Section 1
SUPPLEMENTAL DIRECTIVE
Approved: 1-18-17
Certified: 1-15-20
Expires: 1-15-23
REAL PROPERTY ASSET MANAGEMENT
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Safety, Infrastructure & Operations
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Safety, Infrastructure and Operations
http://hq.na.gov http://nnsa.energy.gov
printed copies are uncontrolled
SD 430.1
http://hq.na.gov/
http://nnsa.energy.gov/
THIS PAGE INTENTIONALLY LEFT BLANK
SD 430.1C 1
1-18-17
REAL PROPERTY ASSET MANAGEMENT
1. PURPOSE. To implement DOE O 430.1C, Real Property Asset Management.
2. CANCELLATION. NNSA Manual, Real Property Management, dated 04-01-09, and
NNSA memorandum, Implementation of DOE Order 430.1B Real Property Asset
Management with the National Nuclear Security Administration, dated 03-22-04.
Cancellation of a directive does not, by itself, modify or otherwise affect any contractual
or regulatory obligation to comply with the directive. Contractor requirements
documents (CRDs) that have been incorporated into a contract remain in effect
throughout the term of the contract until the contract or regulatory commitment is
modified to eliminate requirements or substitute a new set of requirements.
3. APPLICABILITY.
a. Federal. This applies to all NNSA Elements.
b. Contractors. The contractor requirements document (CRD) attached to this SD
sets forth requirements that apply to contractors.
The CRD must be included in contracts that involve the acquisition, management,
or disposition of real property or interests therein, and indicate when the
contractor will be reimbursed for any authorized costs.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 United States Code sections 2406 and
2511, and to ensure consistency through the joint Navy/DOE Naval Nuclear
Propulsion Program, the Deputy Administrator for Naval Reactors (Director) will
implement and oversee requirements and practices pertaining to this Directive for
activities under the Director's cognizance, as deemed appropriate.
4. SUMMARY OF CHANGES. Not applicable.
5. BACKGROUND. DOE O 430.1C, hereafter referred to as the Order, replaced the site-
level requirements of the prior order, 430.1B, with requirements for Under Secretaries to
meet the unique needs of their program through supplemental directives. The
Administrator will implement the Order with clarifications consistent with the needs of
NNSA’s core scientific, engineering, and manufacturing business lines, protecting the
government’s investments in real property while that property has potential value to
NNSA’s mission and while the Government holds a legal interest in the asset, particularly
for protecting people and the environment. It also protects the government’s financial
interest by disposing of excess real property as soon as possible after the excess
declaration. Real property is planned to have a 40- to 60-year life cycle, with recurring
15- to 20-year periods of renovation and renewal, and should be managed with a life-
cycle perspective.
2 SD 430.1C
1-18-17
Decisions to delay real property maintenance and renewal have unavoidable impacts on
service life that may continue after the delayed work is performed. Therefore,
management decisions, including investments in new construction, maintenance,
recapitalization, and disposition, must consider minimizing the total life-cycle costs of
real property.
Section 2
NNSA actions concerning real property will satisfy all requirements of the Order, using
the following systems, tools, and programs.
a. G2 is NNSA’s authoritative data source for planning, programming, and
execution of infrastructure activities.
b. BUILDER™ Sustainment Management System (BUILDER™) is NNSA’s
authoritative data source for information related to condition and functionality
assessments.
c. Facilities Information Management System (FIMS) is the Department’s Real
Property Database of Record.
d. Master Asset Plan (MAP) is NNSA’s enterprise-wide infrastructure strategic plan.
The MAP covers the infrastructure necessary to meet current, planned, and future
mission requirements over the next 25 years, through the integration of five-year
real property planning and budgeting with longer term goals. It provides an
integrated view of NNSA infrastructure and a prioritized infrastructure roadmap
to reduce risks to mission execution in the near-, mid-, and long-terms.
e. Mission Dependency Index (MDI) is NNSA’s risk-based, consequence to mission
metric that assigns a quantitative score to a real property asset. This score
informs decision makers on the potential impact the loss of the asset would have
on NNSA’s mission.
f. Excess Facilities Risk Index (ERI) is NNSA’s risk-based, consequence metric for
retired facilities. The quantitative score assigned from ERI is used to aid
prioritization of disposition projects, based on the risk posed to worker and public
safety or mission work.
6. REQUIREMENTS. NNSA entities managing real property must keep data in G2, FIMS,
and BUILDER™ systems current. For this purpose, current means data should be
updated at sufficient intervals for the data to be used for NNSA decisions and reports at
any time, without requiring sites to review and update the data, and is sufficiently
complete and accurate to support decisions concerning funding.
a. Planning and Budgeting. NNSA shall meet the Order’s requirements for real
property asset management planning and budgeting, preparation of annual
planning guidance, real property planning, and provide five-year real property
planning and budgeting documentation.
SD 430.1C 3
1-18-17
(1) NNSA must use G2 for planning, programming, and execution of
infrastructure activities to fulfill the Order’s requirements to manage
financial investments in real property.
(2) NNSA must use the MAP to fulfill the Order’s requirements for the
following:
(a) Annual planning guidance;
(b) Real property planning;
(c) Five-year real property planning and budgeting;
and include:
(d) A prioritized list of real property acquisition, sustainment, and
disposition activities and projects;
(e) Alignment of real property planning with NNSA and DOE
strategic plans and program guidance; and
(f) Real property meeting the needs of site tenants.
(3) NNSA must use MDI to fulfill the Order’s requirements to do the
following:
(a) Assess real property against core capabilities;
(b) Evaluate the relative importance and contributions of said real
property to mission accomplishment; and
(c) Determine the optimum set of facilities and infrastructure needed
to maintain core capabilities.
(4) NNSA must develop or use existing programs and policies to address
requirements related to the following areas outlined in the Order:
(a) Climate change resilience, adaptation, and sustainability;
(b) Environment, health, safety, and security;
(c) Earthquake risks;
(d) Cultural and natural resource preservation;
Section 3
(e) Historical preservation;
(f) Surveillance, maintenance, and long-term stewardship (LTS)
resource requirements achievements; and
4 SD 430.1C
1-18-17
(g) Reduction or consolidation of space, specifically addressing space
policy, program benchmarks for space utilization, and space
assignment and utilization standards.
(5) NNSA must fulfill the Order’s requirements for reporting results of annual
utilization surveys to FIMS.
(6) NNSA must use BUILDER™ to fulfill the Order’s requirements for
infrastructure condition and functionality assessments.
b. Acquisition. NNSA must ensure the acquisition of real property meets applicable
federal laws and regulations through the use of the following processes and
systems.
