SD 452.3-1A, Defense Programs Business Process System (DPBPS)
This supplemental directive (SD) establishes the Defense Programs Business Process System (DPBPS) Portal as the mechanism for implementing DOE Order (O) 452.3, Management of the DOE Nuclear Weapons Complex. The Portal delivers business requirements and processes specific to the Deputy Administrator for Defense Programs (DP) for directing, managing, operating, and executing programs at the nuclear weapons production facilities and laboratories within the Nuclear Security Enterprise (NSE).
Detailed implementing content for SD 452.3-1A is available at https://dpbps.sandia.gov/
Associated DOE Directive:
Version history and related documents
Superseded by
A newer version replaces this document.
- SD 452.3-1BDefense Programs Business Process System (DPBPS) (Apr 10, 2025)
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Defense Programs
http://nnsa.energy.gov
printed copies are uncontrolled
SUPPLEMENTAL DIRECTIVE
Approved: 2-25-16
DEFENSE PROGRAMS
BUSINESS PROCESS SYSTEM (DPBPS)
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Defense Programs
NNSA SD 452.3-1A
http://nnsa.energy.gov/
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 452.3-1A 1
2-25-16
DEFENSE PROGRAMS BUSINESS PROCESS SYSTEM
1. PURPOSE. This supplemental directive (SD) establishes the Defense Programs Business
Process System (DPBPS) Portal as the mechanism for implementing DOE Order (O)
452.3, Management of the DOE Nuclear Weapons Complex. The Portal delivers business
requirements and processes specific to the Deputy Administrator for Defense Programs
(DP) for directing, managing, operating, and executing programs at the nuclear weapons
production facilities and laboratories within the Nuclear Security Enterprise (NSE).
2. CANCELLATION. NNSA SD M 452.3-1, Defense Programs Business Requirements
and Processes Manual, dated 12-10-09.
Cancellation of a Supplemental Directive (SD) does not, by itself, modify or otherwise
affect any contractual or regulatory obligation to comply with the directive. Contractor
Requirements Documents (CRDs) previously incorporated into a contract remain in
effect throughout the term of the contract unless and until the contract or regulatory
commitment is modified to either eliminate requirements that are no longer applicable or
substitute a new set of requirements (See SD Background Section 5 and CRD Paragraphs
1a, b, c and 8).
3. APPLICABILITY.
a. Federal. This SD and the DPBPS’ content apply to all federal organizations
responsible for maintaining and enhancing the safety, reliability, and performance
of the United States nuclear weapons stockpile including the ability to design,
produce, and test, in order to meet national security requirements.
Field Office Contracting Officers are responsible for including this policy in the
Managing & Operating (M&O) Contractor contracts for the National Security
Enterprise sites listed in section 3.b. (See Figure 1)
b. Contractors. The Contractor Requirements Document (CRD) provided as
Attachment 1, sets forth requirements of this directive that apply to contracts.
The CRD must be included in contracts of National Security Enterprise M&O
Contractor sites performing work under the Defense Programs, shown in Figure 1.
M&O Site
Name
Kansas
City
National
Security
Campus
Lawrence
Livermore
National
Laboratory
Los Alamos
National
Laboratory
Nevada
National
Security
Site
Pantex
Plant
Sandia
National
Laboratories
Savannah
River Site
Y-12
Plant
M&O Site
Designator
KCNSC LLNL LANL NNSS PX SNL SRS Y12
Figure 1: Participation by National Security Enterprise Site
2 NNSA SD 452.3-1A
2-25-16
c. Equivalencies/Exemptions.
(1) Equivalency. Programs or projects that comply with DOE O 413.3B,
Program and Project Management for Acquisition of Capital Assets meet
the intent of this SD.
(2) Exemption. In accordance with the responsibilities and authorities
assigned by Executive Order 12344, codified under 50 USC sections 2406
and 2511, and to ensure consistency through the joint Navy/DOE Naval
Nuclear Propulsion Program, the Deputy Administrator for Naval
Reactors (Director) will implement and oversee requirements and
practices pertaining to this Directive for activities under the Director's
cognizance, as deemed appropriate.
Section 2
4. SUMMARY OF CHANGES.
The update to DOE O 452.3, Management of the Department of Energy Nuclear
Weapons Complex, as well as changes directed by the Principal Assistant Deputy
Administrator for Military Application (PADAMA) to the content, process, and
requirements necessitated changes to this SD. These include administrative changes to
conform to the document format and content requirements in NNSA SD 251.1.
