BOP-50.001, NNSA ESAAB Equivalent Process
To assure that National Nuclear Security Administration (NNSA) projects follow the requirements of DOE Order 41 3.3, Program and Project Management for the Acquisition of Capital Assets, as the projects proceed from concept through design and construction to turnover to operations; to assure that NNSA programs and employees perform their roles and responsibilities in executing these projects; to assure that the NNSA acquisition process reflects an integrated approach to matching program requirements with the project development and execution process; to provide appropriate acquisition executive oversight to the NNSA acquisition process for construction projects greater than $5 million. To ensure line management involvement and accountability for project performance. To demonstrate NNSA commitment to improving the acquisition process to Departmental and Congressional elements.
Associated DOE Directive:
Version history and related documents
Superseded by
A newer version replaces this document.
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
NNSA Policy Letter: BOP-50.001
(DOE 0 413.3)
Date: August 7,2006
TITLE: NNSA ESAAB EQUIVALENT PROCESS
OBJECTIVES:
A. To assure that National Nuclear Security Administration (NNSA) projects follow
the requirements of DOE Order 41 3.3, Program and Project Management for the
Acquisition of Capital Assets, as the projects proceed from concept through
design and construction to turnover to operations;
B. To assure that NNSA programs and employees perform their roles and
responsibilities in executing these projects;
C. To assure that the NNSA acquisition process reflects an integrated approach to
matching program requirements with the project development and execution
process;
D. To provide appropriate acquisition executive oversight to the NNSA acquisition
process for construction projects greater than $5 million.
E. To ensure line management involvement and accountability for project
performance; and
F. To demonstrate NNSA commitment to improving the acquisition process to
Departmental and Congressional elements.
APPLICABILITY: The provisions of this Policy apply to all of the Administration's
organizations and elements.
REOUIREMENTS: The attached process is NNSA implementation guidance for DOE
Order 413.3 - "Program and Project Management for the Acquisition of Capital Assets,"
and applies to all capital and oper@ting projects greater than $5 million. This process
does not establish any new requirements that have not already been established within the
DOE Directives system.
RESPONSIBILITIES:
A. NNSA Administrator will monitor the implementation and results of the NNSA
ESAAB Equivalent Process.
NNSA Policy Letter
B. NNSA DeputyIAssociate Administrators are responsible for the implementation
and ongoing performance of the ESAAB Equivalent Process.
C. NNSA Associate Administrator for Infrastructure and Environment is responsible
for the maintenance of the process and providing technical assistance to other
NNSA organizations in executing the process.
V. POINT OF CONTACT FOR ADMINISTRATION BUSINESS AND OPERATING
POLICY LETTER: Director, Office of Project Management and Systems Support (NA-
Linton F. Brooks
Administrator
Attwhrnents:
1. NNSA ESAAB Equivalent Process Document
2. ESAAB Equivalent Flow Chart
NNSA Policy Letter
ENERGY SYSTEMS ACQUISITION ADVISORY
BOARD (ESAAB) EQUIVALENT PROCESS
for
NATIONAL NUCLEAR SECURITY ADMINISTRATION
July 2006
NNSA ESAAB EQUIVALENT PROCESS
NNSA 1
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
FOREWORD
This Document reflects the current requirements, understandings, and expectations related to the
headquarters’ NNSA ESAAB Equivalent Process. It has been updated to reflect the current versions of
DOE Order 413.3 ‘Program and Project Management for the Acquisitions of Capital Assets’ and DOE
Order 413.3 and DOE Manual 413.3-1 ‘Project Management for the Acquisition of Capital Assets’, and
incorporates a renewed emphasis on integrating safety into the design of projects, particularly for nuclear
projects.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 2
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
TABLE OF CONTENTS
FOREWORD.................................................................................................................................................1
1.0 BACKGROUND ...............................................................................................................................3
Section 2
2.0 PURPOSE........................................................................................................................................3
3.0 APPLICABILITY ...............................................................................................................................3
4.0 GOALS AND OBJECTIVES.............................................................................................................4
5.0 ROLES AND RESPONSIBILITIES ..................................................................................................5
6.0 BOARD MEMBERSHIP REQUIREMENTS.....................................................................................8
7.0 ESAAB EQUIVALENT PROCESS...................................................................................................9
7.1 Scheduling 9
7.2 Review and Comment Resolution 9
7.3 Pre-Briefings 10
7.4 ESAAB EQUIVALENT Board Meetings 10
ATTACHMENT 1 - ESAAB EQUIVALENT BOARD MEMBERSHIPS........................................................12
ATTACHMENT 2 – CRITICAL DECISION REQUEST AND APPROVAL MEMORANDUM EXAMPLES .14
ATTACHMENT 3 - CRITICAL DECISION INFORMATION OUTLINES.....................................................24
ATTACHMENT 4 - ESAAB EQUIVALENT PRESENTATION OUTLINE ...................................................43
NNSA ESAAB EQUIVALENT PROCESS
NNSA 3
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
1.0 BACKGROUND
DOE Order 413.3, ‘Program and Project Management for the Acquisition of Capital Assets’, and DOE M
413.3-1, ‘Project Management for the Acquisition of Capital Assets’, require that as DOE projects proceed
from concept through design, construction, and eventually start of operations, that at the end of each
phases, a designated Acquisition Executive approve the project continuing on into the next phase. These
approval points in the acquisition process are named ‘Critical Decisions’. The Critical Decision authority
resides with the Secretarial Acquisition Executive (SAE) for Major Systems projects and with other
designated Acquisition Executives (delegated from the SAE) for non-Major Systems projects. In addition
to Critical Decisions, baseline change proposals for Major Systems and other large projects are subject to
review and approval by the SAE and/or designated Acquisition Executives. Energy Systems Acquisition
Advisory Boards (ESAABs) and program office acquisition advisory boards are required by DOE Order
413.3 to advise the Acquisition Executives on the critical decisions and baseline change control proposals
that are presented for disposition.
2.0 PURPOSE
This document specifies the procedures that shall be followed by Headquarters NNSA Program Offices
with regard to the Secretarial ESAAB and NNSA ESAAB Equivalent processes. NNSA Site Offices will
develop and implement procedures that will govern Field ESAAB Equivalent processes. These
procedures are consistent with the requirements contained in DOE Order 413.3, and supporting
expectations described in more detail in DOE M 413.3-1.
3.0 APPLICABILITY
Section 3
The ESAAB Equivalent Board advises the designated NNSA acquisition executive on Critical Decisions
(CDs) for all NNSA projects not designated as Major Systems, and Level 1 Baseline Change Proposals
(BCPs) that the ESAAB Secretariat and HQ Program Office agree need review. Projects exempted from
the NNSA HQ ESAAB Equivalent Process are General Plant Projects and Capital Equipment Projects,
less than $5 Million. Responsibility for these projects is delegated to the respective Site Office Manager.
The Site Office Managers are expected to apply DOE M 413.3-1 to their projects on a graded approach.
The Acquisition Executive (AE) for the ESAAB Equivalent Board will make the final decision on the action
presented before the board based upon the input from the board members. The board members act as
subject matter experts in the evaluation of the project proposal, providing to the AE expert analysis,
advice, and recommendations with respect to the implications of the CD or BCP being discussed.
In addition, for all decisions on NNSA Major System projects, the NNSA ESAAB Equivalent Board shall
review all proposals prior to submitting them to the Departmental (Secretarial) ESAAB process. For
those Major Systems projects that have an existing Level 1 Baseline Change Board, the ESAAB
Equivalent process will utilize those boards for the review, supplemented with other disciplines from an
NNSA ESAAB Equivalent Board (i.e. Nuclear Safety, General Counsel, Procurement, etc.), to meet DOE
Order 413.3 and DOE Manual 413.3-1 requirements. Additionally to minimize the review burden on the
project, the ESAAB members support staff will be asked to participate in a combination ESAAB
Readiness Assessment/ESAAB Equivalent review meeting. The ESAAB Equivalent Board members will
advise the Deputy/Associate Administrators to the suitability of the proposed decision or baseline change
being sent forward to the Departmental ESAAB.
