BOP-06.04, Project Reviews
This National Nuclear Security Administration (NNSA) Business Operating Procedure (BOP) describes the process for conducting Project Reviews on projects executed by the NNSA. The principal customers of the reviews are the Administrator, the Principal Deputy Administrator, the Deputy and Associate Administrators, Federal Project Directors, Project Managers, and the individual project Acquisition Executives. The reviews advise Managers on the status of projects and assist management in their project decisions.
Cancels BOP 50.003, Establishment of a National Nuclear Security Administration (NNSA) Independent Project Review (IPR) Policy, dated 6-6-07.
Cancels:
Renumbered From:
BOP 413.4, Project Reviews on Sep 27, 2019
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ONLINE AT: Office of Project Analysis, Oversight, and Review
https://portal.na.gov/NA-MB/na-mb-20/Pages/NNSA-Policy.aspx
printed copies are uncontrolled
BUSINESS OPERATING PROCEDURE
Approved: 11-18-14
PROJECT REVIEWS
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Acquisition and Project Management
BOP-06.04
https://portal.na.gov/NA-MB/na-mb-20/Pages/NNSA-Policy.aspx
THIS PAGE INTENTIONALLY LEFT BLANK
BOP-06.04 1
11-18-14
PROJECT REVIEWS
1. PURPOSE. This National Nuclear Security Administration (NNSA) Business Operating
Procedure (BOP) describes the process for conducting Project Reviews on projects
executed by the NNSA. The principal customers of the reviews are the Administrator,
the Principal Deputy Administrator, the Deputy and Associate Administrators, Federal
Project Directors, Project Managers, and the individual project Acquisition Executives.
The reviews advise Managers on the status of projects and assist management in their
project decisions.
2. CANCELLATION. BOP-50.003, Establishment of a National Nuclear Security
Administration (NNSA) Independent Project Review (IPR) Policy, dated June 6, 2007 was
cancelled on January 14, 2013.
3. APPLICABILITY.
a. NNSA Applicability. This policy applies to all projects (except General Plant
Projects and third party financed projects) constructed for NNSA with an
estimated Total Project Cost (TPC) > $10 million. These projects include Line
Item (Capital) projects and Major Items of Equipment (MIE) projects.
b. Contractors. Does not apply to contractors.
c. Exclusion. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 U.S.C. sections 2406 and 2511 and to
ensure consistency through the joint Navy/DOE Naval Nuclear Propulsion
Program, the Deputy Administrator for Naval Reactors (Director) will implement
and oversee requirements and practices pertaining to this Directive for activities
under the Director’s cognizance, as deemed appropriate.
4. BACKGROUND.
a. Independent Project Reviews (IPRs) provide a method of evaluating the cost,
scope, schedule, and technical attributes of a project, often authorized prior to the
various Critical Decision (CD) milestones during project execution.
b. Technical Independent Project Reviews (TIPRs) are conducted on high risk, high
hazard and Hazard Category 1, 2, or 3 nuclear projects following the completion
of preliminary design. TIPRs are reviews of Nuclear Safety to determine if the
safety documentation is sufficiently conservative and bounding to be relied upon
for the next phase of the project, final design. TIPRs ensure the requirements of
DOE-Standard (STD)-1189-2008 are being appropriately incorporated into
project design deliverables and development of project safety documentation is
compliant with the standard.
c. Peer Reviews (PR) are conducted at least annually on all NNSA projects after
achieving CD-1 to provide expert corroboration/evaluation on a project’s scope,
2 BOP-06.04
11-18-14
cost, schedule, and technical progression. An annual Peer Review will normally
not be conducted in the year an IPR is conducted due to the effort being
duplicative and a distraction from work progress. For the same reason, an annual
Peer Review may be eliminated in the year prior to CD-4 approval. Other
circumstances (project placed on-hold, project approach being revisited, good
project cost and schedule performance, etc, ) may arise that would make an
annual review un-necessary. The requirement for a review will be coordinated
among stakehoders with the final decision residing with APM.