Content deleted or changed from SD 452.3-1, Defense Programs Business Requirements
and Processes Manual, to this SD are as follows:
• SD changes the term RMI (Requirements Modernization and Integration) to
DPBPS throughout the document, reflecting the RMI Project’s follow-on
program;
• SD Section 2 “Cancellation” information was moved to SD Section 5
“Background,” and SD cancellation information was added;
• SD Section 3 “Applicability” was simplified to conform to NNSA SD 251.1:
o Figure 1 was deleted; and
o Figure 2 became SD Figure 1, and a specific exclusion statement was
written to replace the reference to DOE O 452.3;
• SD Section 4 “Requirements” became SD Section 6 “Requirements”:
o SD bullet “6.a” was expanded to explain the DPBPS requirements levels
in the new SD Figure 2 DPBPS Requirements Levels;
o SD bullet “6.b” was added to clarify process requirements making DPBPS
content contractually binding;
o SD bullet “4.b” became SD bullet “6.c” and contains administrative edits
to align terminology;
o SD bullet “4.c” became SD bullet “6.d”; and
o Sub-bullet “6.d.(3)” was added to mandate a change control process
implementing a graded approach;
• SD Attachment 1, Figure 4, was moved to SD Attachment 2, Figure 2;
• SD Attachment 1, Figure 3, was moved to SD Attachment 2, Figure 3, and
NNSA SD 452.3-1A 3
2-25-16
expanded in scope from a process flow specific only to content development, to
incorporate a full operations and maintenance business cycle for the DPBPS;
• SD Section 5 “Responsibilities” moved to SD Section 7 “Responsibilities”:
o SD bullet “5.b,” became SD bullet “7.b” and was aligned with the 2014
NNSA reorganization, removing management responsibilities from NA-17
and assigning joint responsibility to NA-12 and NA-18;
o SD bullet “7.b” was added to assign NA-12 and NA-18 joint responsibility
for appointing the DPBPS Federal Program Manager (FPM);
o SD bullet “7.e” was added to assign responsibility for requesting the Site
Impact Analysis; and
o SD bullet “5.d” became SD bullet “7.f” and the “M&O” was removed
because requirements for M&O Contractors are required to be listed only
in SD Attachments;
• SD Section 6 “Definitions” was moved to SD Section 9 “Definitions/Acronyms
and updated;
• SD Section 7 “References” was moved to SD Section 8 “References” and
updated;
• SD Section 8 “Contact” information was moved to SD Section “10” and contact
information was updated; and
• SD Attachment 1, the M&O Contractor CRD, became SD Attachment 1:
o SD CRD bullet “2” was expanded into SD CRD items “2” and “3” to
explicitly require adherence to both level 2 and 3 DPBPS content;
o SD CRD item “4” was added to require establishment of an M&O
Contractor working group to manage level 3 content;
o SD CRD items “5” and “6” were added to specifically assign the DPBPS
administrative and technical support function to Sandia National
Laboratories and detail responsibilities;
o SD CRD bullet “3” became SD CRD item “7”;
o SD CRD bullet “7.c” were added to document graded approach for
Section 3
revisions;
o SD CRD bullets “4-6” became SD CRD items “8-10”; and
o SD Attachment 1 figures were moved to SD Attachment 2, which applies
to both federal and M&O Contractor personnel per NNSA SD 251.1
requirements.
5. BACKGROUND.
Requirements issued through the cancelled Supplemental Directive 56XB, Rev 2,
Nuclear Weapon Development and Production, dated March 31, 2004, it’s Development
and Production (D&P) Manual, Appendix 56XB and associated Technical Business
Practices (TBPs), Infrastructure Business Practices (IBP), Engineering Procedures (EP),
and Product Realization Standards (PRS) remain in effect until formally cancelled or
replaced by appropriate DPBPS content.
Notification of content cancellation occurs when the PADAMA issues an NNSA change
notice with an “effective date,” (the date by which all M&O contractors must implement
4 NNSA SD 452.3-1A
2-25-16
the approved DPBPS content at their Nuclear Security Enterprise site). The change
notice identifies which specific content are replaced with DPBPS content defined as
Level 2 Federal Requirements, Level 3 Federal Agreements, or Level 3 M&O Contractor
Agreements (MOCAs). (See Section 9, Definitions, for definitions of Level 2 and Level
3 content.)
The cover page of each DPBPS requirements document includes the “effective date”. A
“Cancellation” section contained in the body of each DPBPS requirements document
specifies complete or partial cancellation of content.
6. REQUIREMENTS.
a. The DPBPS shall be the official web-based repository housing the business
requirements, processes, and tools to perform DP activities within the Enterprise.