(1) NNSA must establish the authority of and appoint a Certified Realty
Specialist (CRS) and Real Estate Contracting Officer (RECO) to fulfill the
Order’s requirements for real estate business case analysis; life-cycle cost
analysis; and space management and utilization requirements. A CRS or
RECO must review and approve all planned acquisition and other real
estate actions, and implement NNSA real estate practices as identified by
the NNSA Real Property Officer (RPO).
(2) NNSA must use the MAP to fulfill the Order’s requirements that
acquisitions are supported by a mission need.
(3) NNSA must record required information in the FIMS Anticipated Asset
Information Module (AAIM), based on information from G2,
BUILDER™, the MAP, and other NNSA RPO guidance, to fulfill the
Order’s requirements identified in paragraph 4.b(1)b of the Order.
(4) NNSA must ensure programs fulfill the Order’s requirements to do the
following:
(a) Ensure construction or renovation of existing DOE-owned assets
greater than 5,000 square feet meet federal sustainability guiding
principles;
(b) Ensure new solicitations for DOE-leased buildings above 10,000
rentable square feet meet building efficiency, performance, and
management requirements; and
(c) Ensure facilities, regardless of ownership, comply with applicable
federal metering requirements.
(5) NNSA must fulfill the Order’s requirements that new construction of
DOE-owned building areas, except at environmental closure sites, is offset
SD 430.1C 5
1-18-17
by sale, declaration of excess, or demolition of a building area of an
equivalent or greater size.
c. Sustainment. NNSA must achieve the sustainment of real property assets
maintenance, repair, and renovation activities to ensure mission readiness;
operational safety; worker health, environmental protection and compliance;
security; and property preservation to cost-effectively meet program missions
through the following:
(1) NNSA must ensure programs fulfill the Order’s requirements to maintain
real property assets, including mechanical and electrical systems, and to
ensure real property availability for planned use or disposition using
preventive and predictive maintenance and repairs.
(2) NNSA must use the BUILDER™ Sustainment Management System to
fulfill the Order’s requirements to establish a master equipment list and
conduct infrastructure condition and functionality assessments.
(3) NNSA must follow NNSA RPO guidance to fulfill the Order’s
requirements to establish technical and management processes to align the
performance, functional, and physical attributes of real property assets,
systems and components in the maintenance program with associated
requirements, design, and operations information, and to comply with
applicable DOE maintenance management directives for nuclear facilities.
Section 4
(4) NNSA must use G2 to fulfill the Order’s requirements to do the following:
(a) Track direct and indirect funded expenditures for maintenance,
repair, and renovation at the site level;
(b) Manage planning and budgeting for known future cyclical
maintenance, repair, and renovations requirements for major
building component or infrastructure systems based on the
information in BUILDER™; and
(c) Develop a five-year forecast and update annually to identify
financial investments for sustainment of real property assets to
support DOE strategic plans, program guidance, Departmental
performance targets, and NNSA RPO guidance.
(5) NNSA’s Sustainability program must fulfill the Order’s requirements to
do the following:
(a) Perform comprehensive energy and water assessments for each
operating covered facility at least once during any four-year
period; and
6 SD 430.1C
1-18-17
(b) Recommission covered facilities at least once during any four-year
period, tailored to the size and complexity of the building and its
system components, and to optimize and verify performance of
existing building systems.
(6) NNSA must submit information in FIMS to fulfill the Order’s
requirements to report asset level annual required maintenance for the
upcoming fiscal year, including the estimated fully burdened costs of
predictive and preventive maintenance and repair activities and to record
annually the results of condition and functionality assessments and real
property utilization assessments.
d. Disposition. NNSA must ensure the disposition or long-term stewardship of real
property assets is carried out in accordance with applicable Federal laws and
regulations and compliance with applicable Federal laws and regulations for
excess real property assets at defense nuclear facilities, using the following
systems and processes:
(1) NNSA must use the MAP and ERI to fulfill the Order’s requirements to
identify real property assets that are no longer needed to meet mission
needs and may be candidates for reuse and disposition and to inform
prioritization of asset disposition.
(2) NNSA must use G2 to fulfill the Order’s requirements to track the annual
cost of maintaining excess facilities, at the asset level as directed, once the
asset is declared excess and until final disposition.
(3) NNSA must use FIMS to fulfill the Order’s requirements to record
planned disposition of real property.
(4) NNSA must appoint CRS and RECOs to review and approve a Request
for Disposition (RFD) form before any action to dispose of real property
begins to fulfill the Order’s disposition real estate requirements.
(5) NNSA must establish a disposition program to fulfill the Order’s
requirements to:
(a) Screen real property assets in accordance with federal laws,
regulations, and the Department’s internal process for screening
real property assets prior to declaration of excess;
(b) Dispose of excess real property assets via demolition or other
DOE-approved methods;
(c) Dispose of excess contaminated real property assets in accordance
with applicable federal laws and regulations, DOE directives, and
NNSA RPO guidance; and
SD 430.1C 7
1-18-17
(d) Ensure physical controls, institutional controls, and other
mechanisms to protect people and the environment are in place
while performing disposition activities.
e. Performance Measurement. NNSA shall report performance measures using
FIMS, G2, and other systems as identified by the NNSA RPO.
Section 5
f. Reporting Systems. NNSA shall maintain accurate data in both NNSA-internal
and DOE systems including, but not limited to, the following systems:
(1) FIMS is the Department’s corporate real property inventory system, which
stores real property data. The Department is required to verify and
validate the accuracy of the Federal Real Property Profile (FRPP) annual
submission. NNSA will ensure that site’s data is entered into FIMS to
support the FRPP, and other requirements outlined in the Order.
(2) G2 is NNSA’s authoritative data source for planning, programming, and
execution of infrastructure activities.
(3) BUILDER™ is NNSA’s authoritative data source for information related
to condition and functionality assessments.
7. RESPONSIBILITIES AND AUTHORITIES. These responsibilities are in addition to
those outlined in the Order.
a. Administrator (NA-1):
(1) Ensures accountability for the stewardship of NNSA real property assets.
(2) Approves documented program-specific or location/site-specific
exemptions, exclusions, or deviations from requirements of the Order
based on mission needs, efficiency, or efficacy of execution without
disregarding Federal laws and regulations.
(3) Executes real estate transactions to acquire, manage, and dispose of real
property, to include the acceptance of donations and the initiations of
condemnation actions or executions of declarations of takings.
(4) Delegates transactional real estate execution authorities to acquire,
manage, and dispose of real property, with the exception of accepting
donations and initiations on condemnation actions or executions of
declaration of takings.
(5) Provides direct appointments for the NNSA Real Estate Contracting
Officers (RECOs).
8 SD 430.1C
1-18-17
b. Associate Administrator for Safety, Infrastructure and Operations (NA-50):
(1) Acts as the Program Secretarial Officer (PSO), as identified in 5.d. of the
Order fulfilling all the responsibilities outlined therein.
