SD 430.1A, Real Property Asset Management
This Supplemental Directive (SD) updates the authorities, requirements, and responsibilities for the National Nuclear Security Administration (NNSA) real property asset management and supplements the requirements of Department of Energy (DOE) Order (O) 430.1C Chg. 2, Real Property Asset Management.
Follow changes to SD 430.1A and its other editions: RSS feed
Associated DOE Directive:
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Infrastructure
https://directives.nnsa.doe.gov/directives
Printed copies are uncontrolled.
SUPPLEMENTAL DIRECTIVE
Approved: 10-16-2026
Recertification Due: 10-16-2031
REAL PROPERTY ASSET
MANAGEMENT
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Infrastructure
SD 430.1A
https://directives.nnsa.doe.gov/directives
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 430.1A 1
10-16-26
REAL PROPERTY ASSET MANAGEMENT
1. PURPOSE. This Supplemental Directive (SD) updates the authorities, requirements, and
responsibilities for the National Nuclear Security Administration (NNSA) real property
asset management and supplements the requirements of Department of Energy (DOE)
Order (O) 430.1C Chg. 2, Real Property Asset Management.
2. AUTHORITY. DOE O 430.1C Chg. 2, Real Property Asset Management, dated
September 17, 2020.
3. CANCELLATION. NNSA SD 430.1, Real Property Asset Management, dated
January 18, 2017.
Cancellation of a directive does not modify or otherwise affect any contractual or
regulatory obligation to comply with the directive. Contractor Requirements Documents
(CRDs) incorporated into a contract remain in effect throughout the contract term until
the contract or regulatory commitment is modified to eliminate or substitute a new set of
requirements.
4. APPLICABILITY.
a. Federal. Applies to all NNSA Elements.
b. Contractors. The CRD, provided as Attachment 1, sets forth requirements that
apply to contractors.
The CRD must be included in contracts involving the acquisition, management, or
disposition of real property or interests therein and must indicate when the
contractor will be reimbursed for any authorized costs.
c. Equivalencies/Exemptions.
(1) Equivalency: In accordance with the responsibilities and authorities
assigned by Executive Order 12344, codified at 50 United States Code
sections 2406 and 2511, and to ensure consistency throughout the joint
Navy/DOE Naval Nuclear Propulsion Program, the Deputy Administrator
for Naval Reactors (Director) will implement and oversee requirements
and practices pertaining to this Directive for activities under the Director’s
cognizance, as deemed appropriate.
(2) Exemptions: None
5. SUMMARY OF CHANGES.
a. Changes the Office of Primary Interest (OPI) to the Office of Infrastructure which
reflects the reorganization of the Office of Safety, Infrastructure, and Operations
and the Office of Acquisition and Project Management.
2 NNSA SD 430.1A
10-16-26
b. Incorporates the updated infrastructure life cycle management tools, processes,
and responsibilities throughout the SD and Attachment 1 to continue efficiently
managing DOE and NNSA real property portfolio.
c. Updates responsibilities and authorities to better align with current DOE and
NNSA policy.
6. BACKGROUND. DOE O 430.1C Chg. 2, hereafter referred to as the Order, replaced the
site-level requirements of DOE O 430.1B, Real Property Asset Management, dated
September 24, 2003, with the responsibility for the DOE Under Secretaries to meet the
unique needs of their programs through issuance of supplemental directives and
guidance, as necessary, to implement real property asset management. The NNSA
Administrator is responsible for implementation of the Order with clarifications
consistent with NNSA’s core scientific, engineering, and manufacturing business lines,
protecting the Government’s investments in real property while that property has
potential value to NNSA’s mission and while the Government holds a legal interest in the
assets, particularly for protecting people, the environment, and the Government’s
financial interest by disposing of excess real property as soon as possible after the excess
declaration. Real property is planned to have a 40- to 60-year life cycle, with recurring
20- to 25-year periods of renovation and renewal and should be managed with a life cycle
perspective.
Section 2
Decisions to delay real property maintenance and renewal have unavoidable impacts on
service life that may continue after the delayed work is performed. Therefore,
management decisions, including investments in new construction, maintenance,
recapitalization, and disposition, must consider minimizing the total life cycle costs of
real property.
NNSA actions concerning real property will satisfy all requirements of the Order by
using the following systems, tools, strategic plans, principles, and programs:
a. Real Property Asset Management (RPAM) Guide. NNSA’s guide for effectively
managing real property assets over their life cycle by establishing a standardized,
repeatable, and disciplined process.
b. Program Management System Generation 2 (G2). NNSA’s authoritative data
source for integrated infrastructure planning efforts and supports infrastructure
programming activities.
c. BUILDER™ Sustainment Management System (BUILDER™). NNSA’s
authoritative data source for information related to condition and functionality
assessments.
d. Facilities Information Management System (FIMS). DOE’s real property
database of record for storing real property data. The Department is required to
verify and validate the accuracy of the Federal Real Property Profile (FRPP)
NNSA SD 430.1A 3
10-16-26
annual submission. NNSA will ensure the site data is entered into FIMS to
support the FRPP and other requirements outlined in the Order.
e. Infrastructure Planning Principles. A set of principles and practices developed by
the Integrated Infrastructure Planning (IIP) Team to guide and support the
planning process must be incorporated throughout the enterprise-wide plan and
NNSA’s integrated, systematic and continuous planning process, as appropriate.
f. Master Asset Plan (MAP). NNSA’s enterprise-wide infrastructure strategic plan.
The MAP covers the infrastructure necessary to meet current, planned, and future
mission requirements, through the integration of 5-year real property planning and
budgeting with longer term goals. It provides an integrated view of NNSA
infrastructure and a prioritized infrastructure roadmap that aligns with NNSA’s
integrated infrastructure priorities and agile, time-phased approaches to reduce
risks to mission execution in the near-, mid-, and long-term planning horizons.
g. MAP Deep Dives. NNSA site visits that provide a forum for discussing and
understanding mission requirements. These discussions are capability-focused
and drive current and planned infrastructure investments based on condition,
capacity gaps, and risks to help align site and program-level infrastructure
priorities with NNSA’s goals and resources.
h. Area Planning. A methodology used to develop plans that create a framework for
modernization and drive prioritized integrated investments by incorporating
mission requirements with viable investment options.
i. Enterprise Blueprint. NNSA’s roadmap that aligns timely delivery of specialized
infrastructure with NNSA mission demands by focusing on meeting the program
of record, developing modern nuclear weapons systems, and sustaining an
unrivaled technological advantage in today's increasingly competitive geopolitical
environment.
j. Mission Dependency Index (MDI). NNSA’s risk-based, consequence-to- mission
metric that assigns a quantitative score to a real property asset. This score
informs decision-makers of the potential impact the asset’s loss would have on
NNSA’s mission.
Section 3
k. Excess-Facility Risk Index (ERI). NNSA’s risk-based consequence metric for
retired facilities. The quantitative score assigned by ERI is used to aid in the
prioritization of disposition projects based on the risk posed to worker and public
safety or mission work.
l. Lease Rating Scorecard and Criteria. NNSA’s risk-based methodology that
measures leased data to evaluate the risk a proposed lease will pose to the
Government. The calculated lease rating score informs the decision-making
process, including the present value calculation criteria required by the Office of
Management and Budget.
4 NNSA SD 430.1A
10-16-26
7. REQUIREMENTS. NNSA entities managing real property must keep data in G2, FIMS,
and BUILDER™ systems current. For the purposes of this SD, “current” means data
must be updated at sufficient intervals to ensure complete and accurate data used for
NNSA decisions and reports, including funding, at any time without requiring sites to
review and update the data.
a. Planning and Budgeting. NNSA will meet the Order’s requirements for real
property asset management planning and budgeting, preparation of annual
planning guidance, real property planning, and 5-year real property planning and
budgeting documentation.
(1) NNSA must use G2 to support integrated infrastructure planning efforts
and programming of infrastructure activities to fulfill the Order’s
requirements to manage financial investments in real property.
(2) NNSA must incorporate early-stage planning infrastructure activities,
principles, and information into the development of real estate planning
development.
(3) NNSA must identify the specific real property assets, needs, gaps,
projects, and activities required to meet program mission projections.
(4) NNSA must use the MAP, MAP Deep Dives, area plans, and RPAM
Guide to fulfill the Order’s requirements for the following:
(a) Annual planning guidance.