Attachment 2, Figure 2, shows the hierarchical levels of requirements related to
the DPBPS’ content. Documents in levels 0 and 1 contain parent requirements
that drive Enterprise-wide implementing content, at levels 2 and 3, in the DPBPS.
M&O Contractors develop Level 4 content to specify and further details needed
for site compliance.
b. Content posted in the DPBPS shall become contractually binding on the effective
date informed through the Site Impact Analysis (T014) process and authorized by
the PADAMA. NNSA publishes the content after PADAMA authorization and
before the effective date, to allow contractors time to bring site-specific processes
into compliance.
c. The DPBPS shall contain:
(1) Level 2 Federal Requirements that direct both the M&O contractor and
federal office activities in support of DP;
(2) Level 3 Federal Agreements (FAs) that specify the federal processes that
support and implement parent requirements; DPBPS Level 2 DOE
Directives (e.g., orders, manuals, standards), NNSA Policies, or applicable
United States Code are parent requirements;
(3) Level 3 Managing & Operating Contractor Agreements (MOCAs) that
specify the detailed and standardized intersite requirements and processes
that support and implement parent requirements; DPBPS Level 2 DOE
Directives (e.g., orders, manuals, standards), NNSA Policies, or applicable
United States Code are parent requirements;
(4) Tools that augment requirements documents by providing examples, rules,
forms, and other clarifying information; and
(5) A glossary containing definitions and acronyms specific to DP work
scope.
NNSA SD 452.3-1A 5
2-25-16
d. Requirements and processes shall be established for writing, reviewing, revising,
authorizing, approving, and managing DPBPS content. Attachment 2, Figure 3
shows the high level cycle of activities intended to ensure that the DPBPS
content:
Section 4
(1) includes the sufficient set of requirements and processes required to
perform defense programs activities;
(2) is aligned, integrated, singularly interpretable, and consistently
implemented;
(3) is revised, as needed, in accordance with a defined set of processes and
requirements using a graded approach; and
(4) does not contradict or supersede provisions contained in any applicable
DOE Orders, NNSA Policies, Federal Regulations, or United States Code.
7. RESPONSIBILITIES.
a. The Principal Assistant Deputy Administrator for Military Application
(PADAMA), or his designee, shall provide direction for the management and
operation of DPBPS and its content.
b. The Assistant Deputy Administrators for the Office of Stockpile Management
(NA-12) and the Office of Systems Engineering and Integration (NA-18) shall:
(1) jointly manage the DPBPS; and
(2) appoint a Federal Program Manager to manage the operations of the
DPBPS.
c. NNSA Field Office Contracting Officers shall:
(1) incorporate SD 452.3-1A into the “List of Applicable Directives”
identified in the Laws, Regulations, and DOE Directives clause of the
M&O contracts for the listed Nuclear Security Enterprise sites (See Figure
1);
(2) request a Site Impact Analysis (T014) upon request from the DPBPS
Federal Program Manager, consistent with DEAR 970.5204-2 (b); and
(3) ensure return of the Site Impact Analysis (T014) result within 30 days
after receipt of the Contracting Officer’s notice for additions or changes to
DPBPS content.
d. Federal personnel shall comply with processes and requirements labeled as
“effective” in the DPBPS, per content applicability statements.
6 NNSA SD 452.3-1A
2-25-16
8. REFERENCES.
a. Title XXXII of P.L. 106-65, National Nuclear Security Administration Act, as
amended, (which establishes a separately organized agency within the Department
of Energy).
b. “An Agreement between the Atomic Energy Commission (AEC) and the
Department of Defense (DoD) for the Development, Production, and
Standardization of Atomic Weapons”, March 21, 1953, (provides the basic
document that establishes the interrelationships between the two agencies to
cooperate in the development, production, and maintenance of nuclear weapons).
c. Supplement to the 1953 Agreement for the Development, Production, and
Standardization of Atomic Weapons between the Department of Energy and the
Department of Defense dated September 5, 1984, (delineates the functions of the
two agencies during joint feasibility studies for nuclear weapons (Phase 2), design
definition and cost studies (Phase 2A), and development engineering (Phase 3)).
d. DP Program Execution Guide, NA-10 Program Management Tools and Processes
dated July 2014 establishes the program management categories and execution
requirements for the categories, defines the activities that are performed by the
Federal Program Managers or their designees to meet those requirements, and
provides a common reference for the execution of program management
practices.
e. Department of Defense and Department of Energy Nuclear Weapons Council
“Procedural Guideline for the Phase 6.X Process” (describes the roles and
functions of the Nuclear Weapons Council (NWC), NWC Standing and Safety
Committee (NWCSSC), the Department of Defense, and the Department of
Energy, National Nuclear Security Administration for the Phase 6.X nuclear
weapon refurbishment activities).