Section 2
d. The Acquisition Executive (AE) uses these reviews, IPRs, TIPRs, or PRs, to
determine the readiness level of a project prior to proceeding into subsequent
phases or, in the case of a Peer Review, the overall status of the project. The
National Research Council has recognized the value of NNSA conducting
internal, non-advocate reviews as a means of improving overall project
performance.
5. INTEGRATION OF PROJECT REVIEWS AND PROJECT LIFECYCLE.
Typical:
6. REQUIREMENTS.
a. This policy will be applied in conjunction with the requirements established by
DOE Order (O) 413.3B. Execution of project activities, including
responsibilities, will follow the requirements of DOE O 413.3B unless otherwise
noted herein.
b. All applicable review teams will be appointed and led by personnel from NNSA
Office of Acquisition and Project Management (NA-APM) or the designated
review owner (DOE O 413.3B). These reviews will be conducted to provide
emphasis on technical approach (including nuclear safety for Hazard Category 1,
2, and 3 nuclear facilities), cost and schedule risks; management and acquisition;
BOP-06.04 3
11-18-14
safety culture; environmental safety and health, quality assurance, and
commissioning.
The information below highlights some of the requirements in DOE O 413.3B that
impact NNSA projects and adds additional requirements for NNSA Projects.
c. Prior to CD-0
(1) Mission Validation Independent Review
Criteria: > $750M (Major System Project (MSP))
Responsible Party: Deputy or Associate Administrators
This review is a limited review for MSP’s. The purpose is to validate the
mission need, review the rough order of magnitude (ROM) cost range and
to designate the appropriate AE. A value study may be conducted, as
appropriate, to assist in establishing CD-0.
(2) Independent Cost Review (ICR)
Criteria: > $750M (MSP)
Responsible Party: DOE APM
For MSP’s or projects designated by the Secretarial Acquisition Executive
(SAE), Department of Energy Office of Acquisition and Project
Management (DOE APM) will conduct an ICR. This review validates the
basis of the ROM cost range; provides an assessment of whether the ROM
reasonably bounds the alternatives to be analyzed in the next project
phase; and assists in determining the AE authority designation.
d. Prior to CD-1
(1) Acquisition Strategy (AS) Review
Criteria: TPC >$750M
Responsible Party: DOE-APM
Acquisition Strategies (AS) for MSP’s must be sent to the Energy
Systems Acquisition Advisory Board (ESAAB) Secretariat for
review by DOE-APM prior to scheduling CD-1 decisional
briefings. The Federal Project Director (FPD) and CO must concur
with the AS prior to the DOE-APM review. Within 10 days upon
receipt, DOE-APM will provide a recommendation to the
appropriate PSO who holds approval authority. Approval of the AS
does not constitute approval of the Acquisition Plan (AP). The AP
4 BOP-06.04
11-18-14
must be submitted for review and approval in accordance with
established procurement procedures including DOE Acquisition
Guide, Chapter 7.1.
(2) Acquisition Strategy (AS) Review (Additional requirements for NNSA
Projects)
Criteria: $10M < TPC < $750M
Responsible Party: NA-APM
Section 3
Approval: Acquisition Strategies for Projects within this range
must be sent to NA-APM-1 prior to scheduling CD-1 decisional
briefings. The Federal Project Director (FPD) and CO must
concur with the AS prior to the NA-APM review. Within 10 days
upon receipt, NA-APM will provide a recommendation to the
appropriate Deputy or Associate Administrators who holds
approval authority. Approval of the AS does not constitute
approval of the Acquisition Plan (AP). The AP must be submitted
for review and approval in accordance with established
procurement procedures including DOE Acquisition Guide,
Chapter 7.1.
(3) Independent Project Reviews (High Hazard & Nuclear Facilities)
Criteria: Hazard Category 1, 2, 3, and Nuclear Facilities including
modifications to Nuclear Facilities. Excludes building equipment
and systems that are not line item and are under $50M.
Responsible Party: NA-APM
Note: Chief of Defense Nuclear Safety (CDNS) concurrence on
charge memorandum and review plans is required for reviews of
projects that must implement DOE-STD-1189-2008.