(b) Real property planning.
(c) Five-year real property planning and budgeting that includes:
1 A prioritized list of real property acquisition, sustainment,
and disposition activities and projects.
2 Identification of mission and core capabilities associated
with real property.
3 Alignment of real property planning with NNSA and DOE
strategic plans and program guidance.
4 How real property assets meet the needs of the site tenants.
(5) NNSA must use MDI to fulfill the Order’s requirements to:
(a) Assess real property against core capabilities.
(b) Evaluate the relative importance and contributions of real property
to mission accomplishment.
NNSA SD 430.1A 5
10-16-26
(c) Determine the optimum set of facilities and infrastructure needed
to maintain core capabilities.
(6) NNSA must develop or use existing programs and policies to address
requirements related to the following areas outlined in the Order:
(a) Resilience, energy management, and water management.
(b) Environment, health, safety, and security.
(c) Earthquake risks.
(d) Cultural and natural resource preservation.
(e) Historic preservation.
(f) Surveillance, maintenance, and long-term stewardship resource
requirements achievements.
(g) Reduction or consolidation of space, specifically addressing space
policy, program benchmarks for space utilization, and space
assignment and utilization standards.
(7) NNSA must fulfill the Order’s requirements for reporting results of annual
utilization surveys in FIMS.
(8) NNSA must use BUILDER™ to fulfill the Order’s requirements for
infrastructure condition and functionality assessments.
Section 4
b. Acquisition. NNSA must ensure that the acquisition of real property meets
applicable Federal laws and regulations by using the following processes and
systems, regardless of the acquisition method (e.g., purchase, lease, license,
permit, or non-traditional acquisition).
(1) NNSA must determine the acquisition authority and appoint a Certified
Realty Specialist (CRS) and a Real Estate Contracting Officer (RECO) to
fulfill the Order’s requirements for real estate business case analysis
(BCA)1; life-cycle cost analysis; required programmatic investments to
support occupancy and space management, and utilization requirements.
Before reviewing an NNSA real estate BCA, a CRS/RECO must obtain all
acquisition data based on information from the NNSA Real Property
Officer (RPO) guidance, including the RPAM Guide.
(2) A CRS/RECO must review and approve all real estate actions including
all planned acquisitions and implement NNSA real estate practices as
1 A BCA evaluates options to meet a documented need, assessing estimated costs and benefits as well as alignment to
the NNSA and DOE mission. The BCA evaluation criteria should be tailored to the complexity and level of risk associated with
the acquisition.
6 NNSA SD 430.1A
10-16-26
identified by the RPO. A CRS/RECO must review and approve all real
estate documentation, including acquisition documents such as the
Acquisition Evaluation Checklist, the Preliminary Real Estate Plan, and
the Real Estate Acquisition Package among other documents identified in
the RPAM Guide.
(3) NNSA must use the MAP and area plans to fulfill the Order’s requirement
that acquisitions be supported by a mission need.
(4) NNSA must record required information in the FIMS Anticipated Asset
Information Module regardless of the acquisition method or funding
source, based on information from G2, BUILDER™, the MAP, area
plans, and other NNSA RPO guidance, including the RPAM Guide, to
fulfill the Order’s requirements identified in paragraph 4.b(1)b of the
Order.
(5) NNSA must ensure programs meet Federal sustainability guiding
principles in accordance with the latest DOE requirements for NNSA’s
new construction and modernization projects.
(6) NNSA must fulfill the Order’s requirement that new construction of
DOE-owned building areas, except at environmental closure sites, be
offset by the sale, declaration of excess, or demolition of a building area of
an equivalent or greater size.
c. Sustainment. NNSA must achieve the sustainment of real property asset
maintenance, repair, and renovation activities to ensure mission readiness,
operational safety, worker health, environmental protection, and compliance,
security, and property preservation to cost-effectively meet program missions
through the following:
(1) NNSA must ensure programs fulfill the Order’s requirements to maintain
real property assets, including mechanical and electrical systems, and to
ensure real property availability for planned use or disposition using
preventive and predictive maintenance and repairs.
(2) NNSA must use the BUILDER™ Sustainment Management System to
fulfill the Order’s requirements to establish a master equipment list and
conduct infrastructure condition and functionality assessments.
(3) NNSA must follow NNSA RPO guidance to fulfill the Order’s
requirements to establish technical and management processes to align the
performance, functional, and physical attributes of real property assets,
systems, and components in the maintenance program with associated
requirements, design, and operations information, and comply with
applicable DOE maintenance management directives for nuclear facilities.
Section 5
NNSA SD 430.1A 7
10-16-26
(4) NNSA must use G2 to fulfill the Order’s requirements to do the following:
(a) Track direct and indirect funded expenditures for maintenance,
repair, and renovation at the site level;
(b) Manage planning and budgeting for known future cyclical
maintenance, repair, and renovation requirements for major
building components or infrastructure systems based on the
information in BUILDER™; and
(c) Develop a 5-year forecast and update annually to identify financial
investments for the sustainment of real property assets to support
DOE strategic plans, program guidance, Departmental
performance targets, and NNSA RPO guidance.
(5) NNSA must use BUILDER™ assessments, G2 data, and maintenance
analyses to develop interim strategies (previously referred to as bridging
strategies) for planning out the optimum period for the replacement or
extension of a real property asset’s useful life based on the remaining
service life or estimated time to failure, mission dependency, and
condition of the real property assets with the goal of more effectively
identifying financial investments for sustainment of real property to
support NNSA and DOE strategic plans.
(6) NNSA must perform comprehensive energy and water evaluations, and
recommissioning or retro-commissioning for each operating covered
facility at least once during any 4-year period.
(7) NNSA must submit information in FIMS to fulfill the Order’s
requirements to report asset-level annual required maintenance for the
upcoming fiscal year, including the estimated fully burdened costs of
predictive and preventive maintenance and repair activities, and record
annually the results of condition and functionality assessments and real
property utilization assessments.
d. Disposition. NNSA must ensure that the disposition or long-term stewardship of
real property assets is carried out in accordance and compliance with applicable
Federal laws and regulations for excess real property assets at defense nuclear
facilities, using the following systems and processes:
(1) NNSA must use the MAP Deep Dives, area plans, and ERI to fulfill the
Order’s requirements to identify real property assets that are no longer
needed to meet mission needs and may be candidates for reuse and
disposition and to inform prioritization of asset disposition.
(2) NNSA must use G2 to fulfill the Order’s requirements to track the annual
cost of maintaining excess facilities, at the asset level as directed, once the
asset is declared excess and until final disposition.
8 NNSA SD 430.1A
10-16-26
(3) NNSA must use FIMS to fulfill the Order’s requirements to record the
planned disposition of real property.
(4) NNSA must appoint CRS and RECOs to review and approve a Request
for Disposition form before any action to dispose of real property begins
to fulfill the Order’s disposition real estate requirements.
(5) NNSA must establish a disposition program to fulfill the Order’s
requirements to:
(a) Screen real property assets in accordance with Federal laws, and
regulations, and the Department’s internal process for screening
real property assets prior to the declaration of excess;
(b) Dispose of excess real property assets via demolition or other
DOE-approved methods;
(c) Dispose of excess contaminated real property assets in accordance
with applicable Federal laws and regulations, DOE directives, and
NNSA RPO guidance, including the RPAM Guide; and
Section 6
(d) Ensure physical controls, institutional controls, and other
mechanisms to protect people and the environment are in place
while performing disposition activities.
e. Space Management.
(1) Sustainment and Disposition. NNSA must ensure that facility
housekeeping is completed, including removal of supplies, trash, spills,
clutter, and any other loose items, and that programmatic equipment and
personal property are promptly removed from facilities on a graded
approach and properly transferred, relocated, disposed of, or stored for
future use to:
(a) Ensure space needed for future missions is used efficiently.
(b) Avoid delays in operations or excessive activities.
(c) Facilitate the facility’s transition to its next mission use or
activities or disposition if no future use exists.
f. Performance Measurement. NNSA will report performance measures using
FIMS, G2, and other systems identified by the NNSA RPO.
g. Reporting Systems. NNSA will maintain accurate data in both NNSA-internal
and DOE systems including, but not limited to, FIMS, G2, and BUILDER™.
NNSA SD 430.1A 9
10-16-26
8. RESPONSIBILITIES. These responsibilities are in addition to those outlined in the
Order.
a. Administrator.