9. DEFINITIONS/ACRONYMS. Definitions are contained in the DPBPS Glossary on the
DPBPS (dpbps.sandia.gov).
Section 5
a. Level 2 Federal Requirement: A federally written and authorized DPBPS
document containing a set of requirements that apply to, and implemented by, the
specified M&O Contractors and NNSA federal staff performing Directed
Stockpile Work.
b. Level 3 Federal Agreement (FA): A federally written and authorized DPBPS
process document containing requirements for or between NNSA federal
organizations performing Directed Stockpile Work.
c. Level 3 M&O Contractor Agreement (MOCA): An M&O Contractor-written and
federally authorized process, containing requirements that specify standardized
agreements among the M&O Contractor sites. The MOCAs pertain to the
NNSA SD 452.3-IA
2-25-16
implementation of federal requirements defined in DPBPS Level 2 Federal
Requirements or higher-level parent requirements and apply to all M&O
Contractors performing DP Work.
d. Tool: A subset ofDPBPS Level 2 and Level 3 content containing guides,
templates, work instrnctions, and other aids. The referencing content specifies
whether use of the tool is required or recommended.
e. Contractor: Applies to each of the NSE M&O Contractor Organizations.
10. CONTACT. DPBPS FPM, Office of Stockpile Management at 505-845-4823.
BY ORDER OF THE ADMINISTRATOR:
Attachments:
1. Contractor Requirement Document
7~J2h.~
Frank G. Klotz . G
Administrator
2. DPBPS Structure and Process for Operations and Maintenance
7
THIS PAGE INTENTIONALLY LEFT BLANK
NNSA SD 452.3-1A Attachment 1
2-25-16 AT1-1
ATTACHMENT 1: CONTRACTOR REQUIREMENT DOCUMENT (CRD)
NNSA SD 452.3-1A, DEFENSE PROGRAMS BUSINESS PROCESS SYSTEM
The contractor is responsible for complying with the requirements of this CRD. The contractor
is responsible for flowing down the requirements of this CRD to subcontractors at any tier to the
extent necessary to ensure the contractor’s compliance with the requirements.
This Management and Operating (M&O) Contractor Requirements Document establishes the
requirements for National Nuclear Security Administration (NNSA) M&O Contractors within
the Nuclear Security Enterprise (NSE) for the management of NNSA sites or facilities that are
involved in, interact with the management of the nuclear weapons stockpile, or develop or
produce weapon product or weapon-related product:
1. The contractor shall use the business requirements, processes, and tools established in the
Defense Programs Business Process System (DPBPS) (dpbps.sandia.gov) to implement
National Nuclear Security Administration Act expectations for Defense Programs work.
a. Requirements issued through cancelled Supplemental Directive 56XB, Rev 2,
Nuclear Weapon Development and Production, dated March 31, 2004; its
Development and Production (D&P) Manual, Appendix 56XB; and associated
Technical Business Practices (TBPs); Infrastructure Business Practices (IBP);
Engineering Procedures (EP); Product Realization Standards (PRS) remain in
effect until formally cancelled or replaced by appropriate DPBPS content.
b. Notification of cancellation of content occurs when the Principal Assistant Deputy
Administrator for Military Application (PADAMA) issues an NNSA change
notice with an “effective date”. The change notice identifies which specific
content is replaced with DPBPS content defined as Level 2 Federal Requirements,
Level 3 Federal Agreements, or Level 3 M&O Contractor Agreements (MOCAs).
(See SD Section 9, Definitions, for definitions of Level 2 and Level 3 content.)
Section 6
c. NNSA change notices specify the “effective date” (the date by which all M&O
contractors must implement the approved DPBPS content at their Nuclear
Security Enterprise site). The cover page of each DPBPS requirements document
includes the “release” and “effective” dates. A “Cancellation” section contained
in the body of the DPBPS requirements specifies complete or partial cancellation
of legacy content.
2. The contractor shall implement the effective DPBPS Level 2 business requirements that
apply to their site per content applicability statements.
3. The contractor shall implement the effective DPBPS Level 3 MOCAs that apply to their
site per content applicability statements. M&Os may choose to create Level 4 site-
specific content to specify any further details needed for site compliance.
4. An M&O Contractor working group shall manage creation, modification, and
cancellation of MOCA content.
Attachment 1 NNSA SD 452.3-1A
AT1-2 2-25-16
5. The M&O Contractor selected by NNSA shall appoint an administrative and technical
office to support the DPBPS Federal Program Manager (FPM), implement effective
DPBPS processes and requirements to manage, operate, and maintain the DPBPS and its
contents, and chair a single DPBPS M&O Contractor working group.