(2) Acts as the NNSA RPO, responsible for:
(a) Overseeing NNSA stewardship of real property;
(b) Fulfilling all RPO responsibilities issued in the Order and other
DOE policy, with authority to issue guidance and direction to
ensure consistent implementation of the Order and this
Supplemental Directive across all NNSA sites and the Office of
Secure Transportation (OST);
(c) Working in consultation with the Order’s Office of Primary
Interest where NNSA’s practices are equivalencies to the
requirements of the Order;
(d) Delegating internal NNSA actions, while maintaining direct
responsibility for external actions; and
(e) Issuing RPO working-level implementation plans for this
Supplemental Directive including, but not limited to, the NA-50
Program Management Plan (PMP) and other Real Property
Management requirements.
(3) Measures and reports real property asset performance; also measures real
property asset management performance.
(4) Prepares and submits real property asset information in response to
external requests.
(5) Tracks directly and indirectly funded real property acquisitions,
operations, maintenance, recapitalization, and disposition to ensure a
holistic view of NNSA’s real property holdings and expenditures.
(6) Establishes transparent, consistent, repeatable real property practices
across NNSA sites and OST.
(7) Issues the MAP, covering an enterprise-wide perspective of the
infrastructure requirements necessary to meet mission needs.
Section 6
(8) Charters working groups to manage ad hoc and ongoing real property
issues and challenges and to provide vertical and horizontal channels for
innovations to NNSA real property practices.
SD 430.1C 9
1-18-17
(9) Reviews and certifies DOE real property inventory for accuracy and
completeness to support DOE’s certification of the annual Federal Real
Property Council data submission.
(10) Ensures the interests and needs of NNSA’s federal and contractor
infrastructure workforces are represented in NNSA policies and practices;
alerts the Administrator when the infrastructure workforce may be
evolving away from sufficient capability to meet all obligations.
(11) Represents NNSA real property issues in Department venues, including
the Laboratory Operating Board (LOB), the Excess Contaminated
Facilities Working Group (ECFWG), and the Infrastructure Executive
Committee (IEC). As appropriate, this responsibility may be delegated.
(12) Reviews Departmental guidance and directives, including those related to
the FIMS, tailors the guidance and directives to meet NNSA’s
requirements, and transmits the tailored guidance to NNSA field offices
and OST for incorporation into contract requirements.
(13) Issues process-oriented, operational-level guidance annually, or as needed,
integrating guidance and direction necessary to ensure consistent
management of NNSA infrastructure across all programs, sites, and OST,
supplementing the annual guidance with memoranda as necessary to meet
evolving requirements.
(14) Oversees the NNSA real estate program and ensures that CRS support is
available to all programs within NNSA. Ensures that all Preliminary Real
Estate Plans are reviewed and approved by an NNSA CRS. Ensures CRS
personnel are qualified and recommends the level of RECO warrant to
request from the Administrator (NA-1) for each CRS.
(15) Establishes policies and guidance for NNSA compliance with the Federal
Building Personnel Training Act, ensuring effective oversight of the field
and contractor infrastructure workforce.
(16) Ensures clear demarcation between accountability for maintenance of real
and personal property consistent with the different requirements for and
funding support of the two types of property in cooperation with other
Deputy and Associate Administrators.
(17) Ensures NNSA’s active participation for sustainability and long-term
stewardship, in support of the Order and other applicable regulations and
statutory requirements.
10 SD 430.1C
1-18-17
c. Deputy Administrators and Associate Administrators:
(1) Ensure personal property supported by their programs is inventoried and
maintained with responsibility clearly demarcated from the real property
containing the personal property in cooperation with Associate
Administrator for Safety, Infrastructure and Operations.
(2) Coordinate program-driven real property investments with the Office of
Safety, Infrastructure and Operations to ensure balanced investment across
programmatic and enabling infrastructure.
(3) Ensure all personal property and materials are removed from facilities
when the asset is excessed; personal property must be properly relocated
or stored for future use, properly transferred or moved to an institutional
entity that will be using the space, or disposed of if no future use exists.
(4) Ensure federal offices responsible for planning, construction, operations,
maintenance, and disposition of real property assets meet the requirements
outlined in Attachment 1.
Section 7
d. Associate Administrator for Acquisition and Project Management (NA-APM):
(1) Ensures future new line item construction and renovation projects under
their cognizance provide BUILDER™ ASTM-E1557-09 Uniformat II
inventory data down to Level 5, including specific equipment detail
information, in an electronic format determined in coordination with the
NA-50 BUILDER™ Program Manager and the site-specific BUILDER™
lead. Project acceptance practices must ensure this data is complete and
sufficient to support management of the facility in BUILDER™, with no
further inventory or condition and functionality assessment actions
required, at least 30 days prior to final project closeout. Explore to what
extent data can be provided at no additional cost for current projects in
progress. The condition rating for new construction must meet a green
plus or green condition assessment.
(2) Ensures all new construction and renovation results in components that are
accessible for preventive and corrective maintenance, to support
maintainability of real property assets throughout the lifetime of the asset.
e. Field Office Managers:
(1) Perform all duties outlined in Section 5.h. of the Order.
(2) Ensure accountability for all aspects of federal oversight of real property is
assigned to their staff, including maintaining an accurate inventory of real
property under their control. May divide responsibility between direct
reports as necessary to match local needs.
SD 430.1C 11
1-18-17
(3) Ensure BUILDER™, G2, MDI, ERI, and FIMS data is accurate,
consistent, and in agreement with the NNSA RPO’s guidance, and certify
the accuracy of the data to the NNSA RPO at the end of the fiscal year to
support NNSA certification of data to the Department.
(4) Ensure federal offices responsible for planning, construction, operations,
maintenance, and disposition of real property assets meet the requirements
outlined in Attachment 1 (the CRD).
(5) Ensure that the Contracting Officer incorporates the CRD and all other
applicable real property requirements identified by the NNSA RPO into
M&O contracts.
f. Assistant Deputy Administrator for OST:
(1) Implement this Supplemental Directive through a Memorandum of
Agreement with the NNSA RPO, with consideration of the statutory
requirements of OST's authorization and appropriation.
(2) Determine all expenditures of OST funds for OST property and facilities.
8. REFERENCES. The following references are useful or necessary to perform the
functions covered by this Supplemental Directive. Additional references are available in
the Order.
a. Federal Building Personnel Training Act of 2010, Public Law 111-308,
December 14, 2010.
b. 41 U.S.C. § 102 Federal Management Regulation.
c. 42 U.S.C. § 8523 Energy Management Requirements.
d. GSA Acquisition Regulation (GSAR) Part 570, Acquiring Leasehold Interests in
Real Property.
e. DOE, Asset Management Plan.
f. DOE O 433.1 (series) Maintenance Management Program for DOE Nuclear
Facilities.
g. DOE O 430.1(series), Real Property Asset Management (RPAM).
h. DOE O 580.1(series) Personal Property Management Program.
i. DOE Real Estate Desk Guide, the primary source of information and guidance for
planning, acquiring, managing, and disposing of DOE real property or interests
therein.