For Hazard Category 1, 2, and 3 nuclear facilities, the NA-APM
will conduct an IPR to ensure early integration of safety into the
design process. The review must: 1) ensure that safety
documentation is complete, accurate, and reliable for entry into the
next phase of the project; 2) evaluate whether the preferred
alternative process and facility design, and corresponding safety
analyses, are sufficiently detailed to identify any safety controls
that, because of cost, maintainability, complexity or other limiting
characteristics, could significantly impact the decision to select the
preferred alternative; and 3) validate that the Integrated Project
Team (IPT) charter has identified appropriate functions, roles and
responsibilities for members needed to support nuclear safety, and
BOP-06.04 5
11-18-14
that the IPT members supporting nuclear safety are appropriately
qualified, and have the availability to meet their responsibilities.
The Deputy or Associate Administrators approval of IPRs means
that the Program Office and FPD jointly request the review and
establish the review scope and schedule.
(4) Independent Cost Estimate (ICE) and/or Independent Cost Reviews (ICR)
Criteria: TPC >$100M
Responsible Party: DOE-APM
For projects with a TPC greater than or equal to $100M, DOE-
APM will develop an ICE and/or conduct an ICR, as they deem
appropriate. This review validates the basis of the preliminary cost
range for reasonableness and executability. It also includes a full
accounting of life cycle costs to support the alternative selection
process and budgetary decisions.
(5) Independent Cost Estimate (ICE) and/or Independent Costs Reviews
(ICR) (Additional requirements for NNSA Projects)
Criteria: $10M < TPC < $100M
Responsible Party: NA-APM
For capital projects managed with a TPC less than $100M but
greater than $10M, NA-APM will conduct an ICE or an ICR. This
review validates the basis of the preliminary cost range for
reasonableness and executability. It also includes a full accounting
of life cycle costs to support the alternative selection process and
budgetary decisions.
For Federal direct contracts, NNSA will develop a cost estimate, in
accordance with the BOP-06.03, Independent Cost Estimates
Procedures, which will be reviewed by NA-APM prior to approval
of CD-1.
e. Prior to CD-2
Section 4
(1) Technical Independent Project Reviews (High Hazard & Nuclear
Facilities)
Criteria: Hazard Category 1, 2, 3, and Nuclear Facilities including
modification to Nuclear Facilities. Excludes building equipment
and systems that are not line item and are under $50M.
Responsible Party: NA-APM
6 BOP-06.04
11-18-14
Note: CNS or CDNS concurrence on charge memorandum and
review plans, as appropriate, is required for reviews of projects that
must implement DOE-STD-1189-2008.
For Hazard Category 1, 2, and 3 nuclear facilities, the Deputy or
Associate Administrators will conduct a TIPR, at the completion of
preliminary design, to ensure early integration of safety into the
design process. The TIPR must: 1) ensure that safety
documentation is complete, accurate and reliable for entry into the
next phase of the project; 2) evaluate the IPT to ensure that
appropriate team member functions to support nuclear safety
during final design have been established, and appropriately
qualified team members have been selected and have needed
availability to address nuclear safety-related matters during final
design. Completion or closure of the TIPR recommendations, i.e.
the CAP, is not required prior to CD-2 approval. The Deputy or
Associate Administrators approval of a TIPR means that the
Program Office and FPD jointly request the review and establish
the review scope and schedule.
(2) Performance Baseline Validation Review (CD-2)
Criteria: TPC >$100M
Responsible Party: DOE-APM, External Independent Review
(EIR)
A Performance Baseline Validation Review is required to provide
reasonable assurance that the project can be successfully executed.
For all projects with a TPC greater than or equal to $100M, DOE-
APM will conduct an EIR and develop an ICE in support of the PB
validation. Findings resulting from project reviews must be
addressed by the IPT in their corrective action plan and
expeditiously resolved. Follow-up reviews to validate finding
resolution may be required at the discretion of the reviewing entity.
The estimate shall be at least an Association for the Advancement of
Cost Engineering (AACE) International Inc., Class II estimate.
(3) Independent Project Review (CD-2) (Additional requirements for NNSA
Projects)
Criteria: $10M < TPC <$100M
Responsible Party: NA-APM, Independent Project Review
An Independent Project Review (IPR) is required to provide
reasonable assurance that the project can be successfully executed.