To enable the Secretary of Energy, NNSA Administrator, and Deputy Administrator for Naval Reactors to
fulfill the functions assigned in Executive Order 12344, as set forth in Public Law (P.L.) 98-525, the
NNSA ESAAB EQUIVALENT PROCESS
NNSA 4
July 2006
Department of Energy National Security and Military Applications of Nuclear Energy Authorization Act of
1985, and P.L. 106-65, the National Nuclear Security Administration Act, and consistent with DOE Order
413.3 and BOP-50.001, and as set forth in NNSA memorandum of 14 February 2001 and Deputy
Secretary memorandum of 20 December 2000, Naval Reactors will establish an ESAAB, chaired by the
Director, Naval Reactors to comprehensively evaluate projects between $5M and $400M (non-Major
System Projects) and ensure compliance with NR/NNSA/DOE objectives and requirements. Naval
Reactors will coordinate with and keep appropriate offices informed.
4.0 GOALS AND OBJECTIVES
The concept of using ESAABs at critical decision points in Federal projects was developed from the
Office of Management and Budget Circular No. A-109. The goals and objectives of this procedure
accordingly reflect those of A-109:
• To assure that the NNSA acquisition process reflects an integrated approach to matching
program requirements with the project development and execution process.
� Each acquisition fulfills a mission need and can achieve adequate levels of performance and
reliability in its intended operating environment.
Section 4
� Planning is built upon this mission need.
� Projects are consistent with the Site Utilization Plan and the Ten-Year Site Plan
� Competitive design concepts are evaluated, whenever economically beneficial.
� Appropriate trade-offs are made between investment costs, ownership costs, schedule and
performance.
� A project specific acquisition strategy is developed for each acquisition as soon as it is
decided to solicit alternative design concepts.
� Adequate system tests and evaluations are conducted.
� Performance is assessed against project baselines and these assessments are provided to
the agency head at critical decision points.
• To provide appropriate acquisition executive oversight to the NNSA acquisition process for
construction projects greater than $5 million.
• To ensure effective integration of safety and project management practices including the
identification and resolution of safety issues as early in the decision process as is practicable.
• To ensure line management involvement and accountability for project performance.
• To demonstrate NNSA commitment to improving the acquisition process to Departmental and
Congressional elements.
The ESAAB and ESAAB Equivalent processes also provide a vehicle by which senior management can
reinforce Departmental policy, make necessary course corrections, and verify that all organizational
elements are working towards the same goal. For nuclear projects it is critically important that the
process and expectations related to safety basis documentation, developed to comply with 10 CFR Part
830 requirements, support the CD process. As such, this procedure establishes expectations related to
specific safety basis information and documentation for nuclear related projects, including:
• Ensure that safety analysis is performed at the earliest practical point in the project lifecycle so that
required attributes of facility structures, systems, and components can be specified in design
documents.
• Ensure integration of safety basis developed and project management activities in an incremental and
iterative manner over the project lifecycle.
• Encourage integration of design and safety basis activities through use of a systems engineering
approach tailored to the specific needs and requirements of each project.
• Ensure that nuclear facilities incorporate the concept of defense-in-depth into the facility design
process.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 5
July 2006
It is understood that these goals and objectives will be attained through intelligent cooperation between
the NNSA offices responsible for programs, projects, and oversight. Where necessary, the ESAAB
Equivalent process will be adjusted by NA-54 to adapt to project unique requirements, as well as meet
the need for informed, formal decisions
5.0 ROLES AND RESPONSIBILITIES
ESAAB Equivalent Board Participant’s Functions
Acquisition Executive – Board Chair
• Preside over ESAAB Equivalent Board meetings.
• Make decisions on disposition of all requested CDs and BCPs.
• Assign action items that may result from meeting discussions.
• Assure that: 1) board members and project team members fulfill their ESAAB Equivalent
process responsibilities; 2) that they have taken the appropriate measures to ensure the
project is meeting the programmatic, safety, environmental, security, legal, procurement,
and departmental requirements; and 3) assure that those requirements have been
integrated into the design and execution of the project.
Section 5
• Review Corrective Action Plan (CAP) reports on assigned project action items.
Designated AE - The Deputy Administrator for Defense Programs (DADP), NA-10, the Deputy
Administrator for Nuclear Nonproliferation (DANN), NA-20, Deputy Administrator for Naval
Reactors, (DANR), NA-30, or the Associate Administrator for Infrastructure and Environment, NA-
50, will act as the Acquisition Executive (AE) for their respective headquarters ESAAB Equivalent
Boards, as delegated by NA-1.
For projects less than $100 million that are not designated Major Systems, the Deputy/Associate
Administrator may delegate AE responsibility to the appropriate program Assistant Deputy
Administrator (ADA) or Site Office Manager. This delegation will be made on a case-by-case
basis in accordance with the DOE M 413.3. For the current list of projects that have been
delegated, please refer to the NA-54 website,
ADA - Assistant Deputy Administrator (ADA) can act as AE for those projects delegated by the
Deputy/Associate Administrator. If the ADA is designated as the AE, the standing ESAAB
Equivalent Board members will be used for the meeting.
Site Office Manager - the Site Office Manager can act as AE for those projects delegated by the
NNSA HQ Programs, with the agreement of the Deputy Administrator for Defense Programs, NA-
10. If so delegated, the Site Office must set up an ‘ESAAB Equivalent type’ Board to review
decisions that are presented to the Site Manager. It is expected that the site board would follow
with the principles of DOE Order 413.3, with board membership and processes tailored to the site
and the nature of the projects. Board membership and procedures must be validated by NA-54.
Copies of the meeting minutes, and decisions rendered must be supplied to the respective
program office and NA-54 for historical purposes.
NNSA Chief of Defense Nuclear Safety
• For nuclear related projects, validate that the federal personnel assigned to the Integrated
Project Teams are appropriately qualified and that the level of effort expected from them is
appropriate. This validation of the IPT members will occur at or before CD-1.
• Required board member for nuclear projects, providing specific advice to the AE regarding
the effectiveness of efforts to integrate safety into design
NNSA ESAAB EQUIVALENT PROCESS
NNSA 6
July 2006
NNSA Chief Defense Nuclear Security
• For projects with significant security aspects, validate that the federal personnel assigned to
the Integrated Project Teams are appropriately qualified and that the level of effort expected
from them is appropriate.
• Required board member for projects with significant security aspect, providing specific advice
to the AE regarding the effectiveness of efforts to integrate security into design.
Board Members -
• Fully evaluate the project for compliance with the requirements in the member’s area of
expertise (programmatic, safety, environmental, security, legal, procurement, and
Departmental requirements)
• Provide assurance that those requirements have been integrated into the design and
execution of the project
• Provide timely review of project materials.
• Prepare directed questions/comments on specific project items that need resolution to
the Integrated Project Team (IPT), coordinating with the NNSA program office and the
ESAAB Equivalent Secretariat (NA-54)
• Work to resolve issues with IPT.
• Attend all ESAAB Equivalent Board meetings or provide an alternate.
• Provide recommendation of disposition to the Board Chairperson.
Section 6
NNSA ESAAB Equivalent Board members will act as subject matter experts in the evaluation of
the proposed CD or BCP, to 1) assure that NNSA and DOE requirements are met and common
construction/business practices are followed; and 2) provide effective recommendations and
advice to the board chairperson (i.e. the Acquisition Executive). For nuclear related projects, the
NNSA Chief of Defense Nuclear Safety will be included as a Board member providing specific
advice to the AE regarding the effectiveness of efforts to integrate safety into design.
Program Office -
• Works with the Federal Project Director and the Integrated Project Team to assure that
the project is in compliance with programmatic, safety, environmental, security, legal,
procurement, and departmental requirements
• Works with the Federal Project Director and the Integrated Project Team to assure that
those requirements have been integrated into the design and execution of the project
• Concurs in submittal of Level BCPs to ESAAB for disposition to acquisition executive
• Works with Federal Project Director to prepare project and materials for presentation to
board.
• Coordinates with Federal Project Director and ESAAB Equivalent Secretariat to schedule
meetings.
• Works with Federal Project Director to answer inquiries/resolve issues with board
members.
• Prepares Decision Memorandum for Acquisition Executive signature.
• Coordinates Decision Memorandum with NA-54 to capture action items and/or issues
resulting from the review.
• When Federal Project Director not available, presents proposed Critical Decision or
Baseline Change Proposal to board.
The program office, as part of the Integrated Project Team, coordinates with the Federal Project
Director and ESAAB Equivalent Secretariat to manage the project through the ESAAB Equivalent
process.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 7
July 2006
Federal Project Director -
• Works with the Integrated Project Team and Program Office to assure that the project is
in compliance with programmatic, safety, environmental, security, legal, procurement,
and departmental requirements
• Works with the Integrated Project Team and Program Office to assure that those
requirements have been integrated into the design and execution of the project
• Obtains Program Office concurrence on submittal of Level 0 BCPs for disposition
• Coordinates preparation of project documents supporting the decision process.
