• Selected enlarged floor plans
Preliminary Preliminary
Basis of Design • Preliminary reliability, availability, maintainability, and inspectability
analysis
• Scope of facilities/interface control documents
Preliminary Preliminary
• Code of Record Complete N/A
• Design criteria
• System requirements identified
Complete Complete
Civil • Studies/analyses/drawings/plans Preliminary Preliminary
• Geotechnical Report Complete Complete
NNSA SD 413.3 Appendix D
05-18-21 APD-7
Preliminary Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
Electrical • Drawings (general)
• Electrical load list
• Electrical load study design analysis calculations
• Equipment grounding plans
• Heat load design analysis calculations issued
(electrical equipment and power cabling)
• Lightning protection drawings and details
• Overall ground grid plan
• Panel/MCC/switchgear schedules
• Single-line diagrams
Preliminary Preliminary
Environmental
Management
• Environmental qualification for safety SSCs Complete N/A
Section 16
• National Environmental Policy Act (NEPA) Strategy Complete Complete
Fire Protection • Exemptions and equivalencies for fire protection
• Fire protection system design description
• Fire protection utility flow diagrams, P&IDs, sprinkler distribution
drawings and alternative fire protection/suppression systems
• Section and detail drawings
• Design analysis calculations
Preliminary Preliminary
General • Construction specifications, if applicable
• Equipment and material service requisitions, if applicable
Complete Complete
Heating,
Ventilation, and
Air Conditioning
(HVAC)
• Air flow diagrams
• Ventilation and instrumentation diagram (V&IDs) and associated
lists
Complete Complete
• Air flow design analysis calculations
• Confinement zone drawings
• Duct sizing and fan supply/exhaust design analysis calculations
• Heating/cooling load calculations
• System design descriptions
Preliminary Preliminary
Instrumentation &
Controls (I&C)
• Cabinet/panel layouts
• Control strategy for process and safety systems
• Instrument/panel location drawings
• Instrument installation details
• Instrument list/equipment list
• Instrument specifications
• Security systems layouts
• Telecommunication systems architectural drawings
Preliminary Preliminary
• Major equipment specifications Complete Complete
• Safety integrity level (SIL) calculations in schedule
OR compliant with IEEE 379
Complete N/A
Mechanical,
Process Piping
• Equipment and fabrication specifications for specialty equipment,
if applicable
• Material energy balance (MEB)
• Mechanical handling diagrams (MHDs)
• P&ID Lists (equipment, valve, line, specialty items)
• P&IDs for process and utility systems
• Process Flow Diagram(PFDs) for process and utility systems
• Throughput analysis
Complete Complete
Appendix D NNSA SD 413.3
APD-8 05-18-21
Preliminary Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
• System design descriptions for process systems
• System design descriptions for utilities
Mechanical,
Process Piping
• Environmental qualification for Safety Structures, Systems, and
Components (SSCs)
Complete N/A
• Common component drawings for commodities such as
gloveboxes and process skids
• Drain sizing design analysis calculations
• Electrical load tabulations
• Equipment requirement reports (e.g., ergonomic analysis, time
and motion studies, corrosion/erosion evaluations)
• Hydraulic evaluation/line sizing/equipment sizing design analysis
calculations
• Mechanical assembly layout drawings
• Pipe loading design analysis calculations
• Process gas flow design analysis calculations
Preliminary Preliminary
Plant Design • 3D model: major commodities
(HVAC, pipe, gloveboxes, radio hoods).