(1) Ensures accountability for stewardship of NNSA real property assets.
(2) Approves documented program-specific or location/site-specific
exemptions, exclusions, or deviations from requirements of the Order
based on mission needs, efficiency, or efficacy of execution without
disregarding Federal laws and regulations.
(3) Executes real estate transactions to acquire, manage, and dispose of real
property, to include the acceptance of donations and the initiation of
condemnation actions or execution of declarations of taking.
(4) Delegates transactional real estate execution authorities to acquire,
manage, and dispose of real property, with the exception of accepting
donations and initiation on condemnation actions or execution of
declarations of taking.
(5) Provides direct appointments for the RECOs.
b. Associate Administrator for Infrastructure.
(1) Serves as the Program Secretarial Officer, as identified in 5.d. of the
Order, fulfilling all the responsibilities outlined therein.
(2) Serves as the NNSA RPO, responsible for:
(a) Overseeing NNSA stewardship of real property;
(b) Fulfilling all RPO responsibilities issued in the Order and other
DOE policy, with authority to issue guidance to ensure consistent
implementation of the Order and this SD across all NNSA sites
and the Office of Secure Transportation (OST);
(c) Working in consultation with the Order’s OPI where NNSA’s
practices are equivalent to the requirements of the Order;
(d) Delegating internal NNSA actions, while maintaining direct
responsibility for external actions; and
(e) Issuing RPO working-level implementation plans for this SD,
including, but not limited to, the Office of Infrastructure Program
Management Plan, the RPAM Guide, and other real property
management requirements.
10 NNSA SD 430.1A
10-16-26
(3) Houses the NNSA RPO office to provide the support needed to manage
real property assets effectively.
(4) Measures and reports on real property asset performance and real property
asset management performance.
(5) Prepares and submits real property asset information in response to
external requests.
(6) Tracks direct and indirect funded real property acquisitions, operations,
maintenance, recapitalization, and disposition to ensure a holistic view of
NNSA’s real property holdings and expenditures.
Section 7
(7) Establishes transparent, consistent, and repeatable real property practices
across NNSA sites and OST.
(8) Issues the MAP covering an enterprise-wide perspective of the
infrastructure requirements necessary to meet mission needs.
(9) Charters working groups to manage ad hoc and ongoing real property
issues, challenges, and provide vertical and horizontal channels for
innovation to NNSA real property practices.
(10) Reviews and certifies DOE real property inventory for accuracy and
completeness to support DOE’s certification of the annual Federal Real
Property Council data submission.
(11) Ensures the interests and needs of NNSA’s Federal and contractor
infrastructure workforces are represented in NNSA policies and practices;
alerts the Administrator when the infrastructure workforce may be
evolving away from sufficient capability to meet all obligations.
(12) Represents NNSA real property issues in DOE venues, including the
Laboratory Operating Board and the Excess Contaminated Facilities
Working Group. As appropriate, this responsibility may be delegated.
(13) Reviews DOE guidance and directives, including those related to the
FIMS, tailors the guidance and directives to meet NNSA’s requirements,
and transmits the tailored guidance to NNSA field offices and OST for
incorporation into contract requirements.
(14) Issues process-oriented, operational-level guidance annually, or as needed,
integrating guidance and direction necessary to ensure consistent
management of NNSA infrastructure across all programs, sites, and OST,
supplementing the annual guidance with memoranda as necessary to meet
evolving requirements.
(15) Oversees the NNSA real estate program and ensures that CRS/RECO
NNSA SD 430.1A 11
10-16-26
support is available to all programs within NNSA.
(a) Ensures that all Acquisition Evaluation Checklists and BCAs are
reviewed by the NNSA RPO Office and stakeholders.
(b) Ensures that all Preliminary Real Estate Plans and Real Estate
Acquisition Plans are reviewed and approved by an NNSA CRS.
(c) Ensures that all Federal real estate actions are executed by the
appropriate level of delegated authority by the NNSA RECO.
(d) Ensures CRS personnel are qualified and recommends the level of
RECO warrant to request from the Administrator for each CRS.
(16) Establishes policies and guidance for NNSA compliance with the Federal
Building Personnel Training Act, ensuring effective field and contractor
infrastructure workforce oversight.
(17) Ensures future new line-item construction and renovation projects under
their cognizance provide BUILDER™ ASTM-E1557-09 Uniformat II
inventory data down to Level 5, including specific equipment detail
information, in an electronic format determined in coordination with the
BUILDER™ Program Manager and the site-specific BUILDER™ lead.
Project acceptance practices must ensure this data is complete and
sufficient to support management of the facility in BUILDER™, with no
further inventory or condition and functionality assessment actions
required, at least 30 days prior to final project closeout. Explore to what
extent data can be provided at no additional cost for current projects in
progress.
(a) For new construction, the inventory must be fully operational and
free of defects. BUILDER™ condition ratings must be in very
good condition to be accepted into the real property portfolio.
(b) For renovation projects, only the newly installed and removed
inventory data (down to level 5) needs to be updated in
BUILDER™.
Section 8
(18) Ensures all new construction and renovation results in components that are
accessible for preventive and corrective maintenance to support the
maintainability of real property assets throughout the lifetime of the asset.
(19) Ensures clear demarcation between accountability for maintenance of real
and personal property consistent with the different requirements for
funding support of the two property types in cooperation with other
Deputy and Associate Administrators.
12 NNSA SD 430.1A
10-16-26
c. Deputy Administrators and Associate Administrators.
(1) Ensure personal property supported by their programs is inventoried and
maintained with responsibility clearly demarcated from the real property
containing the personal property in cooperation with the Associate
Administrator for Infrastructure.
(2) Coordinate program-driven real property investments with the Office of
Infrastructure to ensure balanced investment across programmatic and
enabling infrastructure.
(3) Ensure that program-driven real property actions involve the NNSA
RECO.
(4) Ensure all personal property and materials are removed from facilities
when the asset is declared excessed; personal property must be properly
relocated or stored for future use, properly transferred or moved to an
institutional entity that will be using the space or disposed of if no future
use exists.
(5) Ensure Federal offices are responsible for planning, construction,
operations, maintenance, and the disposition of real property assets that
meet the requirements outlined in Attachment 1.
d. Associate Administrator for Environment, Safety, and Health
(1) Ensures NNSA programmatic leadership for resilience in support of the
Order and other applicable regulations and statutory requirements.
(2) Manages the National Environmental Policy Act (NEPA) Compliance
Program to include leading or facilitating NEPA analysis and development
of environmental impact statements, environmental assessments, and
categorical exclusions in support of effective and efficient real property
asset management and mission delivery.
(3) Lead programmatic efforts to implement capital cost avoidance measures
through performance contracts (e.g., Energy Savings Performance
Contracts, Utility Energy Service Contracts).
e. Associate Administrator for Budget and Accounting.
(1) Upon request, leads or supports BCAs.
(2) Advises on how to ensure alignment with infrastructure planning and the
Planning, Programming, Budgeting, and Execution (PPBE) process.
(3) Ensures funding used by management and operating (M&O) contractors to
manage real property assets is used consistent with applicable statutory
NNSA SD 430.1A 13
10-16-26
and policy requirements.
f. Field Office Managers
(1) Perform all duties outlined in Section 5.h. of the Order.
(2) Ensure accountability for all aspects of Federal oversight of real property
are assigned to their staff, including maintaining an accurate inventory of
real property under their control. They may divide responsibility between
direct reports as necessary to match local needs.
(3) Ensure BUILDER™, G2, MDI, ERI, and FIMS data are accurate,
consistent, and in agreement with the NNSA RPO’s guidance, including
the RPAM Guide. At the end of the fiscal year, certify the accuracy of the
data to the NNSA RPO to support the NNSA certification of data to DOE.
(4) Provide oversight and ensure that the Contracting Officer incorporates the
CRD (Attachment 1) and all other applicable real property requirements
identified by the NNSA RPO into M&O contracts.
Section 9
g. Assistant Deputy Administrator for Secure Transportation.
(1) Implements this Supplemental Directive through a Memorandum of
Agreement with the NNSA RPO, with consideration of the statutory
requirements of OST's authorization and appropriation.
(2) Determines all OST fund expenditures for OST property and facilities.
9. REFERENCES. The following references are useful or necessary to perform the
functions covered by this SD. Additional references are available in the Order.
a. Federal Building Personnel Training Act of 2010, Pub. L. 111-308, 124 Stat.