BOP-06.04 7
11-18-14
IPRs are required to validate the Performance Baseline (PB) for
projects with a TPC greater than $10M but less than $100M.
(4) Project Definition Rating Index (PDRI) Analysis
Criteria: TPC > $100M
Responsible Party: FPD/IPT
For projects with a TPC greater than $100M, the FPD shall
conduct a PDRI Analysis. Such analyses are also encouraged for
projects with a TPC less than $100M.
(5) Technology Readiness Assessment.
Criteria: TPC >$10M
Responsible Party: FPD/IPT (IPR will review)
For all Projects where new critical technologies are being
deployed, the IPT shall complete a Technology Readiness
Assessment (TRA) and Technology Maturation Plan, as
appropriate.
(6) Final Design Review
Criteria: All Projects
Responsible Party: FPD/IPT
Section 5
Final Design Review must be conducted for all projects and
involve external reviewers using a formalized, structured approach
to ensure that the reviews are comprehensive, objective and
documented. The purpose of the review is to validate the project
has completed 90% design (full plans and specs without final
signatures), has incorporate safety in design (if required), and the
design is adequate to proceed into final design. For nuclear
projects, including modifications to nuclear projects, this design
review should include confirmation that an appropriate As Low as
Reasonably Achievable (ALARA) Review has been completed as
required by 10 CFR 835 and DOE Order 458.1.
f. Prior to CD-3
(1) Construction or External Independent Review (EIR)/Execution Readiness
Review (ERR)
Criteria: TPC >$750M
8 BOP-06.04
11-18-14
Responsible Party: DOE-APM
An EIR must be performed by DOE-APM on Major System
Projects to verify construction or execution readiness.
(2) Independent Project Review (IPR) (Additional requirements for NNSA
Projects)
Criteria: $10M < TPC < $750M
Responsible Party: NA-APM
An IPR is required for non-Major System Projects to verify
construction or execution readiness, unless waived by NA-APM.
(3) Independent Cost Estimate (ICE)
Criteria: TPC >$100M
Responsible Party: DOE-APM
For projects with a TPC greater than or equal to $100M, DOE-
APM will develop an ICE, if warranted by risk and performance
indicators or as designated by the AE.
(4) Independent Cost Review (ICR) (Additional requirements for NNSA
Projects)
Criteria: $10M < TPC < $100M
Responsible Party: NA-APM
For projects managed by an M&O contractor with a TPC greater
than $10M and less than $100M NA-APM will conduct an
Independent Cost Review (ICR).
For Federal direct contracts, NNSA will develop an independent
cost estimate, in accordance with the FAR, which will be reviewed
by NA-APM prior to approval of CD-3.
(5) Technology Readiness Assessment.
Criteria: TPC > $750M
Responsible Party: FPD/IPT
BOP-06.04 9
11-18-14
For Major System Projects where a significant critical technology
element modification occurs subsequent to CD-2, conduct a TRA,
as appropriate.
(6) Final Design Review for projects not already at 90% design prior to CD-2
Criteria: All Projects
Responsible Party: FPD/IPT
A Final Design Review must be conducted for all projects and
involve external reviewers using a formalized, structured approach
to ensure that the reviews are comprehensive, objective, and
documented.
g. Prior to CD-4
(1) Operational Readiness Review (ORR)
Criteria: High Hazard & Nuclear Facilities, including
modifications to Nuclear Facilities. Radiological Facilities may
also require an ORR. The requirement for an ORR will be
determined on a case by case basis.
Responsible Party: NNSA Line Management as defined by DOE
Order 425.1D
Conduct an ORR for Hazard Category 1, 2, and 3 nuclear facilities,
including modifications to nuclear facilities, in accordance with
DOE O 425.1D and DOE-STD-3006-2010. Per DOE O 425.1D,
tailoring of the effort is possible
(2) Readiness Assessment (RA)
Criteria: Low Hazard & Non-Nuclear. Radiological Facilities
may also require an RA. The requirement for an RA will be
determined on a case by case basis.