• 3D model: major equipment modeled
Complete Complete
• 3D model: process equipment and supports are modeled,
if applicable for CD-3A
• Equipment location drawings
• General arrangement drawings
• Material specifications
• Piping specifications/piping class sheets
• Plot plan
Preliminary Preliminary
Safety in Design
and Safety Basis
• Preliminary fire hazards analysis
• Checkout/Testing/Commissioning Plan
• Hazard analysis report
• Preliminary security vulnerability assessment
• Risk and opportunities assessment
Complete Complete
• Summary of key design activities
• Functional classification and Natural Phenomena Hazard Design
Category categorization for all Safety Class, Safety Significant,
and Defense-in-Depth SSCs
Section 17
• Preliminary safety and design results
• Safety design strategy
Complete N/A
• Criticality safety studies (e.g., nuclear criticality safety
assessments/evaluations and criticality safety process studies)
• Hazard analysis documents
• Hazard and accident analysis
• Preliminary quality level determinations or functional
classifications for all systems
Preliminary N/A
Structural • Anchor force and member sizing design analysis calculations for
mechanical equipment and large electrical equipment, including
electrical/instrument trays or racks
• Material specifications
• Selected material requisitions
• Structural design analysis calculations
Preliminary Preliminary
NNSA SD 413.3 Appendix D
05-18-21 APD-9
Preliminary Design Deliverables
Category Requirement / Deliverable
Degree of Completion
Haz Cat 1, 2, or 3
Nuclear Facility
All Other
Facilities
• Seismic evaluation study Complete Complete
NNSA SD 413.3 Appendix E
05-18-21 APE-1
APPENDIX E: BENEFICIAL OCCUPANCY GUIDANCE
Appendix E NNSA SD 413.3
APE-2 05-18-21
NNSA SD 413.3 Appendix F
05-18-21 APF-1
APPENDIX F: ACRONYMS/ABBREVIATIONS
a. AACEI Association for the Advancement of Cost Engineering International
b. AoA Analysis of Alternatives
c. APM Acquisition and Project Management
d. APMO Acquisition and Project Management Office
e. ASD Alternative Selection Document
f. BOD Beneficial Occupancy Date
g. BPCS Basic Process Control System
h. CD Critical Decision
i. CD-X Critical Decision-X, where (X) is 1,2,3
h. CO Contracting Officer
j. COR Contracting Officer Representative
k. DEAR DOE Acquisition Regulations
l. DMP Design Management Plan
m. DOE-PM DOE Office of Project Management
n. EIR External Independent Review
o. ESAAB Energy Systems Acquisition Advisory Board
p. ESAAB-E Energy Systems Acquisition Advisory Board - Equivalent
q. EVM Earned Value Management
r. FAR Federal Acquisitions Regulation
s. FITARA Federal Information Technology Acquisition Reform Act
t. FPD Federal Project Director
u. FTE Full Time Equivalent
v. G Guide
w. GAO Government Accountability Office
Appendix F NNSA SD 413.3
APF-2 05-18-21
x. GPP General Plant Project
y. HQPM Headquarters Project Manager
z. HVAC Heating, Ventilation, and Air Conditioning
aa. I&C Instrumentation & Controls
bb. IA Inter-Agency Agreement
cc. ICE/R Independent Cost Estimate/Review
dd. IPR Independent Project Review
ee. IPT Integrated Project Team
ff. IT Information Technology
gg. LEED Leadership in Energy and Environmental Design
hh. M Million
ii. M&O Management and Operating Contractor
jj. MCC Motor Control Center
kk. MEB Material Energy Balance
ll. MHD Mechanical Handling Diagram
mm. MNS Mission Need Statement
nn. MSA Major System Acquisition
oo. NEPA National Environmental Policy Act
pp. O Order
qq. OFPP Office of Federal Procurement Policy
rr. OMB Office of Management and Budget
ss. P&ID Piping and Instrumentation Diagram
tt. PB Performance Baseline
uu. PED Project Engineering and Design
vv. PEP Project Execution Plan
NNSA SD 413.3 Appendix F
05-18-21 APF-3
ww. PFD Process Flow Diagram
xx. PM Project Management
yy. PME Project Management Executive
zz. PMRC Project Management Risk Committee
aaa. PPBE Planning, Programming, Budgeting and Evaluation
bbb. PPEP Preliminary Project Execution Plan
ccc. PRD Program Requirements Document
ddd. SES Senior Executive Service
eee. SIL Safety Integrity Level
fff. SIS Safety Instrumented System
ggg. SME Subject Matter Expert
Section 18
hhh. SMT Senior Management Team
iii. SSC Structures, Systems, and Components
jjj. STD Standard
kkk. TPC Total Project Cost
lll. TRA Technology Readiness Assessment
mmm. V&ID Ventilation and Instrumentation Diagram
NNSA SD 413.3 Appendix G
05-18-21 APG-1
APPENDIX G: REFERENCES
a. Federal Acquisitions Regulation and Office of Federal Procurement Policy guidance.