• Coordinates with Program Office and ESAAB Equivalent Board Secretariat to schedule
board meeting.
• Prepares ESAAB Equivalent Board presentation.
• Presents proposed change to Board.
• Works with Program Office and Integrated Project Team to respond to ESAAB Equivalent
Board questions/requests and resolves issues.
The Federal Project Director, as part of the Integrated Project Team, will prepare the project
decision packages, coordinate project responses to board members comments/questions, and
present the information to the AE and the board for consideration.
ESAAB Equivalent Secretariat –
• Coordinates ESAAB Equivalent Board schedules for the AEs.
• Coordinates NNSA ESAAB and ESAAB Equivalent Board schedules with OECM.
• Offers improvements/suggestions on project planning and process to the AE, Program
Office, and Integrated Project Team (IPT).
• Provides written comments on significant project issues to the AE, Program Office, and
Integrated Project Team (IPT).
• Advises AE on the technical and management significance of issues identified from
Section 7
ESAAB and Quarterly reviews.
• Provides science-based recommendations on the root cause of issues and how they can
be resolved.
• Provides expert technical reviews and comments on the planning and execution of
construction projects for headquarters and field elements.
• Develops lines of inquiry for use at the ESAAB Equivalent meeting.
• Records minutes and action items resulting from the AE reviews.
• Coordinates decision memorandum process so: 1) decisions are appropriately
documented; 2) action items/issues are captured and included in the decision
memorandum package; and 3) the memorandum is properly distributed to the project
managers, board members and involved program offices.
• Maintains database/library of HQ ESAAB Equivalent Board meetings and actions
• Works with Federal Project Director, Program Office, and ESAAB Equivalent members to
facilitate review process, arranges meetings, and tracks issues to resolution.
• Works with all parties to improve the ESAAB Equivalent Board process.
• Monitors/validates procedures and processes from Site Offices ESAAB Equivalent
boards.
The secretariat will coordinate the meetings, participate in the ESAAB Equivalent process, advise
the acquisition executive on the issues of the project, and assist the Acquisition Executive in
disseminating information to and from the meeting.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 8
July 2006
6.0 BOARD MEMBERSHIP AREAS OF EXPERTISE REQUIREMENTS
The following table shows the areas of expertise that must be reflected in the membership for the NNSA
ESAAB Equivalent Board that will review and/or approve Critical Decisions and Baseline Change
Proposals for all NNSA line item projects. These areas of expertise are requirements as outlined in the
DOE M 413.3 – Project Management for the Acquisition of Capital Assets. Each area of expertise must
have a designated principal board member and a designated alternate. Line item projects below $100
million that have been delegated to Site Office Managers will be reviewed by a similarly constituted Site
Office level ESAAB Equivalent Board. (The NNSA Board membership is listed in attachments).
Role/Area of Expertise Principal Board Member Alternate Board Members
Chair
Nuclear Safety
Legal
Budget
Environmental
Safety & Health (incl. Integrated
Safety Mgt.)
Security
Procurement
Project
Management
Specialized support as required
Other support as required
ESAAB Equivalent Secretariat
NA-54
OECM Participants
(when required)
NNSA ESAAB EQUIVALENT PROCESS
NNSA 9
July 2006
7.0 ESAAB EQUIVALENT PROCESS
7.1 Scheduling
The Federal Project Director with the concurrence of the NNSA headquarters Program Office will request
an ESAAB Equivalent Board meeting for approval of a Critical Decision (CD) or Baseline Change
Proposal (BCP). This ESAAB Equivalent Board request will follow the format in Attachment 2 and be
forwarded to the ESAAB Equivalent Secretariat (NA-54), who will begin the scheduling process with the
program office and Federal Project Director.
Once a request is received, the Secretariat will coordinate with the AE, OECM, and board members for
the ESAAB Equivalent meeting and notify the Federal Project Director and Program Office of the specific
date.
(The Secretariat will maintain an ESAAB Equivalent schedule on the NA-54 website, that will be
updated with the latest available information.)
7.2 Review and Comment Resolution
Section 8
• The major facet of the NNSA ESAAB Equivalent process is the review and comment
resolution phase. In this phase the ESAAB Equivalent members evaluate the project
request and formulate their comments, issues, and recommendations. The goals of this
phase are: 1) to assure that the project is in compliance with programmatic, safety,
environmental, security, legal, procurement, and departmental requirements; 2) to assure
that those requirements have been integrated into the design and execution of the project
and 3) to resolve all comments and issues prior to the formal ESAAB Equivalent meeting
with the Acquisition Executive.
a. Federal Project Directors, in cooperation with the advocate Program Office will supply appropriate
project documents and materials to the board members approximately one month in advance of
the board meeting. The materials provided will be the requested action documents (i.e. CD
request or BCP), results from any external and/or internal reviews since the last ESAAB
Equivalent meeting, Corrective Action Plans, and other materials that support the proposed
decision or BCP. Attachment 3 contains listings of required documents and comprehensive
outlines of suggested topics/lines of inquiry for each Critical Decision. For nuclear projects,
Attachment 3 establishes expectations to ensure that nuclear safety is properly integrated into
design for each of the CD stages.
b. The board members and the Secretariat will examine the project through the provided materials
and provide directed questions/comments to the Federal Project Director and Program Office.
Board members evaluations should identify project inadequacies, emphasizing in the comments:
• Areas where the project is not in compliance with programmatic, safety, environmental,
security, legal, procurement, and departmental requirements or where requirements have
not been addressed
• Areas where the project has not demonstrated that the requirements have been
integrated into the design and execution of the project
• Those items to be corrected that are proven to ensure probability of project success.
• If the board member decides that the project is not adequately prepared, could the
project proceed with additional requirements
• Document reasons for any critical comment and provide the cost implications of
instituting the board member’s recommendation that addresses comments.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 10
July 2006
c. A telephone conference call or tele-video conference review meeting will be held with the Federal
Project Director, the other IPT members in the field, Program Office, Board staff, and the
Secretariat, to review the project, discuss the comments/questions of the board members and set
a schedule for resolving the outstanding issues/requirements.
d. For NNSA projects that are requesting a decision from the Secretarial ESAAB, the board
members of the ESAAB will be invited to participate in a combined NNSA ESAAB
Equivalent/ESAAB staff meeting. As above, this meeting will be to discuss the
comments/questions of the board staff and work on a schedule for resolving outstanding
issues/requirements. This meeting will take the place of a separate ESAAB staff briefing on the
project.
e. After the review meeting, the Federal Project Director and Program Office will work with the board
members and their staffs to answer inquiries and resolve issues prior to the formal ESAAB
Equivalent Board meeting. If necessary, additional telephone and/or tele-video conferences can
be held to resolve outstanding comments/issues.
Section 9
f. The Secretariat will participate as an advisor to the AE, summarize results of the review and
comment process, and will; 1) offer improvements/suggestions on project planning and process;
2) provide written comments on significant project issues; and 3) provide lines of inquiry for use at
the ESAAB Equivalent meetings and quarterly reviews; to the acquisition executive, program
office and IPT.
7.3 Pre-Briefings
The purpose of the pre-brief is to have a final ‘run through’ with the Deputy/Associate Administrator,
ADAs, and/or staff, to present the project status and issues, and obtain feedback on the presentation prior
to proceeding with the scheduled Secretarial ESAAB Board meeting. For nuclear projects, if there are
any outstanding issues related to integration of safety into design, these will be summarized. For projects
with significant security aspects, any outstanding issues related to integrating security into design, these
will be summarized.
For Major Systems projects that have CD or BCP actions submitted to the Secretarial ESAAB board, a
Pre-Brief with the Deputy/Associate Administrator will be held, at their discretion, at least 2-3 days prior to
the ESAAB meeting. A separate Pre-Brief with NA-1 will also be scheduled 2-3 days prior to the meeting.
Pre-brief presentation materials must be provided to the Secretariat 3 days prior to the pre-brief for
distribution to board members.