3282 (2010), December 14, 2010.
b. 41 U.S.C. § 102 Federal Management Regulation.
c. 42 U.S.C. § 8523 Energy and Water Management Requirements.
d. GSA Acquisition Regulation Part 570, Acquiring Leasehold Interests in Real
Property.
e. DOE, Asset Management Plan.
f. DOE O 433.1 (series) Maintenance Management Program for DOE Nuclear
Facilities.
g. DOE O 430.1(series), Real Property Asset Management (RPAM).
h. DOE G 580.1-1A Chg 1,) Personal Property.
14 NNSA SD 430. lA
10-16-26
1. DOE Real Estate Desk Guide, the primary source of information and guidance for
planning, acquiring, managing, and disposing of DOE real property or interests
therein.
J.
k.
DOE, Real Property Efficiency Plan, September 2015.
DOE, Federal Energy Management Program, Facility Energy Management
Guidelines and Criteria for Energy and Water Evaluations in Covered Facilities,
November 28, 2008 ..
1. Facilities Information Management System (FIMS) User's Guide, Training
Workbook, and Reporting Guide, November 2016.
m.
n.
Office oflnfrastructure Life cycle Management, Program Management Plan.
NNSA Real Property Asset Management Guide.
10. DEFINITIONS. See Attachment 2.
11. ACRONYMS. See Attachment 3
12. CONTACT. Infrastructure Planning and Integration Division, Office oflnfrastructure,
planningandintegration@nnsa.doe.gov.
BY ORDER OF THE ADMINISTRATOR:
Attachments:
1. Contractor Requirements Document.
2. Definitions.
3. Acronyms.
Administrator
mailto:planningandintegration@nnsa.doe.gov
NNSA SD 430.1A Attachment 1
10-16-26 AT1-1
ATTACHMENT 1: CONTRACTOR REQUIREMENTS DOCUMENT
NNSA SD 430.1A
This Contractor Requirements Document (CRD) applies to the National Nuclear Security
Administration (NNSA) contractors whose contracts involve the acquisition, management,
maintenance, or disposition of real property assets. Contractors are expected to meet these
functional requirements by tailoring their business and management practices and using standard
industry practices.
Regardless of who performs the work, the contractor is responsible for complying with the
requirements of this CRD, and for flowing down the requirements to subcontracts at any tier to
the extent necessary to ensure the subcontractor’s compliance with the requirements.
The Department of Energy (DOE) Order (O) 430.1C, herein referred to as the Order, and this
CRD establish performance-based outcomes. Where specific guidance is not given in the Order,
this CRD, the Office of Infrastructure Program Management Plan, the NNSA Real Property
Asset Management (RPAM) Guide, or any other NNSA Real Property Officer (RPO) guidance,
contractors have the latitude to accomplish the required outcomes via their own processes.
1. REQUIREMENTS.
a. Planning. Based on NNSA-furnished program planning guidance, the contractor
must:
(1) Assess the current real property assets against program mission
projections;
Section 10
(2) Use the Infrastructure Planning Principles to inform real property
planning;
(3) Incorporate early-stage planning infrastructure activities and information
into real estate planning development;
(4) Identify the specific real property assets, needs, gaps, projects, and
activities required to meet program mission projections;
(5) Develop interim strategies (bridging strategies) for planning the optimum
period for the replacement or extension of a real property asset’s useful
life based on the remaining service life or estimated time to failure,
mission dependency, and condition of the real property assets;
(6) Provide planning input on the infrastructure necessary to meet near-, mid-,
and long-term mission requirements into the Master Asset Plan (MAP).
This input must align with the data provided in the NNSA Program
Management System Generation 2 (G2); and
(7) Propose a 25-year planning horizon through the development of area plans
and MAP Deep Dives.
Attachment 1 NNSA SD 430.1A
AT1-2 10-16-26
b. Infrastructure Data Management. The contractor must maintain G2 data and
records, Facilities Information Management System (FIMS) data and records, and
data and records to support BUILDER™ Sustainment Management System
(BUILDER™) and other data systems specified by NNSA and DOE policy,
including the guidance provided by the NNSA RPO. Data quality and timeliness
of data should support NNSA decision-making without a request for data updates.
FIMS data must be verified annually.
c. Facility Utilization. Contractors must manage the utilization of their facilities
using industry best practices and applicable Government standards, and in
accordance with NNSA RPO guidance, including the RPAM Guide. Each
contractor must have a space management system, completely accessible to
Federal oversight and field office staff. The space management system must
satisfy DOE, regulatory, and statutory requirements for determining utilization
rates, including the requirement to produce annual reports. The data collected by
the contractor must be sufficient for NNSA and the contractor to reach an
agreement on the optimum size of the site for current and future mission needs.
The data must be sufficient for NNSA’s use to justify the results to Congress, the
Office of Management and Budget, and other external stakeholders, and to meet
the Laboratory Operating Board assessment requirement for utilization.
(1) The contractor must have a space management system that tracks the
current program users of all facilities and ensures all users fit within DOE,
NNSA, and local standards for space usage. The system must also:
(a) Ensure vacating users are not relieved of their responsibility for a
space until facility housekeeping, which includes removing
supplies, trash, spills, clutter and of any other loose items, and
removal of programmatic equipment and personal property has
been completed. Programmatic equipment removal should be done
on a graded approach and should consider the relationship of the
equipment with the building and building systems and the planned
use/life cycle phase of the space. Personal property must be
properly relocated or stored for future use, properly transferred or
moved to an institutional entity that will be using the space, or
disposed of if no future use exists.
(b) Allow the contractor to collect, if needed, a space use charge from
vacating users to recover any additional cost associated with the
remaining programmatic equipment, materials, and personal
property until it has been removed or properly transferred, stored,
or relocated.
Section 11
(c) Support DOE and NNSA reporting requirements, including FIMS
utilization data.
NNSA SD 430.1A Attachment 1
10-16-26 AT1-3
(d) Be available to field office personnel and other Federal oversight
personnel for review.
(2) Contractors must ensure optimum performance of a facility, in accordance
with design or current operating needs, over the useful life of the facility,
while meeting building occupancy and mission requirements.
(3) A subset of these data elements, or others determined by the NNSA RPO,
may be reported through G2. The NNSA RPO will provide further
guidance and requirements.
d. Maintenance and Modernization. The contractor must maintain real property
assets in a manner that promotes operational safety, worker health, environmental
compliance, property preservation, and cost-effectiveness while meeting the
program’s missions and protecting the Government’s investment in real property.
This requires a balanced approach that not only sustains the assets, but also
provides for their recapitalization and includes the following:
(1) Integrated computer systems that include condition and functionality
assessment information for real property assets, a work control system,
management of deferred maintenance, a method to prioritize, and systems
to budget and track maintenance expenditures.
(2) Identification of 5-year maintenance and repair requirements sustainment
and funding for deferred maintenance reduction.
(3) Identification of 5-year recapitalization and capital construction
requirements to replace or modernize existing facilities.
(4) Condition and functionality assessments of real property assets according
to the frequency dictated by the NNSA RPO. At least once within a
5-year period, verify that all required inspections are completed and
ensure BUILDER™ reflects all outstanding and completed maintenance
work orders for repairs and overhauls. The condition and functionality
assessment program shall use a tailored approach based on facility status,
mission, importance, and the magnitude of the hazards associated with
facilities and infrastructure.
(5) Inspection methodology shall be consistent with industry best practices
and shall include identification of safety and health hazards. Deferred
maintenance estimates will be based on BUILDER™ output. The
condition and functionality assessment program will support the reporting
requirements of G2 and FIMS. Each site’s condition and functionality
assessment process must be consistent, auditable, and current by regularly
updating the site’s BUILDER™ database with outstanding and completed
work orders.
Attachment 1 NNSA SD 430.1A
AT1-4 10-16-26
e. Disposition. Contractors must ensure vacating users are not relieved of their
responsibility for a space until facility housekeeping is complete – which includes
removing supplies, trash, spills, clutter and of any other loose items – and
programmatic equipment and personal property has been removed; programmatic
equipment removal should be done on a graded approach and should consider the
relationship of the equipment with the building and building systems and the
planned use/life cycle phase of the space; personal property must be properly
relocated or stored for future use, properly transferred or moved to an institutional
entity that will be using the space, or disposed of if no future use exists.