12
j.
k.
1.
m.
n.
DOE, Real Property Efficiency Plan, September 2015.
DOE, Strategic Sustainability Performance Plan, September 2010.
SD 430.lC
1-18-17
Section 8
DOE, Federal Energy Management Program, Facility Energy Management
Guidelines and Criteria for Energy and Water Evaluations in Covered Facilities,
11-28-08.
Facilities Information Management System (FIMS) User's Guide, Training
Workbook, and Reporting Guide, November 2016.
Office for Safety, Infrastructure and Operations (NA-50), Program Management
Plan, October 2016
9. DEFINITIONS/ACRONYMS. See Attaclnnent 2.
10. CONTACT. Director, Office oflnfrastructure Planning and Analysis (NA-521), Office
of Safety, Infrastructure & Operations, at 202-586-4134.
BY ORDER OF THE ADMINISTRATOR:
?~lo~·~
Administrator
Attaclnnents:
1. Contractor Requirement Document (CRD)
2. Acronyms and Definitions
SD 430.1C Attachment 1
1-18-17 AT1-1
ATTACHMENT 1: CONTRACTOR REQUIREMENTS DOCUMENT
NNSA SD 430.1
This contractor requirements document (CRD) applies to the National Nuclear Security
Administration (NNSA) contractors whose contracts involve the acquisition, management,
maintenance, or disposition of real property assets. Contractors are expected to meet these
functional requirements by tailoring their business and management practices, and using standard
industry practices.
Regardless of who performs the work, the contractor is responsible for complying with the
requirements of this CRD. The contractor is responsible for flowing down the requirements of
this CRD to subcontracts at any tier to the extent necessary to ensure the subcontractor’s
compliance with the requirements.
The DOE Order 430.1C and this CRD lay out performance-based outcomes. Where specific
guidance is not given in the Order, this CRD, the Office of Safety, Infrastructure and Operations
(NA-50) Program Management Plan (PMP), or NNSA Real Property Officer (RPO) guidance,
contractors have the latitude to accomplish the required outcomes via their own processes.
1. PLANNING. Based on NNSA-furnished program planning guidance, the contractor
must—
a. Assess the current real property assets against program mission projections;
b. Identify the specific real property asset projects and activities required to meet
program mission projections; and
c. Propose a 25-year planning horizon through the development of a Master Asset
Plan (MAP).
2. INFRASTRUCTURE DATA MANAGEMENT. The contractor must maintain G2 data
and records, Facilities Information Management System (FIMS) data and records, and
data and records to support BUILDER™ and other data systems specified by NNSA and
DOE policy. Data quality and timeliness of data should support NNSA decisionmaking
without request for data updates. FIMS data must be verified annually.
3. FACILITY UTILIZATION. Contractors must manage the utilization of their facilities
using industry best practices and applicable government standards, and in accordance
with NNSA RPO guidance. Each contractor must have a space management system,
completely accessible to federal oversight and field office staff. The space management
system must satisfy Department, regulatory, and statutory requirements for determining
utilization rates, including the requirement to produce annual reports. The data collected
by the contractor must be sufficient for NNSA and the contractor to reach agreement on
the optimum size of the site for current and future mission needs. The data must be
sufficient for NNSA’s use to justify the results to Congress, the Office of Management
Attachment 1 SD 430.1C
AT1-2 1-18-17
Section 9
and Budget, and other external stakeholders, and to meet the Laboratory Operating Board
(LOB) assessment requirement for utilization.
The contractor must have a space management system that tracks the current program
users of all facilities and ensures all users fit within DOE, NNSA, and local standards for
space usage. The system must also:
a. Ensure vacating users are not relieved of their responsibility for a space until all
programmatic equipment and personal property has been removed; personal
property must be properly relocated or stored for future use, properly transferred
or moved to an institutional entity that will be using the space, or disposed of if no
future use exists.
b. Support DOE and NNSA reporting requirements, including FIMS utilization data.
c. Be available to field office personnel and other federal oversight personnel for
review.
Contractors must ensure optimum performance of a facility, in accordance with design or
current operating needs, over the useful life of the facility, while meeting building
occupancy and mission requirements.
A subset of these data elements, or others determined by the NNSA RPO, may be
reported through G2. Further guidance and requirements will be provided by the NNSA
RPO.
4. MAINTENANCE AND MODERNIZATION. The contractor must maintain real
property assets in a manner that promotes operational safety, worker health,
environmental compliance, property preservation, and cost-effectiveness while meeting
the program missions and protecting the government’s investment in real property. This
requires a balanced approach that not only sustains the assets, but also provides for their
recapitalization and includes the following:
a. Integrated computer systems that include condition and functionality assessment
information for real property assets, a work control system, management of
deferred maintenance, a method to prioritize, and systems to budget and track
maintenance expenditures.
b. Identification of five-year maintenance and repair requirements (sustainment) and
funding for deferred maintenance reduction.
c. Identification of five-year recapitalization and capital construction requirements
to replace or modernize existing facilities.
d. Condition and functionality assessments of real property assets according to the
frequency dictated by the NNSA RPO. At least once within a five-year period,
verify that all of the required inspections are completed and ensure BUILDER™
reflects all outstanding and completed maintenance work orders for repairs and
SD 430.1C Attachment 1
1-18-17 AT1-3
overhauls. The condition and functionality assessment program shall use a
tailored approach based on facility status, mission and importance, and the
magnitude of the hazards associated with facilities and infrastructure.
Inspection methodology shall be consistent with industry best practices, and shall
include identification of safety and health hazards. Deferred maintenance
estimates will be based on BUILDER™ output. The condition and functionality
assessment program will support the reporting requirements of G2 and FIMS.
Until BUILDER™ is fully populated, each site’s current condition and
functionality assessment process must be consistent, auditable, and current by
regularly updating the site’s BUILDER™ database with outstanding and
completed work orders.
Section 10
5. DISPOSITION. Contractors must ensure vacating users are not relieved of their
responsibility for a space until all programmatic equipment and personal property has
been removed; personal property must be properly relocated or stored for future use,
properly transferred or moved to an institutional entity that will be using the space, or
disposed of if no future use exists. Contractors must also manage disposition of their
facilities to meet requirements identified by the NNSA RPO.
6. WORKFORCE. Contractors must maintain a trained workforce, sufficient to achieve the
NNSA mission. Contractors must monitor their workforce and ensure NNSA RPO is
aware of developing workforce-related issues and concerns that could create risks for
infrastructure management.