7.4 ESAAB Equivalent Board Meetings
a. After the review and comment phase has been completed, the Federal Project Director and
Program Office will confirm their intent to continue with the ESAAB Equivalent meeting with the
Secretariat. The Secretariat will make final meeting preparations, distribute the project
presentation to the board members, and coordinate the preparation of a decision memorandum.
b. The decision memorandum, see Attachment 2 for example, will be prepared by the Federal
Project Director and Program Office prior to the meeting and provided to the Secretariat for use at
the ESAAB Equivalent meeting. This memorandum will: 1) describe the decision requested; 2)
capture action items and/or issues resulting from the ESAAB Equivalent review; 3) document
assurances to the AE that the project have addressed the programmatic, safety, environmental,
security, legal, procurement, and departmental requirements; 4) document assurances to the AE
that the project has appropriately integrated those requirements into the design and execution of
the project; and 5) incorporate approval and disapproval spaces for use by the AE and board
members endorsements. The Secretariat will work with the Program Office to ensure decision
memorandum package is complete and obtain board member concurrences prior to the final
meeting.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 11
July 2006
c. At the formal meeting, the Federal Project Director (and/or a Program Office member) will present
the project before the ESAAB Equivalent Board. The presentation should be brief and emphasize
programmatic issues; basic overview of the project; actions taken to assure that the project have
addressed programmatic, safety, environmental, security, legal, procurement, and departmental
requirements; actions taken to assure that the requirements have been appropriately integrated
into the design and execution of the project; comment/issue resolution; and the decision that is
being requested of the AE. (See Attachment 4 for outline of ESAAB Equivalent presentation.)
Any unresolved issue that requires action by the AE should be presented at this time.
Section 10
d. At the conclusion of the presentation, the Decision memo will be offered to the acquisition
executive for signature. The Decision memo will incorporate approval or disapproval, and action
items and/or issues that result from the ESAAB Equivalent review, as appropriate. Signed copies
of the Decision memo will be provided to the Federal Project Director, program office, ESAAB
Equivalent Board members and involved offices within a week of signatures.
Significant changes to the Decision memo, if required, will be made by the Program Office and
IPT, and offered to the acquisition executive for signature within one week of the ESAAB
Equivalent Board meeting.
For Major Systems projects, the Office of Engineering and Construction Management, ME-80, will
prepare the decision memorandum for the Under Secretary’s (S-2) signature. NNSA Program
Office, Project Team, and Secretariat will be asked for input in the drafting of the memorandum.
e. The proceedings of the meeting will be mechanically recorded by the Secretariat. Transcripts of
the action items identified will be distributed to Federal Project Director, Program Office, board
members and interested offices, within two weeks of the meeting.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 12
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
ATTACHMENT 1 - ESAAB EQUIVALENT BOARD MEMBERSHIPS
NNSA ESAAB EQUIVALENT PROCESS
NNSA 13
July 2006
NNSA ESAAB Equivalent Board Membership
Role/Area of Inquiry Principal Board Member Alternate Board Members
Chair Deputy/Associate Administrator Principal Assistant Deputy/Associate
Administrator for Operations
Nuclear Safety Jim McConnell, NA-2.1 P. Cahalane, NA-2.1
D. Minnema, NA-2.1
Legal
Dave Jonas, NA-3.1 R. P. Detwiler, NA-3.1
C. Pak, NA-3.1
Budget Kate Foley, Director, Office of Planning,
Programming, Budgeting, and Evaluation
(PPBE), NA-62
E. Stewart, NA-62
D. Gezelle, NA-62
Environmental Frank Russo, NA-3.6 J. Ordaz, NA-3.6
Safety & Health
(incl. Integrated
Safety Mgt.)
Frank Russo, NA-3.6 T. Wyka, NA-3.6
Security Bill Desmond, NA-70 A. Starnes, NA-70,
C. Stone, NA-70
Procurement Keith Landolt, NA-63
Ed Simpson, ME-62
G. Lyttek, NA-63
Project
Management
Thad Konopnicki, NA-54 M. Hickman, NA-54
D. Oliff, NA-54
Specialized support
as required
Project-specific technology support:
R&D subject matter experts
Program specialists
ES&H subject matter experts
Other support as
required
Office of Diversity
Public Affairs
Congressional Affairs
ESAAB Equivalent Secretariat
NA-54 Thad Konopnicki, Director Office of Project
Management Support, NA-54
Dale Oliff, NA-54
OECM Participants
(when required)
Mike Donnelly, MA-50
Sheri Bone, MA-50
NNSA ESAAB EQUIVALENT PROCESS
NNSA 14
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
ATTACHMENT 2 – CRITICAL DECISION REQUEST AND APPROVAL MEMORANDUM EXAMPLES
NNSA ESAAB EQUIVALENT PROCESS
NNSA 15
July 2006
REQUEST FOR
NNSA ENERGY SYSTEMS ACQUISITION ADVISORY BOARD (ESAAB)
EQUIVALENT REVIEW
Name of Project
Project Location
Project Number Major System? Yes No
Acquisition Executive
Critical Decision 0
Critical Decision 1
Critical Decision 2
Critical Decision 3
Critical Decision 4
Baseline Change Proposal, Level
Type of Review:
Other:
Name E-Mail Org
NNSA Project Director:
Contractor Project Manager:
HQ Program Manager(s):
An NNSA Pre-ESAAB Equivalent Review is Requested on or between these dates:
Section 11
A full NNSA ESAAB Equivalent Review is Requested on or between these dates:
ADDITIONAL ATTENDEES
If your office would like to have the electronic meeting notice for this meeting sent to individuals in addition to the names provided
on this form, include those names and e-mail addresses here:
NAME E-MAIL ADDRESS ORG
The supporting documentation will be available for the ESAAB Equivalent Board members’ review on the Shared Files on the
Extranet NA-54 Web site (https://extranet.nnsa.doe.gov/) at least one month prior to the ESAAB Equivalent scheduled meeting
date*:
1.
I acknowledge and accept
the above requirement: Project Director Date Phone #
2. Approved for scheduling:
Program Office Requesting/Certifying
Official
Date Phone #
3. Fax or e-mail to NA-54 for scheduling: Fax #: 301-903-2544 (To confirm: 301-903-3557)
ATTN: Dale Oliff/Jane Gartner/Ginnie Barazotto, NA-54
E-mail: 1) Save the file;
2) from the Menu bar click on FILE/SEND TO/MAIL RECIPIENT - as Attachment.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 16
July 2006
Required Review Materials
CD-0 Approve Mission Need
1. Mission Need Statement
2. Tailoring Strategy
3. Program Requirements Document
4. Results from Mission Validation Independent Review (if required), and any external and/or internal reviews
including Corrective Action Plans
5. Presentation
CD-1 Approve Alternative Selection and Cost Range
1. Conceptual Design Report
2. Cost Estimate, including documentation on the basis and assumptions
3. Acquisition Strategy
4. One-for-One Replacement documentation
5. Preliminary Project Execution Plan
6. Integrated Project Team
7. Design Review Results, including Technical Independent Project Review (when required)
8. Preliminary Project Data Sheet
9. NEPA strategy and analysis documents
10. High Performance Sustainable Building documentation
11. Preliminary Security Vulnerability Assessment Report
12. Conceptual Safety Design Report (when required)
13. Preliminary Hazard Analysis Report (when required)
14. Safety Evaluation Report (when required)
15. Quality Assurance Program documentation
16. Presentation
CD-2 Approve Performance Baseline
1. Project Execution Plan
2. Performance Baseline (i.e., scope, cost, schedule, risk mitigation, etc.)
3. Cost Estimate, including documentation on the basis and assumptions
4. Performance Baseline Validation Review results including Corrective Action Plans
5. Performance Baseline Validation Letter
6. Independent Cost Estimate or Independent Cost Review (when required)
7. Quality Assurance Program documentation
8. Updated Project Data Sheet
9. Design Review results
10. Preliminary Safety Design Report (when required)
11. Approved Hazard Analysis Report
12. Updated Security Vulnerability Assessment Report
13. Safety Evaluation Report (when required)
14. Evidence of incorporating Sustainable Environmental Stewardship – High Performance Sustainable Building
provisions
15. Final NEPA documentation
16. Presentation
CD-3 Approve Start of Construction
1. Design Review results from final design review
2. Approved Preliminary Safety Analysis Report and DOE Safety Evaluation Report
3. Updated Project Execution Plan and Performance Baseline
4. Results from an Execution Readiness External Independent Review for Major Systems
5. Preliminary Documented Safety Analysis Report (when required)
6. Updated Hazards Analysis Report
7. Updated Security Vulnerability Assessment Report
8. Safety Evaluation Report
9. Approved Construction Project safety and Health Plan
Section 12
NNSA ESAAB EQUIVALENT PROCESS
NNSA 17
July 2006
10. Evidence of incorporating Sustainable Environmental Stewardship – High Performance Sustainable Building
provisions
11. Updated Quality Assurance Program
12. Project Data Sheet
13. Presentation
CD-4 Approve Start of Operations or Project Closeout
1. Verification of Key Performance Parameters or Project Completion Criteria
2. Completed Operational Readiness Review or Readiness Assessment
3. Checkout, Testing and Commissioning Plan
4. Project Transition to Operations Plan
5. Updated Quality Assurance Plan
6. Revised environmental management system
7. Documented Safety Analysis Report with Technical Safety Requirements (when required)
8. Updated Construction Project safety and Health Plan
9. Approved Final Hazards Analysis Report
10. Final Security Vulnerability Assessment Report
11. Safety Evaluation Report (when required)
12. Presentation
PLEASE NOTE:
• ESAAB Equivalent Board members expect all review documents will be made available on Shared
Files on the NA-54 Extranet website for review at least one month prior to scheduled meetings.