b. Department of Energy (DOE) Acquisition Regulations (DEAR).
c. Office of Management and Budget (OMB) Circular A-11 for Capital Acquisition Projects
and its associated Capital Programming Guide.
d. DOE Order 413.3B, Program and Project Management for the Acquisition of Capital
Assets, dated 1-12-21.
e. DOE Guide (G) 413.3-1, Managing Design and Construction Using Systems
Engineering, dated 10-22-15.
f. DOE G 413.3-4A, Technology Readiness Assessments Guide, dated 10-22-15.
g. DOE G 413.3-13, U.S. Department of Energy Acquisition Strategy Guide for Capital
Asset Projects, dated 10-22-15.
h. DOE G 413.3-15A, Project Execution Plans, dated 09-14-18.
i. DOE G 413.3-17, Mission Need Statement, dated 10-22-15.
j. DOE G 413.3-18A, Integrated Project Team Guide for Formation and Implementation,
dated 10-22-15.
k. DOE G 413.3-19, Staffing Guide for Project Management, dated 10-22-15.
l. DOE-STD-1189-2016, Integration of Safety in the Design Process, dated 12-22-16.
m. Government Accountability Office (GAO) Best Practices GAO-20-195G, Cost
Estimating and Assessment Guide, dated 03-12-20.
n. NNSA Policy (NAP) 130.1A, Planning, Programming, Budgeting, and Evaluation
(PPBE) Process, dated 12-09-19.
o. NAP 413.3A, Responsibilities for Independent Cost Estimates, dated 04-30-21.
p. NAP 413.4, Technology Readiness Assessment, dated 12-22-16.
q. NNSA Business Operating Procedure (BOP) 413.4, Project Reviews, dated 11-14-18.
r. NNSA BOP 413.2, Program Requirements Document for Construction Projects, dated
02-15-08.
s. NNSA BOP 413.6, Analysis of Alternatives, dated 03-14-16
t. NNSA BOP 413.8, Energy Systems Acquisition Advisory Board Equivalent (ESAAB-E)
Process, dated 09-30-16.
NATIONAL NUCLEAR SECURITY ADMINISTRATION
1. PURPOSE. Describes the National Nuclear Security Administration (NNSA) roles, responsibilities, and authorities as they relate to capital asset project management for line item and major items of equipment (MIE) projects in accordance with Departm...
2. AUTHORITY. DOE Order 413.3B, Chg. 6, Program and Project Management for the Acquisition of Capital Assets, dated 1-12-21.
3. CANCELLATION. Business Operating Procedure (BOP) 413.7, Program and Project Management for the Acquisition of Capital Assets, dated 8-9-16.
4. APPLICABILITY.
a. Federal. This SD applies to all NNSA federal organizations.
b. Contractor. This SD does not apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by Executive Order 12344, codified at 50 United States Code sections 2406 and 2511, and to ensure consistency throughout the joint Navy/DOE Naval Nuclear Propulsion Prog...
5. SUMMARY OF CHANGES. NNSA BOP 413.7, Program and Project Management for the Acquisition of Capital Assets, was reformatted to create this SD and incorporates the following updates:
a. Updates reflected in DOE O 413.3.
b. An increase in the General Plant Project (GPP) minor construction threshold from $10M to $20M.
c. Key changes to ensure that project requirements and conceptual design are managed by acquisition and project management professionals after completion of the Analysis of Alternatives (AoA) Alternative Selection Document (ASD).