7. DOCUMENTATION. The contractor must document its real property management
activities, including (a) the site’s plan to meet program missions, (b) budgets and
planning estimates, and (c) performance outcomes via the MAP deep-dive process.
8. REAL ESTATE. The contractor must —
a. Follow the procedures specified by the NNSA RPO;
b. Prepare Preliminary Real Estate Plans (PREPs) and Requests for Disposition
(RFDs), obtaining all required approvals and concurrences before proceeding with
a real estate action; and
c. Submit all PREPs and RFDs to acquire, manage, and dispose of real property
assets to their field office and to the NNSA Headquarters (HQ) Certified Realty
Specialist (CRS) through their Field Office Manager or designee for review and
approval.
9. LONG-TERM STEWARDSHIP (LTS). LTS activities must be consistent with
requirements dictated by statutory, regulatory, and other Department policies transmitted
through or established by the NNSA RPO.
Attachment 1 SD 430.1C
AT1-4 1-18-17
10. SUSTAINABILITY. Sustainability activities must be consistent with requirements
dictated by statutory, regulatory, and other Department policies transmitted through or
established by the NNSA RPO. Contractors must provide annual reports to the NNSA
RPO or designee on the accomplishment of requirements.
SD-430.1C Attachment 2
1-18-17 AT2-1
ATTACHMENT 2: REAL PROPERTY ASSET MANAGEMENT DEFINITIONS AND
ACRONYMS
NOTE: All attachments, except Attachment 1 (which applies to contractors only), apply to
both Federal and contractor employees.
1. DEFINITIONS/ACRONYMS. NNSA will rely on the original source documentation for
interpretation of all definitions, drawing on and using the definitions in the Order except
where the NNSA Real Property Office (RPO) determines additional clarification is
needed or where the source documentation provides latitude beyond that within the
definition provided in the Order. The following definitions are provided in addition to
those in the Order:
a. Area is a portion of a site. This term is applicable at larger sites that have been
segmented into areas for facilities planning or other purposes as opposed to a
special area, which is off-site. Example: The Area 23 at the Nevada Nuclear
Security Site (NNSS), is a portion of NNSS devoted primarily to administrative
functions.
b. BUILDER™ is a knowledge-based, sustainment management system, which
includes condition and functionality assessments.
c. Condemnation is a judicial proceeding, initiated by the Government under its
right of eminent domain, to take private property for public use.
Section 11
d. Certified Realty Specialist (CRS) is a DOE employee, in the realty specialist
series, who is certified in one or more of the three specialty realty areas:
acquisition, leasing, and land management and disposal. Employees so certified
are authorized to prepare and implement real estate actions within certified
specialty areas, and to provide the required review and approval prior to execution
by a DOE official with a delegation of authority for real estate actions. Detailed
guidance and procedures for becoming a CRS are found in the DOE Acquisition
Certifications Program Handbook. An NNSA CRS must be an NNSA employee.
e. Declaration of Taking is a pleading filed in a court with a condemnation
proceeding, whereby, with the deposit of just compensation, the interest in the
property, as stated in the pleading, is vested at once in the Government.
f. Disposition is the demolition of a real estate asset or the permanent or temporary
transfer of NNSA control and custody of real property assets to another who
thereby acquires rights to control, use, or relinquish the property.
g. Donation (Gift) is the voluntary transfer or conveyance of an interest in real
property without payment or consideration of any kind.
h. Enabling Infrastructure are land, roads, walkways, utilities, and support facilities
that are required for the programmatically focused facilities to complete their
mission needs.
Attachment 2 SD 430.1C
AT2-2 1-18-17
i. Excess Risk Index (ERI) is NNSA’s risk-based, consequence metric for retired
facilities. The quantitative score assigned by ERI is used to aid prioritization of
disposition projects, based on the risk posed to worker and public safety or
mission work.
j. Facilities Information Management System (FIMS) is the DOE corporate real
property asset database for all real property owned, leased, or managed by DOE.
k. G2 is the National Nuclear Security Administration’s G2 Program Management
System used to track infrastructure planning, programming, and execution efforts.
l. Lease is a contractual agreement that gives exclusive possessory interest in the
property for a specified time, in exchange for payment of rent to the owner.
m. Master Asset Plan (MAP) is NNSA’s enterprise-wide infrastructure strategic plan,
covering a 25-year timeline. The MAP covers the infrastructure necessary to
meet current, planned, and future mission requirements over the next 25 years. It
provides an integrated view of NNSA infrastructure and a prioritized
infrastructure roadmap to reduce risks to mission execution in the near, mid-, and
long-terms.
n. Mission Dependency Index (MDI) is NNSA’s risk-based, consequence to mission
metric that assigns a quantitative score to a real property asset. This score
informs decision makers on the potential impact the loss of the asset would have
on NNSA’s mission.
o. Original Source Documentation are the records and reports that support the data
collection efforts. This information is usually compiled firsthand, by program
subject matter experts in the field.
p. Personal Property includes all equipment, material, and supplies not classified as
real property (Refer to DOE O 580.1A and to 41 CFR Chapter 102-71).
NNSA also considers personal property to be items that are not permanently
affixed to the real property asset and can be removed without serious impact
either to the real property or to the items themselves. Personal property may
include items necessary for the course of normal administrative or business
operations, such as office furniture, as well as science and engineering equipment.
Section 12
q. Preliminary Real Estate Plan (PREP) is a decision document affecting all future
site-selection activity which includes a description of the program or project and
an analysis of all viable options and alternatives considered, along with the
advantages and disadvantages of each.
r. Real Estate Contracting Officer (RECO) is a Certified Realty Specialist who has
been issued a contracting officer warrant to execute real estate actions, within
prescribed limits. An NNSA RECO must be an NNSA employee.
SD-430.1C Attachment 2
1-18-17 AT2-3
s. Request for Disposition (RFD) is the decision document affecting the disposition
of an asset, which includes a description of the facility; the annual surveillance,
operations, and maintenance costs associated with the facility; a condition and
functionality assessment of the facility and the associated maintenance backlog;
and the estimated demolition costs and date.
t. Retired Asset is any asset that has a shutdown status in FIMS.
1. PURPOSE. To implement DOE O 430.1C, Real Property Asset Management.
2. CANCELLATION. NNSA Manual, Real Property Management, dated 04-01-09, and NNSA memorandum, Implementation of DOE Order 430.1B Real Property Asset Management with the National Nuclear Security Administration, dated 03-22-04.
3. APPLICABILITY.
a. Federal. This applies to all NNSA Elements.
b. Contractors. The contractor requirements document (CRD) attached to this SD sets forth requirements that apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by Executive Order 12344, codified at 50 United States Code sections 2406 and 2511, and to ensure consistency through the joint Navy/DOE Naval Nuclear Propulsion Program...