• The Project Director agrees to notify Dale.Oliff@nnsa.doe.gov or Jane.Gartner@nnsa.doe.gov if the
supporting documentation will not be ready for review one month prior to scheduled meetings.
• Board members may reschedule meetings if adequate review time is not provided.
NA-54 Extranet website is located at: https://extranet.nnsa.doe.gov
DO NOT FAX THIS PAGE
NNSA ESAAB EQUIVALENT PROCESS
NNSA 18
July 2006
SAMPLE CD-2 MEMORAMDUM
DOE F 1325.8
(08-93)
United States Government Department of Energy
memorandum
DATE:
REPLY TO
ATTN OF: DP-17 (S. Jaghoory, 3-7091)
SUBJECT: Renovating Roadways Project at the Nevada Test Site, Line Item 99-D-108
TO: Assistant Deputy Administrator for Research, Development and Simulation, DP-
10
Issue: Approval of the Critical Decision (CD) -2, Start Final Design; a
partial CD-3, Start Construction; and a Baseline Change Proposal
(BCP) for the subject project.
Background: This line item project is part of the overall revitalization of the
Nevada Test Site infrastructure that began in early 1980s.
Planning for this project began in early 1990s and it received its
first funding in the Fiscal Year (FY) 1999. However, Congress
imposed a moratorium on releasing the appropriated funds until
the report of the Congressionally mandated External Independent
Review (EIR) was submitted to Congress. This report was
submitted to Congress in June 1999. However, Congress did not
lift the moratorium and cut the FY2000 funding request by more
than $2 million. As a result, the Total Estimated Cost (TEC) of the
project is now $8.981 million instead of $11.005 million. Because
the Department met the intent of the Congressional mandate for
the EIR, Defense Programs released the project funds in early
January 2000.
Discussion: Prior to the cut in the TEC, the scope of the project included
renovating the entire 37 miles of the Mercury Highway and the
total reconstruction of the 2.3 mile long Rainier Mesa Road at the
Nevada Test. To comply with the reduction in the TEC, Defense
Programs proposed to perform a comprehensive survey of the
Mercury Highway and renovate only the worst segments of the
road. This survey has been completed and based on the available
funds only approximately 15.2 miles of the Mercury Highway will
be renovated and the 2.3 mile long Rainier Mesa Road
reconstructed. In addition, contingency plans have been
developed by the project team to increase the scope of the
renovation, if Congress reinstated the cut in the TEC in FY2001.
Section 13
The Title I design has been completed by Bechtel Nevada (BN)
and appropriate design documents have been submitted for review
and comments. These documents have been reviewed by the DP-
17 staff and the DOE Federal Project Director. Comments on the
NNSA ESAAB EQUIVALENT PROCESS
NNSA 19
July 2006
reviewed documents have been submitted to BN for resolution. To
proceed with the final design on a timely fashion, the Federal
Project Director is requesting the CD-2 approval, prior to the
resolution of these comments.
In addition to the CD-2, a partial CD-3 approval is requested to
allow BN to proceed with cleaning and reconstructing the drainage
ditches prior to commencing the main renovation and
reconstruction. Renovating the Mercury Highway and
reconstructing the Rainier Mesa Road will be performed by an
outside subcontractor, through a firm, fixed contract. BN's activity
is scheduled to start soon after the partial CD-3 approval.
A Baseline Change Proposal is also submitted by the Federal
Project Director to re-establish the scope, cost, and schedule for
the project. Although the FY2001 Construction Project Data Sheet
incorporated the changes in the cost, schedule, and scope of the
project, these changes were not formally approved by the
Acquisition Executive.
Member of Defense Programs Energy Systems ESAAB
EQUIVALENT-Equivalent have reviewed the Title I design
documents and the BCP and recommended their approval. As a
result, I request that you approve the CD-2 and CD-3 requests and
BCP to allow the project to proceed to the next phase.
Recommendation: That you sign the attached memorandum to the Manager,
Department of Energy Nevada Operations Office.
Dennis Miotla
Director, Office of Facilities Management and
ES&H Support
Defense Programs
Attachment
NNSA ESAAB EQUIVALENT PROCESS
NNSA 20
July 2006
DOE F 1325.8
(08-93)
United States Government Department of Energy
memorandum
DATE:
REPLY TO
ATTN OF: DP-17 (S. Jaghoory, 3-7091)
SUBJECT: Renovating Roadways Project at the Nevada Test Site, Line Item 99-D-108
TO: Manager, Department of Energy Nevada Operations Office
By this memorandum, I am approving the Critical Decision (CD)-2, Start Final
Design; the partial CD-3, Start Construction; and the Baseline Change Proposal
for the subject project. These approvals were requested by the DOE Nevada
Operations Office (NV) Federal Project Director. My approval is based on the
recommendations of members of Defense Programs Energy Systems ESAAB
EQUIVALENT-Equivalent.
Successful completion of this project is critical to Defense Programs mission at the
Nevada Test Site. As a result, at this time, I will maintain the Acquisition
Executive (AE) responsibility for the project. Once I am confident that the project
is proceeding within the established baselines, I may delegate the AE
responsibility to you.
The DOE NV Federal Project Director has been prompt and diligent in submitting
the required monthly progress report for this and other line item projects at the
Nevada Test Site. I would like to thank him for his effort and encourage him to
continue submitting the monthly reports to keep me and my staff apprised of the
status of the projects.
If you have any questions, please contact me at 202-586-7349 or Dennis Miotla at
301-903-5427.
David H. Crandall
Acting Assistant Deputy Administrator for
Research, Development and Simulation
Defense Programs
NNSA ESAAB EQUIVALENT PROCESS
NNSA 21
July 2006
Section 14
SAMPLE CD-4 MEMORANDUM
DOE F 1325.8
(08-93)
United States Government Department of Energy
memorandum
DATE:
REPLY TO
ATTN OF: DP-17 (S. Jaghoory, 3-7091)
SUBJECT: Critical Decision-4 for the Water Well Replacement Project, Line Item 96-D-102-
010, at the Los Alamos National Laboratory
TO: Acting Deputy Administrator for Defense Programs
Issue: Headquarters approval of Critical Decision (CD-4) is required to
start operating the new water wells constructed under the subject
line item.
Background: This project was initiated to provide four new 800-gallons per
minute (gpm) production wells to replace six existing, marginal or
non-producing wells located in the Guaje Well Field. Each new
well location included drilling, casing, and development of an
approximate 2,000-foot deep well with an associated pump house
equipped with lights, heating, and ventilation systems.
Discussion: Construction activities that were included in the baseline scope of
this project were successfully completed on time in September
1999 and substantially below the Total Estimated Cost of $16.8
million. At the end of Fiscal Year 1999, the Los Alamos National
Laboratory (LANL) returned $2,500,000 of the surplus contingency
fund to Defense Programs. Currently, it is estimated that at least
$200,000 more could be returned once all cost accounts are
closed, which is tentatively scheduled for May 31, 2000.
However, the baseline scope of 800 gpm was not achieved. This
output was based on preliminary information and approximate
data. However, later hydrological studies conducted by LANL and
other experts determined that the total designed amount of 3,200
gpm cannot be sustained over a long period without permanently
damaging the aquifer. As a result, the overall output from the four
wells is now restricted to approximately 2,200 gpm. This reduction
in output is compensated for with higher than expected output from
wells in another existing well-field and the return to operation of a
non-producing well.
Pre-operational tests have shown that pumps at three of the four
new wells are not working as designed. Accordingly, LANL is
working with the pump installers and manufacturer to correct the
problem. This issue is being addressed through the normal
NNSA ESAAB EQUIVALENT PROCESS
NNSA 22
July 2006
warranty agreement at no cost to the Department of Energy.