Responsible Party: NNSA Line Management
Section 6
For non-nuclear projects, conduct a formal assessment of the
project's readiness to operate, as appropriate. Determine the basis
for DOE acceptance of the asset and if the facility or area can be
occupied from both a regulatory and work function standpoint.
Establish a beneficial occupancy/utilization date for the facility
and/or equipment. Per DOE O 425.1D, tailoring of the effort is
possible, and for Low Hazard & Non-Nuclear Facilities, an RA is
optional but not required.
10 BOP-06.04
11-18-14
h. Project Peer Reviews (PR)
(1) These focused, in-depth reviews are conducted by non-advocates (Federal
and M&O or other contractor experts) and support the design and
development of a project. For projects greater than $10M, NA-APM
should conduct a Project Peer Review at least once a year, starting at CD-1
and continuing through CD-4, for large or high-visibility projects and
more frequently for the most complex projects or those experiencing
performance challenges. The reviews should be performed by peers (with
relevant experience and expertise) independent of the project, to evaluate
technical, managerial, cost, scope, and other aspects of the project, as
appropriate. These Project Peer Reviews may supplement or replace
applicable IPRs at the discretion of the AE and vice versa.
(2) PRs will be tailored reviews to address project execution and/or specific
project issues or concerns identified during Quarterly Project Reviews,
external reviews (e.g. IG, GAO, DNFSB, etc.), or by the Deputy or
Associate Administrators or the Acquisition Executive. The tailoring will
be accomplished in consultation with the Federal Project Director, the
Acquisition Executive, the Chief of Defense Nuclear Safety (for Hazard
Category 1, 2, and 3, nuclear facilities, and modifications to nuclear
facilities only), and the associated HQ Program Office to meet the specific
needs of the Administrator, Principal Deputy Administrator, and Deputy
and Associate Administrators. Tailoring will be documented in the review
Charge Memorandum issued by the AE.
(3) For Cause Peer Reviews are initiated due to a significant decline in a
project’s performance, as depicted on the “Monthly Project Status Report
for the Deputy Secretary,” or from other sources. PRs can be initiated by
the Acquisition Executive or NA-APM, for projects that are post CD-2, if
sufficient cause warrants a review. These reviews will generally be
conducted if the project has not corrected performance issues as reported
(i.e. project performance changes from green to yellow or yellow to red).
For Cause Reviews may also be initiated due to significant technical
issues or obstacles that jeopardize project performance and warrant an
independent evaluation and the involvement of the Acquisition Executive
in the resolution of the issue.
(4) Circumstances (project placed on-hold, project approach being revisited,
good project cost and schedule performance, etc,) may arise that would
make an annual review un-necessary. The requirement for a review will
be coordinated among stakehoders with the final decision residing with
NA-APM.
i. Any of the above reviews may be combined where it is in the best interest of the
project and does not specifically conflict with guidance outside this BOP. The
BOP-06.04 11
11-18-14
decision to combine reviews will be reviewed by all stakeholders with NA-APM
making the final decision.
7. REVIEW PROCESS
Section 7
a. The Office of Acquisition and Project Management (NA-APM) leads, manages,
and performs all IPRs, T-IPRs, and PRs within the NNSA. While NA-APM will
lead the reviews, Program Office, Field Office, and appropriate technical
expertise, including the Contracting Officer, are expected to participate in all
reviews, consistent with their individual areas of expertise and the needs of the
review team. To obtain experienced personnel for the Peer Reviews, NA-APM
will attempt to obtain Subject Matter Experts (SME) from incumbent M&O
contractors and other offices within NNSA and DOE as necessary. This will
ensure fair and balanced assessments and have the additional benefit of cross-
pollination, sharing best practices in project management complex-wide. Federal
personnel from NNSA sites that are managing projects of a similar size or
technical complexity may be requested to participate on the reviews. Such
participation will be done in consultation with their management.