Contractors must also manage the disposition of their facilities to meet
requirements identified by the NNSA RPO.
Section 12
f. Workforce. Contractors must maintain a trained workforce, sufficient to achieve
the NNSA mission. They must monitor their workforce and ensure the NNSA
RPO is aware of developing workforce-related issues and concerns that could
create risks for infrastructure management.
g. Documentation. The contractor must document its real property management
activities, including:
(1) The site’s plan to meet program missions;
(2) Budgets and planning estimates; and
(3) Performance outcomes via the MAP Deep Dive process.
h. Real Estate. The contractor must:
(1) Follow the procedures specified by the NNSA RPO, including guidance
provided through the RPAM Guide;
(2) Prepare Service Contracts or Operation Agreements with related Real
Property Checklist, Preliminary Real Estate Plans (PREPs), Real Estate
Acquisition Package, Transfer Request Memo, Acceptance Packages,
Tenant Improvement Checklist, Lease Rating Scorecard, De-excess
Request Memo, and Requests for Disposition (RFDs), obtaining all
required approvals and concurrences before proceeding with a real estate
action; and
(3) Submit all PREPs and RFDs to acquire, manage, and dispose of real
property assets to their field office and to the NNSA Headquarters
Certified Realty Specialist through their Field Office Manager or designee
for review and approval.
i. Long-Term Stewardship (LTS). LTS activities must be consistent with
programming and real property requirements dictated by statutory, regulatory, and
NNSA SD 430.1A Attachment 1
10-16-26 AT1-5
other DOE policies transmitted through or established by the NNSA RPO and the
Office of Environment, Safety, and Health (NA-ESH).
j. Resilience and Energy and Water Management. Resilience and Energy and Water
Management activities must be consistent with programming and real property
requirements dictated by statutory, regulatory, and other DOE policies transmitted
through the NNSA RPO and NA-ESH. Contractors must provide annual reports
to the NNSA RPO, NA-ESH, or designee on the accomplishment of requirements.
2. RESPONSIBILITIES.
a. Management and Operating Contractor.
(1) Assess current real property assets against program mission projections.
(2) Use Infrastructure Planning Principles to inform real property planning.
(3) Incorporate early-stage planning infrastructure activities and information
into real estate planning development.
(4) Identify specific real property assets, needs, gaps, projects, and activities
required to meet program mission projections.
(5) Develop interim strategies (bridging strategies) for planning the optimum
period for the replacement or extension of a real property asset’s useful
life based on the remaining service life or estimated time to failure,
mission dependency, and condition of the real property assets.
(6) Provide planning input on the infrastructure necessary to meet near-, mid-,
and long-term mission requirements into the Master Asset Plan (MAP).
This input must align with the data provided in the NNSA Program
Management System Generation 2 (G2).
(7) Propose a 25-year planning horizon through the development of area plans
and MAP Deep Dives.
(8) Maintain G2 data and records, Facilities Information Management System
(FIMS) data and records, and data and records to support BUILDER™
Sustainment Management System (BUILDER™) and other data systems
specified by NNSA and DOE policy, including the guidance provided by
the NNSA RPO.
Section 13
(9) Have a space management system that tracks the current program users of
all facilities and ensures all users fit within DOE, NNSA, and local
standards for space usage.
(10) Maintain real property assets in a manner that promotes operational safety,
worker health, environmental compliance, property preservation, and cost-
Attachment 1 NNSA SD 430.1A
AT1-6 10-16-26
effectiveness while meeting the program’s missions and protecting the
Government’s investment in real property.
(11) Maintain a trained workforce, sufficient to achieve the NNSA mission.
(12) Provide annual reports to the NNSA RPO, NA-ESH, or designee on the
accomplishment of requirements.
NNSA SD 430.1A Attachment 2
10-16-26 AT2-1
ATTACHMENT 2: DEFINITIONS
Note: All attachments, except Attachment 1 (which applies to contractors only), apply to
Federal and contractor employees.
1. DEFINITIONS. National Nuclear Security Administration (NNSA) will rely on the
original source documentation for interpretation of all definitions, drawing on and using
the definitions in the Department of Energy (DOE) Order 430.1C, herein referred to as
the Order, except where the NNSA Real Property Officer (RPO) determines additional
clarification is needed or where the source documentation provides latitude beyond that
within the definition provided in the Order. The following definitions are provided in
addition to those in the Order:
a. Area. A portion of a site. This term is applicable at larger sites that have been
segmented into areas for facilities planning or other purposes, as opposed to a
special area, which is off-site. Example: The Area 23 at the Nevada Nuclear
Security Site (NNSS), is a portion of NNSS devoted primarily to administrative
functions.
b. Area Planning. A methodology used to develop plans that create a framework for
modernization and drive prioritized integrated investments by incorporating
mission requirements with viable investment options.
c. BUILDER™. A knowledge-based sustainment management system, which
includes condition and functionality assessments.
d. Condemnation. A judicial proceeding, initiated by the Government under its right
of eminent domain, to take private property for public use.
e. Certified Realty Specialist (CRS). A DOE employee, in the realty specialist
series, who is certified in one or more of the three specialty realty areas:
acquisition, leasing, and land management and disposal. Employees so certified
are authorized to prepare and implement real estate actions within certified
specialty areas, and to provide the required review and approval prior to execution
by a DOE official with a delegation of authority for real estate actions. Detailed
guidance and procedures for becoming a CRS are found in the DOE Acquisition
Certifications Program Handbook. An NNSA CRS must be an NNSA employee.
f. Declaration of Taking. A pleading filed in court with a condemnation proceeding,
whereby, with the deposit of just compensation, the interest in the property, as
stated in the pleading, is vested at once in the Government.
g. Disposition. The demolition of a real estate asset or the permanent or temporary
transfer of NNSA control and custody of real property assets to another who
acquires rights to control, use, or relinquish the property.
Attachment 2 NNSA SD 430.1A
AT2-2 10-16-26
h. Donation/Gift. The voluntary transfer or conveyance of an interest in real
property without payment or consideration of any kind.
Section 14
i. Enabling Infrastructure. Land, roads, walkways, utilities, and support facilities
that are required for the programmatically focused facilities to complete their
mission needs.
j. Excess-Facility Risk Index (ERI). NNSA’s risk-based, consequence metric for
retired facilities. The quantitative score assigned by ERI is used to aid
prioritization of disposition projects, based on the risk posed to worker and public
safety or mission work.
k. Facilities Information Management System (FIMS). The DOE corporate real
property asset database for all real property owned, leased, or managed by DOE.
l. G2. The NNSA’s Program Management System Generation 2 system that is
NNSA’s authoritative data source for integrated infrastructure planning efforts
and supports infrastructure programming activities.
m. Integrated Infrastructure Planning (IIP) Team. A cross-functional body of NNSA
entities, including NNSA headquarters, laboratories, plants, and sites which looks
to address infrastructure planning priorities, facilitate risk-informed decisions, and
ensure completion of infrastructure investments while improving NNSA’s agility,
resiliency, and decision making.
n. Lease. A contractual agreement that gives exclusive possessory interest in the
property for a specified time, in exchange for payment of rent to the owner.
o. Lease Rating Scorecard and Criteria. NNSA’s risk-based methodology that
measures leased data to evaluate the risk a proposed lease will pose to the
Government. The calculated lease rating score informs the decision-making
process, including the present value calculation criteria required by the Office of
Management and Budget.
p. Master Asset Plan (MAP). NNSA’s enterprise-wide infrastructure strategic plan.
The MAP covers the infrastructure necessary to meet current, planned, and future
mission requirements. It provides an integrated view of NNSA infrastructure and
a prioritized infrastructure roadmap that aligns with NNSA’s integrated
infrastructure priorities and agile, time-phased approaches to reduce risks to
mission execution in the near, mid, and long-terms.
q. MAP Deep Dive. An NNSA site visit that provides a forum for discussion and
understanding of mission requirements. These discussions are capability focused
and drive current and planned infrastructure investments based on condition,
capacity gaps, and risks to help align site and program-level infrastructure
priorities with NNSA’s goals and resources.