Section 19
6. BACKGROUND. This document defines accountability, responsibilities, and authorities while highlighting key factors that contribute to acquisition of capital assets across NNSA and applies to capital asset line item/MIE projects, as defined in DOE ...
This SD also reflects guidance from Office of Management and Budget (OMB) Circular A-11, the Federal Acquisition Regulation (FAR), Office of Federal Procurement Policy (OFPP) guidance, the DOE Acquisition Regulations (DEAR), DOE O 413.3, and the Depar...
7. REQUIREMENTS.
a. The capital asset project management process must be applied in conjunction with the requirements established by DOE O 413.3, specifically paragraph 3.a, “for projects having a total project cost (TPC) greater than $50M, except where the Administra...
b. As established by the NNSA policy decision, dated July 18, 2019, the Office of Acquisition and Project Management (NA-APM) must assume the lead role for execution and appoint a Federal Project Director (FPD) after the completion of the AoA Alterna...
c. Technology readiness assessments (TRAs) must be developed in accordance with DOE Guide (G) 413.3-4A, Technology Readiness Assessments Guide, and NNSA Policy (NAP) 413.4, Technology Readiness Assessments.
d. NNSA’s peer review policy and independent project reviews (IPR) must be implemented in accordance with BOP 413.4, Project Reviews.
e. Independent cost estimates and reviews must be conducted in accordance with NAP 413.3A, Responsibilities for Independent Cost Estimates, and Government Accountability Office (GAO)-20-195G, Cost Estimating and Assessment Guide.
f. Projects designated as Hazard Category 1, 2, or 3 nuclear facilities must comply with design safety requirements of DOE-Standard (STD)-1189-2016, Integration of Safety in the Design Process, DOE O 413.3 project management processes, and other appli...
g. When approved by the NNSA Administrator, Acquisition and Project Management Offices (APMO) for Major System Acquisition (MSA) projects must be established by NA-APM and led by a member of the Senior Executive Service (SES).
(1) The APMO is tailored and staffed with project management, acquisition, quality assurance, and technical subject matter expert(s) (SME) to ensure scaled and sufficient oversight is provided in accordance with the DOE G 413.3-19, Staffing Guide for ...
(2) The APMO Director must have the appropriate acquisition and project management training, experience, and certification level to ensure a sound understanding of the FAR and a broad knowledge base from which to communicate performance expectations b...
8. RESPONSIBILITIES.
a. Administrator (NA-1).
(1) Delegates Project Management Executive (PME) authority, as appropriate.
(2) Designates a project owner before Critical Decision (CD)-1.
(3) Ensures that the NA-APM FPD appointed to non-major system projects is qualified and has appropriate communication skills and leadership characteristics prior to designation.
(4) Serves as Chair and appoints members for Acquisition Advisory Boards.
Section 20
b. Associate Administrator for Acquisition and Project Management (NA-APM-1).
(1) Assists the Heads of NNSA Elements in developing CD-0 documents.
(2) Assumes the lead role in the execution of the project beginning with the completion of the AoA ASD and continuing through the approval of CD-4 to include developing the project execution documentation based on the selected alternative for the proj...
(3) Ensures all CD activities post AoA approval are completed and ensures NNSA follows DOE’s acquisition and project management requirements outlined in the DEAR, DOE O 413.3, and the Department’s policies for aligning contracts and contract incentive...
(4) Provides overall direction, strategic guidance, and management with respect to the acquisition and management of capital asset projects and ensures that NNSA implements all applicable federal and departmental acquisition policies and regulations.
(5) Serves as a Member of the Project Management Risk Committee (PMRC) and coordinates projects greater than $100M with the PMRC.
(6) Obtains full time equivalent (FTE) allocations for FPD billets from NA-1, hires, trains, supervises, and develops FPDs, and writes FPD appointment memoranda.
(7) Manages the PME initial delegation memoranda, and any subsequent delegations that may be appropriate if material changes in the project occur after the initial delegation, drafts all CD approval memoranda, and obtains subsequent approvals througho...
c. Director, Office of Enterprise Project Management (NA-APM-20). Approves exemptions to this SD. This responsibility cannot be delegated.
d. Director, Office of Cost Estimating and Program Evaluation (NA-1.3-1).