4. SUMMARY OF CHANGES. Not applicable.
5. BACKGROUND. DOE O 430.1C, hereafter referred to as the Order, replaced the site-level requirements of the prior order, 430.1B, with requirements for Under Secretaries to meet the unique needs of their program through supplemental directives. The ...
a. G2 is NNSA’s authoritative data source for planning, programming, and execution of infrastructure activities.
b. BUILDER™ Sustainment Management System (BUILDER™) is NNSA’s authoritative data source for information related to condition and functionality assessments.
c. Facilities Information Management System (FIMS) is the Department’s Real Property Database of Record.
d. Master Asset Plan (MAP) is NNSA’s enterprise-wide infrastructure strategic plan. The MAP covers the infrastructure necessary to meet current, planned, and future mission requirements over the next 25 years, through the integration of five-year rea...
e. Mission Dependency Index (MDI) is NNSA’s risk-based, consequence to mission metric that assigns a quantitative score to a real property asset. This score informs decision makers on the potential impact the loss of the asset would have on NNSA’s mi...
f. Excess Facilities Risk Index (ERI) is NNSA’s risk-based, consequence metric for retired facilities. The quantitative score assigned from ERI is used to aid prioritization of disposition projects, based on the risk posed to worker and public safety...
Section 13
6. REQUIREMENTS. NNSA entities managing real property must keep data in G2, FIMS, and BUILDER™ systems current. For this purpose, current means data should be updated at sufficient intervals for the data to be used for NNSA decisions and reports at ...
a. Planning and Budgeting. NNSA shall meet the Order’s requirements for real property asset management planning and budgeting, preparation of annual planning guidance, real property planning, and provide five-year real property planning and budgeting...
(1) NNSA must use G2 for planning, programming, and execution of infrastructure activities to fulfill the Order’s requirements to manage financial investments in real property.
(2) NNSA must use the MAP to fulfill the Order’s requirements for the following:
(a) Annual planning guidance;
(b) Real property planning;
(c) Five-year real property planning and budgeting;
and include:
(d) A prioritized list of real property acquisition, sustainment, and disposition activities and projects;
(e) Alignment of real property planning with NNSA and DOE strategic plans and program guidance; and
(f) Real property meeting the needs of site tenants.
(3) NNSA must use MDI to fulfill the Order’s requirements to do the following:
(a) Assess real property against core capabilities;
(b) Evaluate the relative importance and contributions of said real property to mission accomplishment; and
(c) Determine the optimum set of facilities and infrastructure needed to maintain core capabilities.
(4) NNSA must develop or use existing programs and policies to address requirements related to the following areas outlined in the Order:
(a) Climate change resilience, adaptation, and sustainability;
(b) Environment, health, safety, and security;
(c) Earthquake risks;
(d) Cultural and natural resource preservation;
(e) Historical preservation;
(f) Surveillance, maintenance, and long-term stewardship (LTS) resource requirements achievements; and
(g) Reduction or consolidation of space, specifically addressing space policy, program benchmarks for space utilization, and space assignment and utilization standards.
(5) NNSA must fulfill the Order’s requirements for reporting results of annual utilization surveys to FIMS.
(6) NNSA must use BUILDER™ to fulfill the Order’s requirements for infrastructure condition and functionality assessments.
b. Acquisition. NNSA must ensure the acquisition of real property meets applicable federal laws and regulations through the use of the following processes and systems.
(1) NNSA must establish the authority of and appoint a Certified Realty Specialist (CRS) and Real Estate Contracting Officer (RECO) to fulfill the Order’s requirements for real estate business case analysis; life-cycle cost analysis; and space managem...
(2) NNSA must use the MAP to fulfill the Order’s requirements that acquisitions are supported by a mission need.
(3) NNSA must record required information in the FIMS Anticipated Asset Information Module (AAIM), based on information from G2, BUILDER™, the MAP, and other NNSA RPO guidance, to fulfill the Order’s requirements identified in paragraph 4.b(1)b of the...
(4) NNSA must ensure programs fulfill the Order’s requirements to do the following:
(a) Ensure construction or renovation of existing DOE-owned assets greater than 5,000 square feet meet federal sustainability guiding principles;
(b) Ensure new solicitations for DOE-leased buildings above 10,000 rentable square feet meet building efficiency, performance, and management requirements; and
(c) Ensure facilities, regardless of ownership, comply with applicable federal metering requirements.
Section 14
(5) NNSA must fulfill the Order’s requirements that new construction of DOE-owned building areas, except at environmental closure sites, is offset by sale, declaration of excess, or demolition of a building area of an equivalent or greater size.
c. Sustainment. NNSA must achieve the sustainment of real property assets maintenance, repair, and renovation activities to ensure mission readiness; operational safety; worker health, environmental protection and compliance; security; and property p...
(1) NNSA must ensure programs fulfill the Order’s requirements to maintain real property assets, including mechanical and electrical systems, and to ensure real property availability for planned use or disposition using preventive and predictive maint...
(2) NNSA must use the BUILDER™ Sustainment Management System to fulfill the Order’s requirements to establish a master equipment list and conduct infrastructure condition and functionality assessments.
(3) NNSA must follow NNSA RPO guidance to fulfill the Order’s requirements to establish technical and management processes to align the performance, functional, and physical attributes of real property assets, systems and components in the maintenance...
(4) NNSA must use G2 to fulfill the Order’s requirements to do the following:
(a) Track direct and indirect funded expenditures for maintenance, repair, and renovation at the site level;
(b) Manage planning and budgeting for known future cyclical maintenance, repair, and renovations requirements for major building component or infrastructure systems based on the information in BUILDER™; and
(c) Develop a five-year forecast and update annually to identify financial investments for sustainment of real property assets to support DOE strategic plans, program guidance, Departmental performance targets, and NNSA RPO guidance.
(5) NNSA’s Sustainability program must fulfill the Order’s requirements to do the following:
(a) Perform comprehensive energy and water assessments for each operating covered facility at least once during any four-year period; and
(b) Recommission covered facilities at least once during any four-year period, tailored to the size and complexity of the building and its system components, and to optimize and verify performance of existing building systems.
(6) NNSA must submit information in FIMS to fulfill the Order’s requirements to report asset level annual required maintenance for the upcoming fiscal year, including the estimated fully burdened costs of predictive and preventive maintenance and repa...
d. Disposition. NNSA must ensure the disposition or long-term stewardship of real property assets is carried out in accordance with applicable Federal laws and regulations and compliance with applicable Federal laws and regulations for excess real pr...