NNSA SD 430.1A Attachment 2
10-16-26 AT2-3
r. Memorandum of Agreement. A formal document outlining a cooperative
relationship and specific responsibilities between two or more parties aiming to
achieve a common goal.
s. Mission Dependency Index (MDI). NNSA’s risk-based, consequence to mission
metric that assigns a quantitative score to a real property asset. This score
informs decision-makers of the potential impact the asset loss would have on
NNSA’s mission.
t. Original Source Documentation. The records and reports that support the data
collection efforts. This information is usually compiled firsthand, by program
subject matter experts in the field.
u. Personal Property. All equipment, material, and supplies not classified as real
property (Refer to DOE O 580.1A and to 41 CFR Chapter 102-71). NNSA also
considers personal property to be items that are not permanently affixed to the
real property asset and can be removed without serious impact either to the real
property or to the items themselves. Personal property may include items
necessary for the course of normal administrative or business operations, such as
office furniture, as well as science and engineering equipment.
Section 15
v. Preliminary Real Estate Plan (PREP). A decision document affecting all future
site-selection activity that includes a description of the program or project and an
analysis of all viable options and alternatives considered, along with the
advantages and disadvantages of each.
w. Real Estate Acquisition Package (REAP). A decision document affecting all
future site-selection leased activity that follows the PREP submission and
includes the remaining information needed prior to the lease execution.
x. Real Estate Contracting Officer (RECO). A CRS who has been issued a
contracting officer warrant to execute real estate actions, within prescribed limits.
An NNSA RECO must be an NNSA employee.
y. Request for Disposition (RFD). The decision document affecting the disposition
of an asset, which includes a description of the facility; the annual surveillance,
operations, and maintenance costs associated with the facility; a condition and
functionality assessment of the facility and the associated maintenance backlog;
and the estimated demolition costs and date.
z. Retired Asset. Any asset that has a shutdown status in FIMS.
NNSA SD 430.1A Attachment 3
10-16-26 AT3-1
ATTACHMENT 3: ACRONYMS/ABBREVIATIONS
Note: All attachments, except Attachment 1 (which applies to contractors only), apply to Federal
and contractor employees.
a. BCA Business Case Analysis.
b. BUILDER BUILDER™ Sustainment Management System.
c. CRD Contractor Requirements Document.
d. CRS Certified Realty Specialist.
e. ERI Excess-Facility Risk Index.
f. FIMS Facilities Information Management System.
g. FRPP Federal Real Property Profile.
h. G2 NNSA’s Program Management System Generation 2.
i. IIP Integrated Infrastructure Planning.
j. LTS Long-Term Stewardship.
k. MAP Master Asset Plan.
l. MDI Mission Dependency Index.
m. M&O Management and Operating.
n. NEPA National Environmental Policy Act.
o. OPI Office of Primary Interest.
p. OST Office of Secure Transportation.
q. PPBE Planning, Programming, Budgeting, and Execution.
r. PREP Preliminary Real Estate Plan.
s. REAP Real Estate Acquisition Package.
t. RECO Real Estate Contracting Officer.
u. RFD Request for Disposition.
Attachment 3 NNSA SD 430.1A
AT3-2 10-16-26
v. RPAM Real Property Asset Management.
w. RPO Real Property Officer.
1. PURPOSE. This Supplemental Directive (SD) updates the authorities, requirements, and responsibilities for the National Nuclear Security Administration (NNSA) real property asset management and supplements the requirements of Department of Energy (...
2. AUTHORITY. DOE O 430.1C Chg. 2, Real Property Asset Management, dated September 17, 2020.
3. CANCELLATION. NNSA SD 430.1, Real Property Asset Management, dated January 18, 2017.
Cancellation of a directive does not modify or otherwise affect any contractual or regulatory obligation to comply with the directive. Contractor Requirements Documents (CRDs) incorporated into a contract remain in effect throughout the contract term...
4. APPLICABILITY.
a. Federal. Applies to all NNSA Elements.
b. Contractors. The CRD, provided as Attachment 1, sets forth requirements that apply to contractors.
c. Equivalencies/Exemptions.
(1) Equivalency: In accordance with the responsibilities and authorities assigned by Executive Order 12344, codified at 50 United States Code sections 2406 and 2511, and to ensure consistency throughout the joint Navy/DOE Naval Nuclear Propulsion Pr...
Section 16
5. SUMMARY OF CHANGES.
a. Changes the Office of Primary Interest (OPI) to the Office of Infrastructure which reflects the reorganization of the Office of Safety, Infrastructure, and Operations and the Office of Acquisition and Project Management.
b. Incorporates the updated infrastructure life cycle management tools, processes, and responsibilities throughout the SD and Attachment 1 to continue efficiently managing DOE and NNSA real property portfolio.
c. Updates responsibilities and authorities to better align with current DOE and NNSA policy.
6. BACKGROUND. DOE O 430.1C Chg. 2, hereafter referred to as the Order, replaced the site-level requirements of DOE O 430.1B, Real Property Asset Management, dated September 24, 2003, with the responsibility for the DOE Under Secretaries to meet the ...
a. Real Property Asset Management (RPAM) Guide. NNSA’s guide for effectively managing real property assets over their life cycle by establishing a standardized, repeatable, and disciplined process.
b. Program Management System Generation 2 (G2). NNSA’s authoritative data source for integrated infrastructure planning efforts and supports infrastructure programming activities.
c. BUILDER™ Sustainment Management System (BUILDER™). NNSA’s authoritative data source for information related to condition and functionality assessments.
d. Facilities Information Management System (FIMS). DOE’s real property database of record for storing real property data. The Department is required to verify and validate the accuracy of the Federal Real Property Profile (FRPP) annual submission. ...
e. Infrastructure Planning Principles. A set of principles and practices developed by the Integrated Infrastructure Planning (IIP) Team to guide and support the planning process must be incorporated throughout the enterprise-wide plan and NNSA’s inte...
f. Master Asset Plan (MAP). NNSA’s enterprise-wide infrastructure strategic plan. The MAP covers the infrastructure necessary to meet current, planned, and future mission requirements, through the integration of 5-year real property planning and bud...
g. MAP Deep Dives. NNSA site visits that provide a forum for discussing and understanding mission requirements. These discussions are capability-focused and drive current and planned infrastructure investments based on condition, capacity gaps, and ...
h. Area Planning. A methodology used to develop plans that create a framework for modernization and drive prioritized integrated investments by incorporating mission requirements with viable investment options.
i. Enterprise Blueprint. NNSA’s roadmap that aligns timely delivery of specialized infrastructure with NNSA mission demands by focusing on meeting the program of record, developing modern nuclear weapons systems, and sustaining an unrivaled technolog...
j. Mission Dependency Index (MDI). NNSA’s risk-based, consequence-to- mission metric that assigns a quantitative score to a real property asset. This score informs decision-makers of the potential impact the asset’s loss would have on NNSA’s mission.
k. Excess-Facility Risk Index (ERI). NNSA’s risk-based consequence metric for retired facilities. The quantitative score assigned by ERI is used to aid in the prioritization of disposition projects based on the risk posed to worker and public safety...
l. Lease Rating Scorecard and Criteria. NNSA’s risk-based methodology that measures leased data to evaluate the risk a proposed lease will pose to the Government. The calculated lease rating score informs the decision-making process, including the p...
Section 17
7. REQUIREMENTS. NNSA entities managing real property must keep data in G2, FIMS, and BUILDER™ systems current. For the purposes of this SD, “current” means data must be updated at sufficient intervals to ensure complete and accurate data used for ...
a. Planning and Budgeting. NNSA will meet the Order’s requirements for real property asset management planning and budgeting, preparation of annual planning guidance, real property planning, and 5-year real property planning and budgeting documentat...
(2) NNSA must incorporate early-stage planning infrastructure activities, principles, and information into the development of real estate planning development.
(4) NNSA must use the MAP, MAP Deep Dives, area plans, and RPAM Guide to fulfill the Order’s requirements for the following:
(a) Annual planning guidance.
(b) Real property planning.
(c) Five-year real property planning and budgeting that includes:
1 A prioritized list of real property acquisition, sustainment, and disposition activities and projects.
2 Identification of mission and core capabilities associated with real property.
3 Alignment of real property planning with NNSA and DOE strategic plans and program guidance.
4 How real property assets meet the needs of the site tenants.
(a) Assess real property against core capabilities.
(b) Evaluate the relative importance and contributions of real property to mission accomplishment.
(c) Determine the optimum set of facilities and infrastructure needed to maintain core capabilities.