(1) Advises NA-1 on policies and procedures for cost analysis, estimation, and AoAs. Conducts the independent review of the AoA as outlined in BOP 413.6, Analysis of Alternatives, or successor policy.
(2) Performs TRA responsibilities outlined in NAP 413.4, Technology Readiness Assessments.
(3) Manages all CD phase independent cost estimates/reviews as outlined in NAP 413.3A, Responsibilities for Independent Cost Estimates.
e. Associate Administrator for Safety, Infrastructure and Operations (NA-50-1).
(1) Enables safe operations, ensures effective infrastructure, and provides enterprise services to meet the 21st century nuclear security enterprise needs.
(2) Works with the FPD in integrating safety into the design of nuclear construction projects and ensures DOE-STD-1189-2016, Integration of Safety in the Design Process, is implemented for Hazard Category 1, 2, and 3 nuclear facilities.
(3) Provides Environmental, Safety & Health; Waste Management; Quality Assurance; and Nuclear Safety technical experts to support the Integrated Project Team (IPT) and NNSA’s Independent Project Peer Reviews.
(4) Provides Guiding Principles for Sustainable Federal Buildings, Leadership in Energy & Environmental Design (LEED), and LEED Gold waiver technical experts to support project teams. Delegates Safety Basis approval to the Field Office Manager or app...
f. Chief and Associate Administrator for Defense Nuclear Security (NA-70-1). Ensures the field office security representatives to the IPT implement DOE’s security orders and policies.
g. Associate Administrator for Information Management (NA-IM-1).
(1) Ensures the Heads of NNSA Element’s and field office’s information management representatives to the IPT communicate and implement all DOE and NNSA Information Technology (IT) and cybersecurity orders and policies.
(2) Approves IT components in the design and procurement to be in compliance with the Federal Information Technology Acquisition Reform Act (FITARA).
Section 21
h. Associate Administrator for Management and Budget (NA-MB-1).
(1) Serves as the lead for conducting NNSA initiated AoAs, in accordance with BOP 413.6, Analysis of Alternatives.
(2) At the discretion of the program offices and their specific budget allocations, ensures funds for NA-APM products and services come from the sponsoring NNSA Element’s appropriated funds, the details of which are to be developed in accordance with ...
(3) Ensures programs comply with Department Orders, including DOE O 413.3, during the fiscal year Congressional budget process.
(4) Provides IPT representation to ensure programmatic cost estimates are developed in accordance with NNSA policies and best practices.
(5) Assists the Heads of NNSA Elements, if requested, in developing the Mission Need Statement (MNS) and Program Requirements Document (PRD) to ensure an AoA can be accomplished in accordance with standard practices.
i. Office of Project Analysis, Oversight and Review (NA-APM-1.1).
(1) Implements NNSA’s peer review policy and conducts Independent Project Reviews (IPR) from CD-0 through CD-4, in accordance with DOE/NNSA requirements.
(2) Provides feedback independent of NA-APM or Heads of NNSA Elements through direct lines of communication to the Principal Deputy Administrator (NA-2).
(3) Serves as a member of the PMRC and briefs the PMRC on its IPRs.
j. Heads of NNSA Elements.
(1) Lead the development of the Mission Need Statement (MNS) and establish the project requirements through the PRD.
(2) Participates in the AoA process in accordance with BOP 413.6, Analysis of Alternatives.
(3) Manage requirements generation, develop the budget requests, fund capital asset projects, including funding for FPD support governed by DOE O 413.3, and monitor and approve scope changes as identified in the Project Execution Plan (PEP) change con...
(4) Upon project completion, assume responsibility for oversight of operations of the completed project in accordance with Beneficial Occupancy Date (BOD) guidance and verify that the mission need has been met.
(5) As a capital asset project progresses through the various CD phases, is responsible for the mission need, requirements, technical alternative selection, budgets, and funding of capital asset projects governed by DOE O 413.3.
k. Field Office Managers.