Water production and distribution, including operation of the new
wells, will be transferred to the County of Los Alamos to comply
with the 1998 Defense Authorization Act, Public Law 105-85. Final
details of the transfer are being worked out between the County,
DOE, and LANL.
The Energy System ESAAB EQUIVALENT members have
reviewed this package and recommended its approval. This
project is not designated as a Major System. As such, a January 3,
2000, memorandum from the Deputy Secretary assigned the
responsibility of all critical decisions for non-Major Systems to the
Program Secretarial Officers.
Recommendation: That you sign the attached letter to the Manager, Los Alamos Area
Office.
David H. Crandall
Acting Assistant Deputy Administrator
for Research, Development, and Simulation
Defense Programs
Attachment
NNSA ESAAB EQUIVALENT PROCESS
NNSA 23
July 2006
DOE F 1325.8
(08-93)
United States Government Department of Energy
memorandum
DATE:
REPLY TO
ATTN OF: DP-17 (S. Jaghoory, (301) 903-7091)
SUBJECT: Critical Decision-4 for the Water Well Project, Line Item 96-D-102-010, at the
Section 15
Los Alamos National Laboratory
TO: Manager, Los Alamos Area Office
In accordance with the request received from the Los Alamos Area Office,
authorization is hereby granted for Critical Decision 4, Transition to Operations,
for the Water Wells Replacement project at Los Alamos National Laboratory.
This decision is based on recommendations of the Defense Programs Energy
Systems ESAAB EQUIVALENT- Equivalent members. I expect the project
close-out report to be finalized before the end of May 2000 and an information
copy sent for my review and record.
Please convey my congratulations and appreciation to our DOE Project
Engineer, Mr. Steve Fong, and the Los Alamos National Laboratory's project
staff for a job well done. Their hard work and dedication were instrumental in
the successful completion of this important project.
If you have any question, please contact me or have your staff contact Mr.
Dennis Miotla at (301) 903-5427.
THOMAS F. GIOCONDA
Brigadier General, USAF
Acting Deputy Administrator
for Defense Programs
NNSA ESAAB EQUIVALENT PROCESS
NNSA 24
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
ATTACHMENT 3 - CRITICAL DECISION INFORMATION OUTLINES
NNSA ESAAB EQUIVALENT PROCESS
NNSA 25
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
ATTACHMENT 3 - CRITICAL DECISION INFORMATION OUTLINES
CRITICAL DECISION 0 (CD-0) - APPROVE MISSION NEED
A. Required Information:
The following is the List of Critical Decision Prerequisites from the DOE Order 413.3 and DOE
Manual 413.3-1.
Mission Need Statement
Tailoring Strategy
Program Requirements Document
Results from Mission Validation Independent Review (if required),
and any external and/or internal reviews including Corrective Action Plans
Presentation
B. Suggested Project Preparation Topics for Critical Decisions
The following list provides a general outline for construction scope, cost, schedule, management,
and other project related topics that a project requesting CD-0, Approve Mission Need, typically
will have investigated prior to the decision. As part of the project development process, field and
IPT members document results from the investigation of these topics. The depth and breadth of
the effort in addressing these project development topics would be scaled, based upon the cost,
complexity, and risks of the project. For example, not all projects will be required to follow the
formal Safety Analysis Report process, but all projects should perform a hazards analysis.
For nuclear related projects, to ensure that nuclear safety is appropriately integrated into design,
those nuclear safety related expectations that should be considered as mandatory are identified
in bold.
This list is offered as an aid in preparing for a CD-0. DOE project lessons learned and Project
Management studies have shown that "projects fail not because they planned to fail, but because
they have failed to plan. The listing is an attempt to capture the important issues/topics that
typically have caused NNSA projects problems in the past.
Note: The following lists of topics will be merged with the list of recommended review topics/lines
of inquiry in the Independent Project Review Plan.
Statement of Mission Need
define specific need of program
relate need to DOE and NNSA strategic Plans
identify how project functions support mission
mission need date for project
impact of not meeting mission need date
impact of Critical Decision 0 delay
identification and support of mission advocate
Section 16
Brief Description
NNSA ESAAB EQUIVALENT PROCESS
NNSA 26
July 2006
location (site selection decision required?)
purpose & function
features
long term goals
Minimum Technical/Functional Requirements
Technical performance objectives and interfaces
feasibility of meeting objectives
R&D required – How funded? R&D plan costs, program support/schedule of deliverables
for design
availability of special systems/equipment
integration with other project activities
quality assurance planning
demonstrate linkage between requirements and mission
Facility Design Description complete?
Systems Engineering Planning
Safety, including Nuclear Safety
define safety objectives and constraints
Initial estimated facility hazard categorization based on a project radiological
inventory
Preliminary evaluation on whether safety SSCs will be needed and the steps to be
taken during the definition phase (conceptual design) to establish facility level
safety system classification
integrated safety management strategy/process flow diagram
Acquisition Strategy
acquisition decision process
acquisition alternatives being considered (i.e. Design-Bid-Build, Design-Build, Lease
Back)
factors for determining decision
strategy to obtain and use Preliminary Engineering and Design (PED) funding
/incremental funding or other funding profiles
survey of public and private sector to determine current state-of-the-art project delivery
systems and selection of benchmarks of similar projects in DOE and private
industry/lessons learned
make-buy decision process
define and evaluate feasibility of alternatives of facility/system being proposed
Tri-lab agreement placement/site priority
Resource Capability
ID capabilities required
capabilities of site personnel in these technologies to support project
strategy to obtain necessary project capabilities
Risks
preliminary risk assessment
basis for risk assessment
mitigation strategies
Preliminary Security Planning
planned Security Assessments vulnerabilities
compliance with Design Basis Threat Policy
functional requirements for security defined
preliminary security determination from review of Site Safeguards & Security Plan
plan for addressing security in design
NNSA ESAAB EQUIVALENT PROCESS
NNSA 27
July 2006
Preliminary Environmental Strategy
expected NEPA strategy
pollution prevention issues
waste minimization issues
other expected environmental issues
local outreach strategy
Sustainable Design strategies
Proposed Cost and Schedule
fiscal year funding start
expected design duration
expected construction duration
critical milestones
cost range for project TEC & TPC
preliminary funding profile
mortgage analysis (capital and operating) – does this reasonably fit in NNSA budget out
years?
facility operating costs – can NNSA budget support operating costs?
preliminary CD1 & CD2 Request dates versus budget cycle milestones
Preliminary Legal Strategy
preliminary determination on make-buy decisions
preliminary review of local agreements
preliminary NEPA and permitting strategy
Organizational Interfaces
Involvement of related agencies
Strategy for developing internal agency agreements
State and regulatory agency agreements
Strategy for cooperation/collaboration with agencies
Conceptual Planning/acquisition
cost
Congressional notification/approval required (CDR cost > $3M)
schedule/duration
budget planning requirements
who will do CDR
Section 17
how will it be acquired/accomplished
additional R&D and/or planning required prior to CD-1
option to be developed
total operating (OPEX) prior to Title I start
Source of conceptual phase funding.
Project Management (Federal Acquisition Team)
members - organized, charter – roles & responsibilities of each
program manager - names
project manager/COTR relationship
safety
environmental and health
legal
contracts
public outreach
maintenance and operations
contracting officer
NNSA ESAAB EQUIVALENT PROCESS
NNSA 28
July 2006
copy of proposed Project Manager resume and history
Project inclusion in M&O performance award?
Identify all assumptions
Identify similar successful and unsuccessful
project on site and other sites for future
bench marking and lesson learned identification
NNSA ESAAB EQUIVALENT PROCESS
NNSA 29
July 2006
CRITICAL DECISION 1 (CD-1) - APPROVE PRELIMINARY BASELINE RANGE
A. Required Information:
The following is the List of Critical Decision Prerequisites from the DOE Order 413.3 and DOE
Manual DOE 413.3-1. This list is subject to change and will be updated when there are changes
to the Order:
Conceptual Design Report
Cost Estimate, including documentation on the basis and assumptions
Acquisition Strategy
One-for-One Replacement documentation
Preliminary Project Execution Plan
Integrated Project Team
Design Review Results,
including Technical Independent Project Review (when required)
Preliminary Project Data Sheet
NEPA strategy and analysis documents
High Performance Sustainable Building documentation
Preliminary Security Vulnerability Assessment Report
Conceptual Safety Design Report (when required)
Preliminary Hazard Analysis Report (when required)
Safety Evaluation Report (when required)
Quality Assurance Program documentation
Presentation
B. Suggested Project Preparation Topics for Critical Decisions
The following list provides a general outline for construction scope, cost, schedule, management,
and other project related topics that a project requesting CD-1, Approve Preliminary Baseline
Range, typically will have investigated prior to the decision. As part of the project development
process, field and IPT members document results from the investigation of these topics. The
depth and breadth of the effort in addressing these project development topics would be scaled,
based upon the cost, complexity, and risks of the project. For example, not all projects will be
required to follow the formal Safety Analysis Report process, but all projects should perform a
hazards analysis.