(1) NNSA must use the MAP and ERI to fulfill the Order’s requirements to identify real property assets that are no longer needed to meet mission needs and may be candidates for reuse and disposition and to inform prioritization of asset disposition.
(2) NNSA must use G2 to fulfill the Order’s requirements to track the annual cost of maintaining excess facilities, at the asset level as directed, once the asset is declared excess and until final disposition.
(3) NNSA must use FIMS to fulfill the Order’s requirements to record planned disposition of real property.
(4) NNSA must appoint CRS and RECOs to review and approve a Request for Disposition (RFD) form before any action to dispose of real property begins to fulfill the Order’s disposition real estate requirements.
(5) NNSA must establish a disposition program to fulfill the Order’s requirements to:
(a) Screen real property assets in accordance with federal laws, regulations, and the Department’s internal process for screening real property assets prior to declaration of excess;
(b) Dispose of excess real property assets via demolition or other DOE-approved methods;
(c) Dispose of excess contaminated real property assets in accordance with applicable federal laws and regulations, DOE directives, and NNSA RPO guidance; and
(d) Ensure physical controls, institutional controls, and other mechanisms to protect people and the environment are in place while performing disposition activities.
Section 15
e. Performance Measurement. NNSA shall report performance measures using FIMS, G2, and other systems as identified by the NNSA RPO.
f. Reporting Systems. NNSA shall maintain accurate data in both NNSA-internal and DOE systems including, but not limited to, the following systems:
(1) FIMS is the Department’s corporate real property inventory system, which stores real property data. The Department is required to verify and validate the accuracy of the Federal Real Property Profile (FRPP) annual submission. NNSA will ensure th...
(2) G2 is NNSA’s authoritative data source for planning, programming, and execution of infrastructure activities.
(3) BUILDER™ is NNSA’s authoritative data source for information related to condition and functionality assessments.
7. RESPONSIBILITIES AND AUTHORITIES. These responsibilities are in addition to those outlined in the Order.
a. Administrator (NA-1):
(1) Ensures accountability for the stewardship of NNSA real property assets.
(2) Approves documented program-specific or location/site-specific exemptions, exclusions, or deviations from requirements of the Order based on mission needs, efficiency, or efficacy of execution without disregarding Federal laws and regulations.
(3) Executes real estate transactions to acquire, manage, and dispose of real property, to include the acceptance of donations and the initiations of condemnation actions or executions of declarations of takings.
(4) Delegates transactional real estate execution authorities to acquire, manage, and dispose of real property, with the exception of accepting donations and initiations on condemnation actions or executions of declaration of takings.
(5) Provides direct appointments for the NNSA Real Estate Contracting Officers (RECOs).
b. Associate Administrator for Safety, Infrastructure and Operations (NA-50):
(1) Acts as the Program Secretarial Officer (PSO), as identified in 5.d. of the Order fulfilling all the responsibilities outlined therein.
(2) Acts as the NNSA RPO, responsible for:
(a) Overseeing NNSA stewardship of real property;
(b) Fulfilling all RPO responsibilities issued in the Order and other DOE policy, with authority to issue guidance and direction to ensure consistent implementation of the Order and this Supplemental Directive across all NNSA sites and the Office of S...
(c) Working in consultation with the Order’s Office of Primary Interest where NNSA’s practices are equivalencies to the requirements of the Order;
(d) Delegating internal NNSA actions, while maintaining direct responsibility for external actions; and
(e) Issuing RPO working-level implementation plans for this Supplemental Directive including, but not limited to, the NA-50 Program Management Plan (PMP) and other Real Property Management requirements.
Section 16
(3) Measures and reports real property asset performance; also measures real property asset management performance.
(4) Prepares and submits real property asset information in response to external requests.
(5) Tracks directly and indirectly funded real property acquisitions, operations, maintenance, recapitalization, and disposition to ensure a holistic view of NNSA’s real property holdings and expenditures.
(6) Establishes transparent, consistent, repeatable real property practices across NNSA sites and OST.
(7) Issues the MAP, covering an enterprise-wide perspective of the infrastructure requirements necessary to meet mission needs.
(8) Charters working groups to manage ad hoc and ongoing real property issues and challenges and to provide vertical and horizontal channels for innovations to NNSA real property practices.
(9) Reviews and certifies DOE real property inventory for accuracy and completeness to support DOE’s certification of the annual Federal Real Property Council data submission.
(10) Ensures the interests and needs of NNSA’s federal and contractor infrastructure workforces are represented in NNSA policies and practices; alerts the Administrator when the infrastructure workforce may be evolving away from sufficient capability ...
(11) Represents NNSA real property issues in Department venues, including the Laboratory Operating Board (LOB), the Excess Contaminated Facilities Working Group (ECFWG), and the Infrastructure Executive Committee (IEC). As appropriate, this responsib...
(12) Reviews Departmental guidance and directives, including those related to the FIMS, tailors the guidance and directives to meet NNSA’s requirements, and transmits the tailored guidance to NNSA field offices and OST for incorporation into contract ...
(13) Issues process-oriented, operational-level guidance annually, or as needed, integrating guidance and direction necessary to ensure consistent management of NNSA infrastructure across all programs, sites, and OST, supplementing the annual guidance...
(14) Oversees the NNSA real estate program and ensures that CRS support is available to all programs within NNSA. Ensures that all Preliminary Real Estate Plans are reviewed and approved by an NNSA CRS. Ensures CRS personnel are qualified and recomm...
(15) Establishes policies and guidance for NNSA compliance with the Federal Building Personnel Training Act, ensuring effective oversight of the field and contractor infrastructure workforce.
(16) Ensures clear demarcation between accountability for maintenance of real and personal property consistent with the different requirements for and funding support of the two types of property in cooperation with other Deputy and Associate Administ...
(17) Ensures NNSA’s active participation for sustainability and long-term stewardship, in support of the Order and other applicable regulations and statutory requirements.
c. Deputy Administrators and Associate Administrators:
(1) Ensure personal property supported by their programs is inventoried and maintained with responsibility clearly demarcated from the real property containing the personal property in cooperation with Associate Administrator for Safety, Infrastructur...
(2) Coordinate program-driven real property investments with the Office of Safety, Infrastructure and Operations to ensure balanced investment across programmatic and enabling infrastructure.
(3) Ensure all personal property and materials are removed from facilities when the asset is excessed; personal property must be properly relocated or stored for future use, properly transferred or moved to an institutional entity that will be using t...
(4) Ensure federal offices responsible for planning, construction, operations, maintenance, and disposition of real property assets meet the requirements outlined in Attachment 1.
Section 17
d. Associate Administrator for Acquisition and Project Management (NA-APM):
(1) Ensures future new line item construction and renovation projects under their cognizance provide BUILDER™ ASTM-E1557-09 Uniformat II inventory data down to Level 5, including specific equipment detail information, in an electronic format determine...