(1) If the authority has been delegated, approve the Documented Safety Analysis and the Safety Evaluation Report.
(2) Upon project completion, provide oversight of operations of the completed project in accordance with BOD guidance and verify that the mission need was met.
l. Acquisition and Project Management Office Directors (APMOs). Provide overall direction, strategic guidance, and management of the project office in performance of all functions necessary to deliver the project in accordance with its original appro...
m. Federal Project Director (FPD).
(1) Leads the IPT comprised of NNSA Elements and contractor personnel (when appropriate but not required) and serves as the single point of contact responsible for the overall execution of the project immediately after completion of the AoA ASD throug...
(2) Evaluates and verifies reported progress, provides project execution metrics in accordance with guidance provided by NA-APM, provides projections for future progress, and notifies senior management whenever project performance indicates a likeliho...
(3) Serves to support and defend the project cost, schedule, performance, and scope baselines, and ensures that the project receives adequate resources and expertise in all necessary areas.
(4) Manages the CD-X performance baseline through monthly meetings and invites representatives from the NNSA Elements and NNSA field offices to attend to maintain situational awareness of project performance.
(5) Serves as the Contracting Officer’s Representative (COR), upon appointment.
Section 22
n. Headquarters Project Manager (HQPM).
(1) Serves as the project management professional in NA-APM assigned to a project when an MNS and PRD begin development.
(2) Serves as the primary advisor to the NNSA Elements to ensure that the effort approved at CD-0 has sufficiently developed requirements to proceed through pre-conceptual design to support the AoA. Helps ensure that the MNS and PRD requirements are ...
(3) Serves as the FPD after the completion of the AoA Alternative Selection Document until one is assigned, and acts as the FPD in the absence of the FPD throughout the life of the project. Remains with the project through CD-4 and is the most knowle...
(4) Ensures communication flows swiftly through HQ Elements, that decisions and actions are well documented, and are executed on a schedule.
o. Senior Management Team (SMT).
(1) Comprised of SES representatives from the NNSA Elements identified in the CD-X Preliminary Project Execution Plan (PPEP).
(2) Provides monitoring of the federal IPT, including providing input to complex issues and making decisions based on recommendations, through regular monthly meetings.
(3) SMTs apply to all projects where the PME requests one be chartered.
p. Project Management Risk Committee (PMRC).
(1) Reviews CD packages with values greater than or equal to $750M for CD-0.
(2) Reviews all CDs and makes recommendations to the pertinent PMEs and the Energy System Acquisition Advisory Board (ESAAB) for projects with a TPC greater than or equal to $100M, for CD-1 through CD-4.
(3) Receives out-briefs on all independent project peer reviews.
9. ACRONYMS. See Appendix F.
10. REFERENCES. See Appendix G.
11. CONTACT. The Office of Enterprise Project Management, NA-APM-20, 202-586-9814, NA-APM-20@nnsa.doe.gov.
A. Project Process – Critical Decision Requirements
1. Pre CD-0: Prepare Mission Need for Approval.
a. Develop Mission Need. When a credible performance gap is identified between current capabilities and those required to achieve the mission, the Heads of NNSA Elements lead the development of a Mission Need Statement (MNS) that translates mission n...
b. Prepare the Program Requirements Document (PRD). The Heads of NNSA Elements must develop and maintain the PRD during the life of the project, as required by Business Operating Procedure (BOP) 413.2 Admin Chg. 1, Program Requirements Document for C...
c. Identify and Provide Funding. The responsible Heads of NNSA Elements establish the Rough Order of Magnitude cost range and provide funding for capital asset projects from appropriated funds. The Heads of NNSA Elements formulate the budget details...