For nuclear related projects, to ensure that nuclear safety is appropriately integrated into design,
those nuclear safety related expectations that should be considered as mandatory are identified
in bold.
This list is offered as an aid in preparing for a CD-1. DOE project lessons learned and Project
Management studies have shown that "projects fail not because they planned to fail, but because
they have failed to plan". The listing is an attempt to capture the important issues/topics that
typically have caused NNSA projects problems in the past.
Note: The following lists of topics will be merged with the list of recommended review topics/lines
of inquiry in the Independent Project Review Plan.
Statement of Mission Need - Validation of currency
define specific need of program
relate need to DOE and NNSA strategic Plans
identify how project functions specifically support mission
mission need date for project
Section 18
NNSA ESAAB EQUIVALENT PROCESS
NNSA 30
July 2006
impact of not meeting date
Brief Description
location (site selection decision approved?)
purpose & function
features
long term goals
plan to overcome past site project development/execution problems?
Technical/Functional Requirements
treatment of technical performance objectives and interfaces in conceptual design
If nuclear facility, reviewed and selected appropriate NRC standards?
feasibility of meeting objectives
R&D funding in place, integrated in project schedules/completed ID deliverables for
design
availability of special systems/equipment
reliability of systems as relates to facility usability
review of design components that would effect future decommissioning
integration with other project activities
Title I design control strategies
configuration management plan and implementation process
Plan for incorporation of lessons learned from similar projects
Implementation of Quality Assurance (QA) Plan
compare to 6% design benchmark used by DOD
impact of Critical Decision delay
compare to GSA Administration space guidance
Safety, including Nuclear Safety
ID facility processes
Preliminary Hazards Analysis including Hazard Category II nuclear facilities
preliminary design basis accidents
hazard categorization
Initial selection of facility level safety class and safety significant systems
Identification of initial safety functions
Identification of design criteria for safety related SSCs
facility design descriptions
system design descriptions
steps to be taken during the execution phase to develop a draft preliminary
documented safety analysis to support approval of the performance baseline
Facility Siting Determination
Hazardous-material Inventory and Characterization
Preliminary Defense in Depth
Acquisition Strategy
assessment of alternatives - definition and evaluation including life cycle cost
results of survey to determine current state-of-the-art for project
results of bench marking of similar projects
PED funding Execution Plan
RFQ/RFP/contracting strategy -
(design-build versus design-bid-build decision analysis vs Construction Management
process)
Preliminary Acquisition Plan
Resource Capability
Assessment of site/Project and Program team personnel capabilities in project specific
technologies
NNSA ESAAB EQUIVALENT PROCESS
NNSA 31
July 2006
plans to obtain necessary project capabilities
Risks
risk assessment
basis for risk assessment
mitigation strategies
contingency analysis
Cost and Schedule
preliminary TEC & TPC
detailed cost estimate
funding profile
mortgage analysis (capital and operating)
facility operating costs
fiscal year funding start
preliminary project schedule including critical path analysis
project milestones
Project Management
approved preliminary Project Execution Plan
project data sheet (CPDS for PED funding to be approved, TEC/TPC Range number)
assignment of COTR responsibility
Federal Project Acquisition Team status (part of PEP -changes in personnel that must be
approved by AE
program manager
project manager
safety
environmental and health
legal
contracting officer
public outreach
maintenance
operations
Identify past reviews to date
Is EIR complete or was a favorable internal non-advocate review complete and EIR
scheduled?
Status of correction action plan items.
Section 19
Environmental
preliminary NEPA assessment/status/issues
permitting requirements
pollution prevention plans
waste minimization plans
other expected environmental issues
local outreach input/results
Sustainable Design features per DOE Order 430.2A
Energy Conservation Report (ECR) submitted per DOE Order 430.2A
Security
security determination from review of Site Safeguards & Security Plan
completed security assessments to include vulnerability assessments
Legal
determination on contracting strategy
local agreements review results
preliminary NEPA assessment
NNSA ESAAB EQUIVALENT PROCESS
NNSA 32
July 2006
permitting requirements
Organizational Interfaces
Involvement of related agencies - schedule integration of stakeholders - DNFSB, NEPA, etc.
State and regulatory agency agreements
cooperation/collaboration agreements with agencies
internal agreements documented and in place.
Report of Lessons Learned & benchmark addressed by IPT
Identify all assumptions
NNSA ESAAB EQUIVALENT PROCESS
NNSA 33
July 2006
CRITICAL DECISION 2 (CD-2) - APPROVE PERFORMANCE BASELINE
A. Required Information:
The following is the List of Critical Decision Prerequisites from the DOE Order 413.3 and DOE
Manual 413.3-1. This list is subject to change and will be updated when there are changes to the
Order:
Project Execution Plan
Performance Baseline (i.e., scope, cost, schedule, risk mitigation, etc.)
Cost Estimate, including documentation on the basis and assumptions
Performance Baseline Validation Review results including Corrective Action Plans
Performance Baseline Validation Letter
Independent Cost Estimate or Independent Cost Review (when required)
Quality Assurance Program documentation
Updated Project Data Sheet
Design Review results
Preliminary Safety Design Report (when required)
Approved Hazard Analysis Report
Updated Security Vulnerability Assessment Report
Safety Evaluation Report (when required)
Evidence of incorporating Sustainable Environmental Stewardship – High
Performance Sustainable Building provisions
Final NEPA documentation
Presentation
B. Suggested Project Preparation Topics for Critical Decisions
The following list provides a general outline for construction scope, cost, schedule, management,
and other project related topics that a project requesting CD-2, Approve Performance Baseline,
typically will have investigated prior to the decision. As part of the project development process,
field and IPT members document results from the investigation of these topics. The depth and
breadth of the effort in addressing these project development topics would be scaled, based upon
the cost, complexity, and risks of the project. For example, not all projects will be required to
follow the formal Safety Analysis Report process, but all projects should perform a hazards
analysis.
For nuclear related projects, to ensure that nuclear safety is appropriately integrated into design,
those nuclear safety related expectations that should be considered as mandatory are identified
in bold.
This list is offered as an aid in preparing for a CD-2. DOE project lessons learned and Project
Management studies have shown that "projects fail not because they planned to fail, but because
they have failed to plan". The listing is an attempt to capture the important issues/topics that
typically have caused NNSA projects problems in the past.
Note: The following lists of topics will be merged with the list of recommended review topics/lines
of inquiry in the Independent Project Review Plan.
Section 20
Statement of Mission Need
affirm mission need of program
mission need date for project
impact of not meeting date
construction schedule for meeting date
NNSA ESAAB EQUIVALENT PROCESS
NNSA 34
July 2006
Brief Description
location
purpose & function
features
long term goals
System Design Descriptions (SDD)
Technical/Functional Requirements
results of Title I design review
If nuclear facility, have NRC standards been appropriately addressed in Title I?
incorporation of technical performance objectives and interfaces in design
value engineering results and incorporation of design
availability of special systems/equipment
reliability of systems as relates to facility usability
integration with other project activities
design control process
completed design criteria
confirm lessons learned incorporated into design
confirm Quality included in design
value engineering results
system design descriptions
decommissioning considerations
Safety, including Nuclear Safety
Draft Preliminary Documented Safety Analysis (PDSA) (focus on Chapter 1 thru 4)
including final facility hazard category, hazard and accident analysis, identification
of safety class and safety significant SSCs, and safety SSC functional
requirements
safety SSC functional requirements
Facility Design Description chapter 1 - 3
System Design Description chapter 1 – 3, summarizing design requirements for all
safety SSCs.