(2) Ensures all new construction and renovation results in components that are accessible for preventive and corrective maintenance, to support maintainability of real property assets throughout the lifetime of the asset.
e. Field Office Managers:
(1) Perform all duties outlined in Section 5.h. of the Order.
(2) Ensure accountability for all aspects of federal oversight of real property is assigned to their staff, including maintaining an accurate inventory of real property under their control. May divide responsibility between direct reports as necessar...
(3) Ensure BUILDER™, G2, MDI, ERI, and FIMS data is accurate, consistent, and in agreement with the NNSA RPO’s guidance, and certify the accuracy of the data to the NNSA RPO at the end of the fiscal year to support NNSA certification of data to the De...
(4) Ensure federal offices responsible for planning, construction, operations, maintenance, and disposition of real property assets meet the requirements outlined in Attachment 1 (the CRD).
(5) Ensure that the Contracting Officer incorporates the CRD and all other applicable real property requirements identified by the NNSA RPO into M&O contracts.
f. Assistant Deputy Administrator for OST:
(1) Implement this Supplemental Directive through a Memorandum of Agreement with the NNSA RPO, with consideration of the statutory requirements of OST's authorization and appropriation.
(2) Determine all expenditures of OST funds for OST property and facilities.
8. REFERENCES. The following references are useful or necessary to perform the functions covered by this Supplemental Directive. Additional references are available in the Order.
a. Federal Building Personnel Training Act of 2010, Public Law 111-308, December 14, 2010.
b. 41 U.S.C. § 102 Federal Management Regulation.
c. 42 U.S.C. § 8523 Energy Management Requirements.
d. GSA Acquisition Regulation (GSAR) Part 570, Acquiring Leasehold Interests in Real Property.
e. DOE, Asset Management Plan.
f. DOE O 433.1 (series) Maintenance Management Program for DOE Nuclear Facilities.
g. DOE O 430.1(series), Real Property Asset Management (RPAM).
h. DOE O 580.1(series) Personal Property Management Program.
i. DOE Real Estate Desk Guide, the primary source of information and guidance for planning, acquiring, managing, and disposing of DOE real property or interests therein.
j. DOE, Real Property Efficiency Plan, September 2015.
k. DOE, Strategic Sustainability Performance Plan, September 2010.
l. DOE, Federal Energy Management Program, Facility Energy Management Guidelines and Criteria for Energy and Water Evaluations in Covered Facilities, 11-28-08.
m. Facilities Information Management System (FIMS) User’s Guide, Training Workbook, and Reporting Guide, November 2016.
n. Office for Safety, Infrastructure and Operations (NA-50), Program Management Plan, October 2016
Section 18
9. DEFINITIONS/ACRONYMS. See Attachment 2.
10. CONTACT. Director, Office of Infrastructure Planning and Analysis (NA-521), Office of Safety, Infrastructure & Operations, at 202-586-4134.
a. Ensure vacating users are not relieved of their responsibility for a space until all programmatic equipment and personal property has been removed; personal property must be properly relocated or stored for future use, properly transferred or moved...
b. Support DOE and NNSA reporting requirements, including FIMS utilization data.
c. Be available to field office personnel and other federal oversight personnel for review.
1. DEFINITIONS/ACRONYMS. NNSA will rely on the original source documentation for interpretation of all definitions, drawing on and using the definitions in the Order except where the NNSA Real Property Office (RPO) determines additional clarification...
a. Area is a portion of a site. This term is applicable at larger sites that have been segmented into areas for facilities planning or other purposes as opposed to a special area, which is off-site. Example: The Area 23 at the Nevada Nuclear Securi...
b. BUILDER™ is a knowledge-based, sustainment management system, which includes condition and functionality assessments.
c. Condemnation is a judicial proceeding, initiated by the Government under its right of eminent domain, to take private property for public use.
d. Certified Realty Specialist (CRS) is a DOE employee, in the realty specialist series, who is certified in one or more of the three specialty realty areas: acquisition, leasing, and land management and disposal. Employees so certified are authorized...
e. Declaration of Taking is a pleading filed in a court with a condemnation proceeding, whereby, with the deposit of just compensation, the interest in the property, as stated in the pleading, is vested at once in the Government.
f. Disposition is the demolition of a real estate asset or the permanent or temporary transfer of NNSA control and custody of real property assets to another who thereby acquires rights to control, use, or relinquish the property.
g. Donation (Gift) is the voluntary transfer or conveyance of an interest in real property without payment or consideration of any kind.
h. Enabling Infrastructure are land, roads, walkways, utilities, and support facilities that are required for the programmatically focused facilities to complete their mission needs.
i. Excess Risk Index (ERI) is NNSA’s risk-based, consequence metric for retired facilities. The quantitative score assigned by ERI is used to aid prioritization of disposition projects, based on the risk posed to worker and public safety or mission w...
j. Facilities Information Management System (FIMS) is the DOE corporate real property asset database for all real property owned, leased, or managed by DOE.
k. G2 is the National Nuclear Security Administration’s G2 Program Management System used to track infrastructure planning, programming, and execution efforts.
l. Lease is a contractual agreement that gives exclusive possessory interest in the property for a specified time, in exchange for payment of rent to the owner.
m. Master Asset Plan (MAP) is NNSA’s enterprise-wide infrastructure strategic plan, covering a 25-year timeline. The MAP covers the infrastructure necessary to meet current, planned, and future mission requirements over the next 25 years. It provide...
Section 19
n. Mission Dependency Index (MDI) is NNSA’s risk-based, consequence to mission metric that assigns a quantitative score to a real property asset. This score informs decision makers on the potential impact the loss of the asset would have on NNSA’s mi...
o. Original Source Documentation are the records and reports that support the data collection efforts. This information is usually compiled firsthand, by program subject matter experts in the field.
p. Personal Property includes all equipment, material, and supplies not classified as real property (Refer to DOE O 580.1A and to 41 CFR Chapter 102-71).
NNSA also considers personal property to be items that are not permanently affixed to the real property asset and can be removed without serious impact either to the real property or to the items themselves. Personal property may include items necess...
q. Preliminary Real Estate Plan (PREP) is a decision document affecting all future site-selection activity which includes a description of the program or project and an analysis of all viable options and alternatives considered, along with the advanta...
r. Real Estate Contracting Officer (RECO) is a Certified Realty Specialist who has been issued a contracting officer warrant to execute real estate actions, within prescribed limits. An NNSA RECO must be an NNSA employee.
s. Request for Disposition (RFD) is the decision document affecting the disposition of an asset, which includes a description of the facility; the annual surveillance, operations, and maintenance costs associated with the facility; a condition and fun...
t. Retired Asset is any asset that has a shutdown status in FIMS.