Section 23
2. Post CD-0/Pre CD-1: Prepare Alternative Selection and Cost Range for Approval.
a. Establish and Manage the Integrated Project Team (IPT). Upon approval of the mission need for a capital asset project, the Heads of NNSA Elements establish an IPT comprising NNSA field office personnel, NNSA Element personnel, project and acquisit...
b. FPD Appointment. NA-APM identifies the appropriately certified FPDs who can be assigned to specific projects. The FPD is assigned after completion of the AoA ASD.
c. Develop Alternatives and Finalize AoA. For projects seeking CD-1 approval, NA-MB conducts an AoA that is independent of the contractor organization that would benefit from the proposed project (e.g., Management and Operating Contractor, [M&O]). T...
d. Develop the Acquisition Strategy. NA-APM develops the acquisition strategy, in consultation with the Heads of NNSA Elements, to identify the high-level plan for satisfying the mission need in the most effective, economical, and timely manner. The...
e. Develop the CD-1 Preliminary Project Execution Plan (PPEP). NA-APM leads the development of the CD-1 PPEP, which describes the organizational framework and overall management system for the project from AoA approval to CD-1 approval. The CD-1 PPE...
f. Develop the DMP. NA-APM leads the development of the DMP, which establishes the anticipated levels of design maturity at each CD phase. The DMP must be developed as early as possible after approval of the AoA to ensure that design activities are ...
g. Develop the Conceptual Design. The NA-APM FPD leads the conceptual design team. As a part of this effort, the FPD prepares a CD-1 PPEP that defines roles and responsibilities, a DMP, and implements a CD-1 performance baseline with change control ...
h. Develop the CD-2 PPEP. The FPD is responsible for updating the CD-1 PPEP to describe the organizational framework and overall management system for the project from CD-1 approval to CD-2 approval. The CD-2 PPEP must be approved prior to CD-1 appr...
i. Exemptions, Equivalencies, and Waivers. A project may seek exemptions or equivalencies to the requirements in DOE directives in accordance with the process described in DOE O 251.1D, Departmental Directives Program, Appendix E. Examples include a...
3. Post CD-1/Pre CD-2: Prepare Performance Baseline for Approval.
a. Baseline Development. NA-APM formalizes the cost, schedule, and scope of a project at CD-2, and measures success against this baseline at project completion, including key performance parameters. The project requirements, identified in the approv...
b. Establish a Project Management Office (PMO), if applicable. A PMO provides a full-time team dedicated to the project to ensure project delivery is in accordance with the established cost, schedule, and scope baselines. For a Major System Acquisit...
c. Develop the PEP. The FPD is responsible for drafting and updating the PEP prior to CD-2 approval. The PEP is a living document that is based on the CD-2 PPEP and must be updated to capture changes to project systems, processes, procedures, and pe...
d. Plan for Site Integration. The FPD, Heads of NNSA Elements, through the IPT, establish a plan for site integration. Planning for site integration involves identifying site interface issues and infrastructure requirements in order to mitigate barr...
e. Award and Administer Design Contracts or Interagency Agreements (IAs). Design contracts or IAs are awarded and managed according to the DMP. NA-APM or its agent awards design contracts, work authorizations, and IAs to support project requirements...
f. For conventional, non-nuclear construction, the design can be less than 90% complete prior to CD-2. Through an IPR, NA-APM ensures that adequate definition exists to provide a budget quality cost and schedule estimate for the total project perform...
Section 24
4. Pre CD-3A: Long Lead Procurements. A CD-3A package can be submitted in conjunction with another CD or separately. Some potential reasons to pursue a CD-3A authorization include the following:
5. Pre CD-2/3: Approve Performance Baseline and Start of Construction Execution. The preparations for a CD-2/3 submittal package include all the activities necessary for both the CD-2 and CD-3 submission combined in the same submittal package. A CD...
6. Post CD-2/Pre CD-3: Prepare for Construction Execution Start.
a. Complete Project Design. After the Project Baseline is approved, the FPD completes the project definition/design, begins to execute the Acquisition Strategy, and initiates early procurements.
b. Manage the Project Baseline. The FPD manages the project baseline by overseeing and evaluating the progress of the project through CD-4. The FPD evaluates performance against cost, schedule, and scope. NA-APM monitors performance through monthly...
c. The FPD updates the baseline in accordance with the change control thresholds in the PEP when there is a new requirement or a change to the cost, schedule, or scope.