(6) NNSA must develop or use existing programs and policies to address requirements related to the following areas outlined in the Order:
(a) Resilience, energy management, and water management.
(b) Environment, health, safety, and security.
(c) Earthquake risks.
(d) Cultural and natural resource preservation.
(e) Historic preservation.
(f) Surveillance, maintenance, and long-term stewardship resource requirements achievements.
(g) Reduction or consolidation of space, specifically addressing space policy, program benchmarks for space utilization, and space assignment and utilization standards.
(7) NNSA must fulfill the Order’s requirements for reporting results of annual utilization surveys in FIMS.
b. Acquisition. NNSA must ensure that the acquisition of real property meets applicable Federal laws and regulations by using the following processes and systems, regardless of the acquisition method (e.g., purchase, lease, license, permit, or non-t...
(1) NNSA must determine the acquisition authority and appoint a Certified Realty Specialist (CRS) and a Real Estate Contracting Officer (RECO) to fulfill the Order’s requirements for real estate business case analysis (BCA)0F ; life-cycle cost analysi...
(4) NNSA must record required information in the FIMS Anticipated Asset Information Module regardless of the acquisition method or funding source, based on information from G2, BUILDER™, the MAP, area plans, and other NNSA RPO guidance, including the ...
(5) NNSA must ensure programs meet Federal sustainability guiding principles in accordance with the latest DOE requirements for NNSA’s new construction and modernization projects.
(6) NNSA must fulfill the Order’s requirement that new construction of DOE-owned building areas, except at environmental closure sites, be offset by the sale, declaration of excess, or demolition of a building area of an equivalent or greater size.
Section 18
c. Sustainment. NNSA must achieve the sustainment of real property asset maintenance, repair, and renovation activities to ensure mission readiness, operational safety, worker health, environmental protection, and compliance, security, and property p...
(1) NNSA must ensure programs fulfill the Order’s requirements to maintain real property assets, including mechanical and electrical systems, and to ensure real property availability for planned use or disposition using preventive and predictive maint...
(3) NNSA must follow NNSA RPO guidance to fulfill the Order’s requirements to establish technical and management processes to align the performance, functional, and physical attributes of real property assets, systems, and components in the maintenanc...
(4) NNSA must use G2 to fulfill the Order’s requirements to do the following:
(a) Track direct and indirect funded expenditures for maintenance, repair, and renovation at the site level;
(b) Manage planning and budgeting for known future cyclical maintenance, repair, and renovation requirements for major building components or infrastructure systems based on the information in BUILDER™; and
(c) Develop a 5-year forecast and update annually to identify financial investments for the sustainment of real property assets to support DOE strategic plans, program guidance, Departmental performance targets, and NNSA RPO guidance.
(5) NNSA must use BUILDER™ assessments, G2 data, and maintenance analyses to develop interim strategies (previously referred to as bridging strategies) for planning out the optimum period for the replacement or extension of a real property asset’s use...
(6) NNSA must perform comprehensive energy and water evaluations, and recommissioning or retro-commissioning for each operating covered facility at least once during any 4-year period.
(7) NNSA must submit information in FIMS to fulfill the Order’s requirements to report asset-level annual required maintenance for the upcoming fiscal year, including the estimated fully burdened costs of predictive and preventive maintenance and repa...
d. Disposition. NNSA must ensure that the disposition or long-term stewardship of real property assets is carried out in accordance and compliance with applicable Federal laws and regulations for excess real property assets at defense nuclear facili...
(1) NNSA must use the MAP Deep Dives, area plans, and ERI to fulfill the Order’s requirements to identify real property assets that are no longer needed to meet mission needs and may be candidates for reuse and disposition and to inform prioritization...
(3) NNSA must use FIMS to fulfill the Order’s requirements to record the planned disposition of real property.
(4) NNSA must appoint CRS and RECOs to review and approve a Request for Disposition form before any action to dispose of real property begins to fulfill the Order’s disposition real estate requirements.
(5) NNSA must establish a disposition program to fulfill the Order’s requirements to:
(a) Screen real property assets in accordance with Federal laws, and regulations, and the Department’s internal process for screening real property assets prior to the declaration of excess;
(b) Dispose of excess real property assets via demolition or other DOE-approved methods;
(c) Dispose of excess contaminated real property assets in accordance with applicable Federal laws and regulations, DOE directives, and NNSA RPO guidance, including the RPAM Guide; and
(d) Ensure physical controls, institutional controls, and other mechanisms to protect people and the environment are in place while performing disposition activities.
Section 19
e. Space Management.
(1) Sustainment and Disposition. NNSA must ensure that facility housekeeping is completed, including removal of supplies, trash, spills, clutter, and any other loose items, and that programmatic equipment and personal property are promptly removed fr...
(a) Ensure space needed for future missions is used efficiently.
(b) Avoid delays in operations or excessive activities.
(c) Facilitate the facility’s transition to its next mission use or activities or disposition if no future use exists.
f. Performance Measurement. NNSA will report performance measures using FIMS, G2, and other systems identified by the NNSA RPO.
8. RESPONSIBILITIES. These responsibilities are in addition to those outlined in the Order.
a. Administrator.
(1) Ensures accountability for stewardship of NNSA real property assets.
(3) Executes real estate transactions to acquire, manage, and dispose of real property, to include the acceptance of donations and the initiation of condemnation actions or execution of declarations of taking.
(4) Delegates transactional real estate execution authorities to acquire, manage, and dispose of real property, with the exception of accepting donations and initiation on condemnation actions or execution of declarations of taking.
b. Associate Administrator for Infrastructure.
(2) Serves as the NNSA RPO, responsible for:
(a) Overseeing NNSA stewardship of real property;
(b) Fulfilling all RPO responsibilities issued in the Order and other DOE policy, with authority to issue guidance to ensure consistent implementation of the Order and this SD across all NNSA sites and the Office of Secure Transportation (OST);
(c) Working in consultation with the Order’s OPI where NNSA’s practices are equivalent to the requirements of the Order;
(d) Delegating internal NNSA actions, while maintaining direct responsibility for external actions; and
(e) Issuing RPO working-level implementation plans for this SD, including, but not limited to, the Office of Infrastructure Program Management Plan, the RPAM Guide, and other real property management requirements.
(3) Houses the NNSA RPO office to provide the support needed to manage real property assets effectively.
(4) Measures and reports on real property asset performance and real property asset management performance.
(5) Prepares and submits real property asset information in response to external requests.
(6) Tracks direct and indirect funded real property acquisitions, operations, maintenance, recapitalization, and disposition to ensure a holistic view of NNSA’s real property holdings and expenditures.
(7) Establishes transparent, consistent, and repeatable real property practices across NNSA sites and OST.
(8) Issues the MAP covering an enterprise-wide perspective of the infrastructure requirements necessary to meet mission needs.
(9) Charters working groups to manage ad hoc and ongoing real property issues, challenges, and provide vertical and horizontal channels for innovation to NNSA real property practices.
(10) Reviews and certifies DOE real property inventory for accuracy and completeness to support DOE’s certification of the annual Federal Real Property Council data submission.
(11) Ensures the interests and needs of NNSA’s Federal and contractor infrastructure workforces are represented in NNSA policies and practices; alerts the Administrator when the infrastructure workforce may be evolving away from sufficient capability ...
(12) Represents NNSA real property issues in DOE venues, including the Laboratory Operating Board and the Excess Contaminated Facilities Working Group. As appropriate, this responsibility may be delegated.
(13) Reviews DOE guidance and directives, including those related to the FIMS, tailors the guidance and directives to meet NNSA’s requirements, and transmits the tailored guidance to NNSA field offices and OST for incorporation into contract requireme...
(14) Issues process-oriented, operational-level guidance annually, or as needed, integrating guidance and direction necessary to ensure consistent management of NNSA infrastructure across all programs, sites, and OST, supplementing the annual guidance...
(15) Oversees the NNSA real estate program and ensures that CRS/RECO support is available to all programs within NNSA.
(a) Ensures that all Acquisition Evaluation Checklists and BCAs are reviewed by the NNSA RPO Office and stakeholders.
(b) Ensures that all Preliminary Real Estate Plans and Real Estate Acquisition Plans are reviewed and approved by an NNSA CRS.
(c) Ensures that all Federal real estate actions are executed by the appropriate level of delegated authority by the NNSA RECO.