6. All M&O contractors shall comply with effective DPBPS requirements to ensure that
Level 3 MOCAs and associated tools:
a. include the sufficient set of requirements and processes required to perform
defense programs activities;
b. are aligned, integrated, clearly understood, and consistently implemented;
c. are revised, as needed, in accordance with a defined set of processes and
requirements using a graded approach; and
d. do not contradict or supersede provisions contained in any applicable DOE Orders
or NNSA Policies.
7. The contractor shall perform the activities associated with the content development and
review processes, and, consistent with DEAR 970.5204-2 (b), perform Site Impact
Analysis (T014) within 30 days after receipt of the Contracting Officer’s notice as a
result of an addition or change to DPBPS content.
8. Changes or additions to Level 2 Requirements and Level 3 MOCAs in the DPBPS shall
not necessitate a revision to the “List of Applicable Directives” pursuant to DEAR
970.5204-2 Laws, Regulations, and DOE Directives (DEC 2000) clause of each M&O
contract. Content posted in the DPBPS becomes contractually binding on the effective
date informed through the Site Impact Analysis (T014) process performed by the
Contracting Officer. NNSA publishes the content after PADAMA authorization and
before the effective date, to allow contractors time to bring site-specific processes into
compliance.
9. Notification of PADAMA-approved (released) Level 2 or Level 3 added or changed
content shall be provided via DPBPS to federal and contractor organizations, as
previously identified in SD Section 3.
NNSA SD 452.3-1A Attachment 2
2-25-16 AT2-1
ATTACHMENT 2: DPBPS STRUCTURE AND PROCESS FOR OPERATIONS AND
MAINTENANCE
NOTE: All attachments, except Attachment 1 (which applies to contractors only), apply to
both Federal and contractor employees.
Figure 2: DPBPS Requirements Levels
Figure 3: DPBPS Management Cycle
Section 7
1. purpose. This supplemental directive (SD) establishes the Defense Programs Business Process System (DPBPS) Portal as the mechanism for implementing DOE Order (O) 452.3, Management of the DOE Nuclear Weapons Complex. The Portal delivers business r...
3. APPLICABILITY.
a. Federal. This SD and the DPBPS’ content apply to all federal organizations responsible for maintaining and enhancing the safety, reliability, and performance of the United States nuclear weapons stockpile including the ability to design, produce, ...
b. Contractors. The Contractor Requirements Document (CRD) provided as Attachment 1, sets forth requirements of this directive that apply to contracts.
c. Equivalencies/Exemptions.
4. SUMMARY OF CHANGES.
5. Background.
6. REQUIREMENTS.
(1) Level 2 Federal Requirements that direct both the M&O contractor and federal office activities in support of DP;
(2) Level 3 Federal Agreements (FAs) that specify the federal processes that support and implement parent requirements; DPBPS Level 2 DOE Directives (e.g., orders, manuals, standards), NNSA Policies, or applicable United States Code are parent requir...
(3) Level 3 Managing & Operating Contractor Agreements (MOCAs) that specify the detailed and standardized intersite requirements and processes that support and implement parent requirements; DPBPS Level 2 DOE Directives (e.g., orders, manuals, standa...
(4) Tools that augment requirements documents by providing examples, rules, forms, and other clarifying information; and
(5) A glossary containing definitions and acronyms specific to DP work scope.
(1) includes the sufficient set of requirements and processes required to perform defense programs activities;
(2) is aligned, integrated, singularly interpretable, and consistently implemented;
(3) is revised, as needed, in accordance with a defined set of processes and requirements using a graded approach; and
(4) does not contradict or supersede provisions contained in any applicable DOE Orders, NNSA Policies, Federal Regulations, or United States Code.
7. RESPONSIBILITIES.
(1) jointly manage the DPBPS; and
(2) appoint a Federal Program Manager to manage the operations of the DPBPS.
(1) incorporate SD 452.3-1A into the “List of Applicable Directives” identified in the Laws, Regulations, and DOE Directives clause of the M&O contracts for the listed Nuclear Security Enterprise sites (See Figure 1);
(2) request a Site Impact Analysis (T014) upon request from the DPBPS Federal Program Manager, consistent with DEAR 970.5204-2 (b); and
(3) ensure return of the Site Impact Analysis (T014) result within 30 days after receipt of the Contracting Officer’s notice for additions or changes to DPBPS content.
8. References.
9. Definitions/acronyms. Definitions are contained in the DPBPS Glossary on the DPBPS (dpbps.sandia.gov).
10. Contact. DPBPS FPM, Office of Stockpile Management at 505-845-4823.