7. Post CD-3/Pre CD-4: Prepare for Start of Operations or Project Completion.
a. Award Construction Contracts and IAs. NA-APM or its agent awards construction contracts, work authorizations, and IAs to support project requirements. To ensure successful outcomes, close coordination is expected between contracting staff across ...
b. Manage Construction Contracts and IAs. NA-APM or its agent oversees and manages construction services through contracts and IAs to achieve the project baseline.
c. Manage Site Integration Issues. The FPD takes the lead role in managing any site integration issues, in support of construction activities, with the NNSA Elements, Nuclear construction projects must also comply with design safety requirements of D...
d. Prepare for Transition to Operations. In close coordination with Heads of NNSA Elements, the FPD is responsible for developing and managing startup, turnover, and closeout plans in accordance with DOE O 413.3. Activities include checkout, testing...
e. Establish Beneficial Occupancy Date (BOD). The stage of construction of a building or facility, before final completion, at which its user can occupy it for the purpose for which it was constructed. Beneficial occupancy does not imply that a proj...
Section 25
8. Post CD-4: Prepare for Project Closeout.
a. Accept Project for Operations. Heads of NNSA Elements verify the mission need and project requirements are met and accept the project for operation in accordance with the PEP.
b. Turnover to Operations and Conduct Closeout Activities. Upon acceptance, the FPD continues to provide monthly project reviews with all IPT members until closeout activities are completed. This includes completing any punch list items, managing wa...
c. Project Closeout. The FPD prepares the project documents for PME approval, schedules the ESAAB or ESAAB-E, and officially closes the project out in the DOE Project Assessment and Reporting System. Also see BOP 413.8, Energy Systems Acquisition Ad...
a. Federal Acquisitions Regulation and Office of Federal Procurement Policy guidance.
b. Department of Energy (DOE) Acquisition Regulations (DEAR).
c. Office of Management and Budget (OMB) Circular A-11 for Capital Acquisition Projects and its associated Capital Programming Guide.
d. DOE Order 413.3B, Program and Project Management for the Acquisition of Capital Assets, dated 1-12-21.
e. DOE Guide (G) 413.3-1, Managing Design and Construction Using Systems Engineering, dated 10-22-15.
f. DOE G 413.3-4A, Technology Readiness Assessments Guide, dated 10-22-15.
g. DOE G 413.3-13, U.S. Department of Energy Acquisition Strategy Guide for Capital Asset Projects, dated 10-22-15.
h. DOE G 413.3-15A, Project Execution Plans, dated 09-14-18.
i. DOE G 413.3-17, Mission Need Statement, dated 10-22-15.
j. DOE G 413.3-18A, Integrated Project Team Guide for Formation and Implementation, dated 10-22-15.
k. DOE G 413.3-19, Staffing Guide for Project Management, dated 10-22-15.
l. DOE-STD-1189-2016, Integration of Safety in the Design Process, dated 12-22-16.
m. Government Accountability Office (GAO) Best Practices GAO-20-195G, Cost Estimating and Assessment Guide, dated 03-12-20.
n. NNSA Policy (NAP) 130.1A, Planning, Programming, Budgeting, and Evaluation (PPBE) Process, dated 12-09-19.
o. NAP 413.3A, Responsibilities for Independent Cost Estimates, dated 04-30-21.
p. NAP 413.4, Technology Readiness Assessment, dated 12-22-16.
q. NNSA Business Operating Procedure (BOP) 413.4, Project Reviews, dated 11-14-18.
r. NNSA BOP 413.2, Program Requirements Document for Construction Projects, dated 02-15-08.
s. NNSA BOP 413.6, Analysis of Alternatives, dated 03-14-16
t. NNSA BOP 413.8, Energy Systems Acquisition Advisory Board Equivalent (ESAAB-E) Process, dated 09-30-16.
Blank Page
Blank Page