b. IPRs are performed at the request of the Program Office, the FPD, NA-APM, or
Deputy or Associate Administrators. IPRs are also required prior to CD-1, 2, and
3 ESAABs. NA-APM will lead a Corrective Action Plan (CAP) Closure Review
for all recommendations identified at previous IPRs, TIPRs, and PRs. The CAP
Closure Review can be addressed at a Peer Review or IPR. This CAP Closure
Review must be addressed prior to a project moving into the next project phase
(e.g. preliminary design to final design) or approval of a Critical Decision. NA-
APM, the Review Committee Lead, and the Federal Project Director approve the
CAP and CAP Closure Review. The Associate Administrator for Acquisition and
Project Management (NA-APM-1) resolves disagreements.
c. Review scope varies with the type of review being conducted. IPR scope, unless
tailored, will include as a minimum, technical approach, project management
systems, acquisition, cost, schedule, and risk, "safety in design" review (if
applicable and in consultation with CDNS for nuclear facilities, and modifications
to nuclear facilities), safety culture, environmental, occupational safety and
health, quality assurance, start-up/commissioning and any specific review areas
requested by the Project and/or Program Office. For nuclear projects, TIPRs will
include a comprehensive technical review of nuclear safety and security
particularly related to project design. Peer Review scope can be similar to an IPR
or may be proposed and negotiated with the Program Office and FPD. The
review process will be conducted in a non-adversarial manner with the objective
of increasing the project’s likelihood of success.
d. The reviews will be conducted in an open format. Program offices will be invited
to attend all review team sessions. For nuclear projects, which have Defense
Nuclear Facilities Safety Board (DNFSB) oversight, the DNFSB staff will be
invited to observe the review.
12 BOP-06.04
11-18-14
e. The Integrated Project Team (IPT) will prepare a Project Definition Rating Index
(PDRI) for each review of a project with TPC greater than $10 million, as
requested by the Acquisition Executive. The PDRI is a management tool for the
IPT and is not required to be used by either the IPR or TIPR. All IPRs, PRs, and
TIPRs will review Technology Readiness Assessments conducted by projects as
required by DOE Order 413.3B and other applicable NNSA Policy.
f. All IPR/TIPR/PR Reports will be approved/signed by the Review Committee
Leader.
Section 8
g. At the conclusion of each review, an outbrief will be conducted, if practical, with
the Federal Project Director regarding the review results. Project site officials and
program managers are encouraged to attend the outbrief. CDNS (or appropriate
CDNS representative) should attend the outbrief for nuclear projects.
h. The Review Committee Leader is responsible for conducting post-review
briefings to the Administrator, Principal Deputy Administrator, and the Deputy
and Associated Administrators, the AE, CDNS (for nuclear projects), and the
Program Office or their designee regarding the review results.
i. The funding for TIPRs, IPRs, and Peer Reviews, on large (>$750M), complex
projects will be the responsibility of the Program Office. All other smaller project
reviews will be funded by the Project. Funding needs/amounts for each review
will be identified, working with the Program Office, after receipt of a Charge
Memorandum. Funding issues will be resolved with the Project/Program Office
by the 10th of the month prior to conducting the review. Required funding is to be
used for SME contractor participation, travel, and support and will be provided by
the project at the beginning of the Fiscal Year. This funding will support both
contractor and federal participation.
j. A Charge Memorandum is the initiating documentation and the official request by
the Deputy or Associate Administrators, the Acquisition Executive or the FPD to
conduct an IPR/TIPR/PR. This Charge memorandum will outline areas and
issues that are to be addressed in the review. NA-APM negotiates the dates on
which the review is to be conducted with the FPD. Review documentation will be
available to the Review Committee a minimum of four (4) weeks prior to the
onsite review. If documentation is not available four weeks ahead of the onsite
review, the review may be postponed. For nuclear facilities, CDNS will be
consulted, and will concur on the nuclear safety scope and breadth of reviews
through formal concurrence on the Charge Memorandum, Review Plans, and
associated Criteria and Review Approach Documents (CRADs). Project reviews
previously conducted by the Program/Project office, as well as external reviews
(IG, GAO, DOE-APM, DNFSB, etc.) will be considered in scoping/tailoring the
IPR/TIPR/PR. For nuclear projects, previous formal CDNS Advice regarding
approval of the Safety Design Strategy will also be considered in the scoping of
these reviews.