(d) Ensures CRS personnel are qualified and recommends the level of RECO warrant to request from the Administrator for each CRS.
Section 20
(16) Establishes policies and guidance for NNSA compliance with the Federal Building Personnel Training Act, ensuring effective field and contractor infrastructure workforce oversight.
(17) Ensures future new line-item construction and renovation projects under their cognizance provide BUILDER™ ASTM-E1557-09 Uniformat II inventory data down to Level 5, including specific equipment detail information, in an electronic format determin...
(a) For new construction, the inventory must be fully operational and free of defects. BUILDER™ condition ratings must be in very good condition to be accepted into the real property portfolio.
(b) For renovation projects, only the newly installed and removed inventory data (down to level 5) needs to be updated in BUILDER™.
c. Deputy Administrators and Associate Administrators.
(1) Ensure personal property supported by their programs is inventoried and maintained with responsibility clearly demarcated from the real property containing the personal property in cooperation with the Associate Administrator for Infrastructure.
(3) Ensure that program-driven real property actions involve the NNSA RECO.
(4) Ensure all personal property and materials are removed from facilities when the asset is declared excessed; personal property must be properly relocated or stored for future use, properly transferred or moved to an institutional entity that will b...
(5) Ensure Federal offices are responsible for planning, construction, operations, maintenance, and the disposition of real property assets that meet the requirements outlined in Attachment 1.
d. Associate Administrator for Environment, Safety, and Health
(1) Ensures NNSA programmatic leadership for resilience in support of the Order and other applicable regulations and statutory requirements.
e. Associate Administrator for Budget and Accounting.
(1) Upon request, leads or supports BCAs.
f. Field Office Managers
g. Assistant Deputy Administrator for Secure Transportation.
(1) Implements this Supplemental Directive through a Memorandum of Agreement with the NNSA RPO, with consideration of the statutory requirements of OST's authorization and appropriation.
9. REFERENCES. The following references are useful or necessary to perform the functions covered by this SD. Additional references are available in the Order.
a. Federal Building Personnel Training Act of 2010, Pub. L. 111-308, 124 Stat. 3282 (2010), December 14, 2010.
b. 41 U.S.C. § 102 Federal Management Regulation.
c. 42 U.S.C. § 8523 Energy and Water Management Requirements.
d. GSA Acquisition Regulation Part 570, Acquiring Leasehold Interests in Real Property.
e. DOE, Asset Management Plan.
f. DOE O 433.1 (series) Maintenance Management Program for DOE Nuclear Facilities.
g. DOE O 430.1(series), Real Property Asset Management (RPAM).
h. DOE G 580.1-1A Chg 1,) Personal Property.
i. DOE Real Estate Desk Guide, the primary source of information and guidance for planning, acquiring, managing, and disposing of DOE real property or interests therein.
j. DOE, Real Property Efficiency Plan, September 2015.
k. DOE, Federal Energy Management Program, Facility Energy Management Guidelines and Criteria for Energy and Water Evaluations in Covered Facilities, November 28, 2008..
l. Facilities Information Management System (FIMS) User’s Guide, Training Workbook, and Reporting Guide, November 2016.
m. Office of Infrastructure Life cycle Management, Program Management Plan.
n. NNSA Real Property Asset Management Guide.
Section 21
10. DEFINITIONS. See Attachment 2.
11. ACRONYMS. See Attachment 3
12. CONTACT. Infrastructure Planning and Integration Division, Office of Infrastructure, planningandintegration@nnsa.doe.gov.
a. Planning. Based on NNSA-furnished program planning guidance, the contractor must:
(a) Ensure vacating users are not relieved of their responsibility for a space until facility housekeeping, which includes removing supplies, trash, spills, clutter and of any other loose items, and removal of programmatic equipment and personal prop...
(b) Allow the contractor to collect, if needed, a space use charge from vacating users to recover any additional cost associated with the remaining programmatic equipment, materials, and personal property until it has been removed or properly transfer...
(c) Support DOE and NNSA reporting requirements, including FIMS utilization data.
(d) Be available to field office personnel and other Federal oversight personnel for review.
1. DEFINITIONS. National Nuclear Security Administration (NNSA) will rely on the original source documentation for interpretation of all definitions, drawing on and using the definitions in the Department of Energy (DOE) Order 430.1C, herein referre...
a. Area. A portion of a site. This term is applicable at larger sites that have been segmented into areas for facilities planning or other purposes, as opposed to a special area, which is off-site. Example: The Area 23 at the Nevada Nuclear Securi...
b. Area Planning. A methodology used to develop plans that create a framework for modernization and drive prioritized integrated investments by incorporating mission requirements with viable investment options.
c. BUILDER™. A knowledge-based sustainment management system, which includes condition and functionality assessments.
d. Condemnation. A judicial proceeding, initiated by the Government under its right of eminent domain, to take private property for public use.
e. Certified Realty Specialist (CRS). A DOE employee, in the realty specialist series, who is certified in one or more of the three specialty realty areas: acquisition, leasing, and land management and disposal. Employees so certified are authorized...
f. Declaration of Taking. A pleading filed in court with a condemnation proceeding, whereby, with the deposit of just compensation, the interest in the property, as stated in the pleading, is vested at once in the Government.
g. Disposition. The demolition of a real estate asset or the permanent or temporary transfer of NNSA control and custody of real property assets to another who acquires rights to control, use, or relinquish the property.
h. Donation/Gift. The voluntary transfer or conveyance of an interest in real property without payment or consideration of any kind.
i. Enabling Infrastructure. Land, roads, walkways, utilities, and support facilities that are required for the programmatically focused facilities to complete their mission needs.
j. Excess-Facility Risk Index (ERI). NNSA’s risk-based, consequence metric for retired facilities. The quantitative score assigned by ERI is used to aid prioritization of disposition projects, based on the risk posed to worker and public safety or m...
k. Facilities Information Management System (FIMS). The DOE corporate real property asset database for all real property owned, leased, or managed by DOE.
Section 22
l. G2. The NNSA’s Program Management System Generation 2 system that is NNSA’s authoritative data source for integrated infrastructure planning efforts and supports infrastructure programming activities.
m. Integrated Infrastructure Planning (IIP) Team. A cross-functional body of NNSA entities, including NNSA headquarters, laboratories, plants, and sites which looks to address infrastructure planning priorities, facilitate risk-informed decisions, an...
n. Lease. A contractual agreement that gives exclusive possessory interest in the property for a specified time, in exchange for payment of rent to the owner.
o. Lease Rating Scorecard and Criteria. NNSA’s risk-based methodology that measures leased data to evaluate the risk a proposed lease will pose to the Government. The calculated lease rating score informs the decision-making process, including the p...
p. Master Asset Plan (MAP). NNSA’s enterprise-wide infrastructure strategic plan. The MAP covers the infrastructure necessary to meet current, planned, and future mission requirements. It provides an integrated view of NNSA infrastructure and a pri...
q. MAP Deep Dive. An NNSA site visit that provides a forum for discussion and understanding of mission requirements. These discussions are capability focused and drive current and planned infrastructure investments based on condition, capacity gaps,...
s. Mission Dependency Index (MDI). NNSA’s risk-based, consequence to mission metric that assigns a quantitative score to a real property asset. This score informs decision-makers of the potential impact the asset loss would have on NNSA’s mission.
t. Original Source Documentation. The records and reports that support the data collection efforts. This information is usually compiled firsthand, by program subject matter experts in the field.
u. Personal Property. All equipment, material, and supplies not classified as real property (Refer to DOE O 580.1A and to 41 CFR Chapter 102-71). NNSA also considers personal property to be items that are not permanently affixed to the real property...
v. Preliminary Real Estate Plan (PREP). A decision document affecting all future site-selection activity that includes a description of the program or project and an analysis of all viable options and alternatives considered, along with the advantage...
w. Real Estate Acquisition Package (REAP). A decision document affecting all future site-selection leased activity that follows the PREP submission and includes the remaining information needed prior to the lease execution.
x. Real Estate Contracting Officer (RECO). A CRS who has been issued a contracting officer warrant to execute real estate actions, within prescribed limits. An NNSA RECO must be an NNSA employee.
y. Request for Disposition (RFD). The decision document affecting the disposition of an asset, which includes a description of the facility; the annual surveillance, operations, and maintenance costs associated with the facility; a condition and func...
z. Retired Asset. Any asset that has a shutdown status in FIMS.