BOP-06.04 13
11-18-14
8. RESPONSIBILITIES.
a. Acquisition Executive (AE). The approving authority for a project’s Critical
Decisions per DOE O 413.3B. The AE may request a project review.
b. Chief of Defense Nuclear Safety (CDNS). For nuclear facilities, CDNS
concurrence is required for the Charge Memorandum, Review Plans, and
associated Criteria and Review Approach Documents (CRADs). CDNS must
ensure the qualifications of IPT members, review committee members, and
effective implementation of DOE-STD-1189-2008 as applicable.
c. Federal Project Director (FPD). Individual certified under the Department’s
Project Management Career Development Program as responsible and
accountable to NA-APM for project execution.
d. Office of Project Analysis Oversight and Review (NA-APM 1.1). The NNSA
staff responsible for leading, managing, and performing all Peer Reviews,
Independent Project Reviews, Technical Independent Project Reviews, and CAP
Closure Reviews within the NNSA. NA-APM may select a Review Team Leader
external to the NA-APM organization.
Section 9
e. Deputy or Associate Administrators /Federal Program Manager. An
office/individual in the headquarters organizational element responsible for
managing a program. They may request a review.
f. Heads of Field Elements and Headquarters NNSA Elements.
(1) Review procurement requests for new non-M&O contracts and other site
and facility management contracts that involve classified matter or nuclear
materials and contain DEAR clause 952.204-2, Security Requirements,
and ensure that the requirements are included in those contracts.
(2) NNSA elements must notify contracting officers of affected M&O
contracts and other site and facility management contracts to incorporate a
CRD into those contracts.
g. Contracting Officers.
(1) Once notified, are responsible for incorporating a CRD into the affected
contracts via the laws, regulations, and DOE directives clause of the
contracts.
(2) Assist originators of procurement requests to incorporate the requirements
in new non-M&O contracts and other site and facility management
contracts, as appropriate.
14 BOP-06.04
11-18-14
8. REFERENCES.
a. DOE Order 413.3B, Program and Project Management for the Acquisition of
Capital Asset, dated 11-29-10.
b. DOE G 413.3-9, Project Review Guide for Capital Asset Projects, dated 9-23-08.
c. DOE G 413.3-12, Project Definition Rating Index Guide for Traditional Nuclear
and Non-Nuclear Construction Projects, dated 7-22-10
d. DOE O 425.1D, Admin Change 1, Verification of Readiness to Start Up or
Restart Nuclear Facilities, dated 4-2-13
e. DOE-STD-1189-2008, Integration of Safety into the Design Process.
f. DOE-STD-3006-2010, Planning and Conducting Readiness Reviews
g. NNSA Annual Peer Review, Independent Project Review and Technical
Independent Project Review Handbook, January 2011.
h. DOE Order 430.1B, Real Property and Asset Management
9. DEFINITIONS.
a. Annual Peer Reviews – An Annual Peer Review will be conducted for each
project with a TPC greater than $10M that has achieved CD-1. Other
circumstances (project placed on-hold, project approach being revisited, good
project cost and schedule performance, etc, ) may arise that would make an
annual review un-necessary. The requirement for a review will be coordinated
among stakehoders with the final decision residing with APM.
b. CAP Closure Process – A CAP Closure Review will be conducted for each
project with a TPC greater than $10M that has had a previous IPR/TIPR with
Recommendations. A CAP Closure Review will be conducted for all high risk,
high hazard, and Hazard Category 1, 2, and 3 nuclear facilities to ensure closure
of previously identified Recommendations. CAP Closure will be led by the NA-
APM incorporated into an IPR, PR, or TIPR.
c. Charge Memorandum – A memorandum written and signed by NA-APM
directing a Project Review and charging the Review Committee. The
memorandum states the purpose for the review, suggested tailoring, and areas of
particular concern or needing special attention. A copy is included as an
attachment to the IPR report.
d. Critical Decisions (CD) – a formal determination made by the Secretarial
Acquisition Executive/Acquisition Executive at a specific point in a project’s life
cycle that allows the project to proceed to the next phase.
BOP-06.04 15
11-18-14
Section 10
e. Design Maturity – Advancing design maturity to a sufficient level prior to
establishing the performance baseline is essential to project management success.
The project design will be considered sufficiently mature when the Program has
developed a cost estimate and all relevant organizations have a high degree of
confidence that it will endure to project completion. In determining the
"sufficiency" of the design level, factors such as project size, duration, and
complexity will be considered. For basic facilities, such as administrative
buildings, general purpose laboratories, and utilities, the design does not have to
be as mature as for a complex chemical or nuclear processing facility, which
would necessitate the design being complete before work begins and at 90%
before CD-2. In any case, construction should not be allowed to proceed until the
design is sufficiently mature to limit change orders to a minimum.
In conducting External Independent Reviews, NA-APM, will evaluate the
sufficiency of the project's design maturity. This analysis will serve as a key
evaluation factor in formulating its recommendation to validate a project
performance baseline. In addition, when approving a Critical Decision (CD), the
Acquisition Executive should consider the sufficiency of the design maturity.
f. For Cause Peer Review – A For Cause PR is initiated due to significant
declination in a project’s performance.
g. Independent Project Review (IPR) – An important project management tool that
serves to verify the project’s mission, organization, development, processes,
technical requirements, baselines, progress, etc. IPR’s are conducted prior to
Critical Decisions. IPR’s are performed by reviewers from within or outside the
Program but having no association with the project being reviewed.
h. Project Peer Reviews - Focused, in-depth reviews conducted by non-advocates
(Federal and M&O or other subject matter experts) supporting the design and
technical development of a project. Project Peer Reviews should be conducted at
least once a year for all >$10M projects and more frequently for the most
complex projects or those experiencing performance challenges. An IPR may
supplement or replace applicable Project Reviews at the discretion of the Program
Office or NA-APM (post CD-2 projects). The Office of Project Analysis
Oversight and Review (NA-APM 1.1) staff will conduct Peer Reviews. A copy
of all Project Peer Reviews will be forwarded to the Project Program Office.
i. Preliminary Design – Continues the design effort utilizing the conceptual design
and the Program Requirements Document (PRD) as a basis for project
development. Preliminary Design develops topographical and subsurface data
and determines the requirements and criteria, which will govern the definitive or
final design. Tasks include preliminary planning and engineering studies,
preliminary design calculations, drawings, and outline specifications, life-cycle
cost analysis, preliminary cost estimates, and scheduling for project completion.
Preliminary design provides identification of long lead procurement items and
analysis of risks associated with continued project development.
16
J.
k.
BOP-06.04
11-18-14
Project - A group of related activities that has a defined starting and end point and
is undertaken to create a unique product or service in support of a program.
Section 11
Technical Independent Project Review (TIPR)- an IPR conducted prior to
initiation of Final Design for high risk, high hazard, and Hazard Category 1, 2,
and 3 nuclear facilities. At a minimum, the TIPR shall be conducted prior to CD-
2, Approve Performance Baseline. The focus of this review is to determine that
safety documentation and design is sufficiently conservative and bounding to be
relied upon for the next phase of the project (DOE-STD-1189).
10. CONTACT. Office of Project Analysis, Oversight, and Review (NA-APM 1.1), 202-
586-6567.
BY ORDER OF THE ADMINISTRATOR:
Associate Administrator
for Acquisition and Project Management
1. purpose. This National Nuclear Security Administration (NNSA) Business Operating Procedure (BOP) describes the process for conducting Project Reviews on projects executed by the NNSA. The principal customers of the reviews are the Administrator, ...
2. CANCELLATION. BOP-50.003, Establishment of a National Nuclear Security Administration (NNSA) Independent Project Review (IPR) Policy, dated June 6, 2007 was cancelled on January 14, 2013.
3. APPLICABILITY.
5. INTEGRATION OF PROJECT REVIEWS AND PROJECT LIFECYCLE.
6. REQUIREMENTS.
8. RESPONSIBILITIES.
8. References.
9. Definitions.
10. Contact. Office of Project Analysis, Oversight, and Review (NA-APM 1.1), 202-586-6567.