Fire Hazard Analysis
Defense in depth & worker protection design criteria
Preliminary Technical Safety requirements.
steps to be taken during the execution phase to develop a final preliminary
documented safety analysis to support approval of the start of construction
Acquisition Strategy
Long lead/special equipment procurement strategies/plans/contracts
RFP/contracting strategy for construction
updated Acquisition Plan
RFP approval along with CD-3 request for design build
Assessment of pre-CD2 performance
impact of Critical Decision delay
Risks
risk assessment - update
basis for risk assessment
mitigation strategies - update
contingency analysis - revised
Cost and Schedule
performance baseline detailed cost estimate, TEC, & TPC
updated funding profile & mortgage analysis (capital and operating)
NNSA ESAAB EQUIVALENT PROCESS
NNSA 35
July 2006
facility operating costs analysis
performance baseline project schedule including critical path analysis
project milestones
Project Management
approved updated Project Execution Plan
updated project data sheet
results of External and Non-advocate reviews
results of ICE
Federal Project Acquisition Team (part of PEP)
confirm in place ID any changes - AE approve changes for key positions
program manager
project manager
safety
environmental and health
legal
contracts
public outreach
maintenance
operations
Status of correction action plan items
Identify past reviews to date
Environmental
Final NEPA determination
permitting arrangements
pollution prevention ideas incorporated into design
waste minimization ideas incorporated into design
local outreach input/results
ID waste sites incorporated in design
Sustainable Design strategies executed as planned
Security
security determination from review of Site Safeguards & Security Plan/results of security
vulnerability assessments
incorporation of specific security design criteria
Legal
contracting strategy
NEPA determination
permitting arrangements
Organizational Interfaces
Section 21
Involvement of related agencies - revised schedule for stakeholders interface
State and regulatory agency agreements
cooperation/collaboration agreements with agencies
internal MOUs in place
look at CD 0(zero)/comments
identify all assumptions
NNSA ESAAB EQUIVALENT PROCESS
NNSA 36
July 2006
CRITICAL DECISION 3 (CD-3) - APPROVE START OF CONSTRUCTION
A. Required Information:
The following is the List of Critical Decision Prerequisites from the DOE Order 413.3 and DOE
Manual 413.3-1. This list is subject to change and will be updated when there are changes to
the Order:
Design Review results from final design review
Approved Preliminary Safety Analysis Report and DOE Safety Evaluation Report
Updated Project Execution Plan and Performance Baseline
Execution Readiness External Independent Review Results for Major Systems
Preliminary Documented Safety Analysis Report (when required)
Updated Hazards Analysis Report
Updated Security Vulnerability Assessment Report
Safety Evaluation Report
Approved Construction Project safety and Health Plan
Evidence of incorporating Sustainable Environmental Stewardship – High
Performance Sustainable Building provisions
Updated Quality Assurance Program
Project Data Sheet
Presentation
B. Suggested Project Preparation Topics for Critical Decisions
The following list provides a general outline for construction scope, cost, schedule, management,
and other project related topics that a project requesting CD-3, Approve Start of Construction or
Remedial Action, typically will have investigated prior to the decision. As part of the project
development process, field and IPT members document results from the investigation of these
topics. The depth and breadth of the effort in addressing these project development topics would
be scaled, based upon the cost, complexity, and risks of the project. For example, not all projects
will be required to follow the formal Safety Analysis Report process, but all projects should
perform a hazards analysis.
For nuclear related projects, to ensure that nuclear safety is appropriately integrated into design,
those nuclear safety related expectations that should be considered as mandatory are identified
in bold.
This list is offered as an aid in preparing for a CD-3. DOE project lessons learned and Project
Management studies have shown that "projects fail not because they planned to fail, but because
they have failed to plan". The listing is an attempt to capture the important issues/topics that
typically have caused NNSA projects problems in the past.
Note: The following lists of topics will be merged with the list of recommended review topics/lines
of inquiry in the Independent Project Review Plan.
Statement of Mission Need
affirm mission need of program
mission need date for project
construction schedule for meeting date
Brief Description
location
purpose & function
features
NNSA ESAAB EQUIVALENT PROCESS
NNSA 37
July 2006
long term goals
final design plans
Technical/Functional Requirements
results of Title II design review
incorporation of technical performance objectives and interfaces in design assurance
If nuclear facility, have appropriate NRC standards been incorporated in Title II design?
assurance of compliance with codes and standards/quality assurance review results
systems designs as relates to facility reliability/usability
integration with other project activities
configuration management process operating
confirm quality incorporated in design
Safety
Section 22
Final Preliminary Documented Safety Analysis (PDSA)
DOE PDSA Safety Evaluation Report
Facility Design Description complete
System Design Description complete
ES&H integration in project execution
safety orders and regulations compliance assured
OSHA Safety plan in place
Final drawings, specifications, and supporting analysis for safety related
Structures, Systems, Components
steps to be taken during the construction phase to develop a final documented
safety analysis to support approval of the start of operations
Acquisition Strategy
long lead/special equipment procurement status
RFP/contracting strategy for construction - design build combine with CD-2
final Acquisition Plan
U.S. vendor participation/completed all foreign ownership determinations
Assessment of pre-CD#3 performance
Impact of Critical Decision delay
Risks
updated risk assessment
mitigation strategies
contingency status
Cost and Schedule
cost and schedule status of design effort – including earned value analysis
updated performance baseline detailed cost estimate, TEC, & TPC
updated funding profile & mortgage analysis (capital and operating)
facility operating costs
updated performance baseline detailed project schedule (resource-loaded with critical
path analysis)
project milestones
project control systems in place and operating
review of CD-2 comments
Project Management
approved final Project Execution Plan
updated project data sheet
project controls, scheduling, configuration management, reporting and change control
procedures
project completion plan approved - transition plan and budget
NNSA ESAAB EQUIVALENT PROCESS
NNSA 38
July 2006
outyear operating funds included in planning budgets - operation, maintenance, security
Federal Project Acquisition Team (part of PEP)
program manager
project manager
safety
environmental and health
legal
contracts
public outreach
maintenance
operations
status of corrective action plan items
identify past reviews to date
Environmental
Final NEPA determination approved
permitting arrangements complete
pollution prevention ideas incorporated into design
waste minimization ideas incorporated into design
local outreach input/results
Security
security determination from review of Site Safeguards & Security Plan
incorporation of specific security needs in design
security plan for construction, to include escorts for construction (if necessary) funded
and available
coordination of construction activities with security organization
Legal
contracting strategy
RFP process and contract award - combine with CD-2 for design build
NEPA determination
permitting arrangements
Organizational Interfaces
Involvement of related agencies - results of safety stakeholder reviews - DNFSB other
State and regulatory agency agreements
cooperation/collaboration agreements with agencies
internal agreements status
identify all assumptions
NNSA ESAAB EQUIVALENT PROCESS
NNSA 39
July 2006
CRITICAL DECISION 4 (CD-4) - APPROVE START OF OPERATIONS OR PROJECT CLOSEOUT
A. Required Information:
The following is the List of Critical Decision Prerequisites from the DOE Order 413.3 and DOE
Manual 413.3-1. This list is subject to change and will be updated when there are changes to the
Order:
Verification of Key Performance Parameters or Project Completion Criteria
Completed Operational Readiness Review or Readiness Assessment
Checkout, Testing and Commissioning Plan
Project Transition to Operations Plan
Updated Quality Assurance Plan
Revised environmental management system
Documented Safety Analysis Report
Section 23
with Technical Safety Requirements (when required)
Updated Construction Project safety and Health Plan
Approved Final Hazards Analysis Report
Final Security Vulnerability Assessment Report
Safety Evaluation Report (when required)
Presentation
B. Suggested Project Preparation Topics for Critical Decisions
The following list provides a general outline for construction scope, cost, schedule, management,
and other project related topics that a project requesting CD-4, Approve Start of Operations or
Project Closeout, typically will have investigated prior to the decision. As part of the project
development process, field and IPT members document results from the investigation of these
topics. The depth and breadth of the effort in addressing these project development topics would
be scaled, based upon the cost, complexity, and risks of the project. For example, not all projects
will be required to follow the formal Safety Analysis Report process, but all projects should
perform a hazards analysis.
For nuclear related projects, to ensure that nuclear safety is appropriately integrated into design,
those nuclear safety related expectations that should be considered as mandatory are identified
in bold.
This list is offered as an aid in preparing for a CD-4. DOE project lessons learned and Project
Management studies have shown that "projects fail not because they planned to fail, but because
they have failed to plan". The listing is an attempt to capture the important issues/topics that
typically have caused NNSA projects problems in the past.
Note: The following lists of topics will be merged with the list of recommended review topics/lines
of inquiry in the Independent Project Review Plan.
Statement of Mission Need
has mission need been met – validation document
Brief Description
location
purpose & function
features
long term goals
Project Management
staff reduction plan
NNSA ESAAB EQUIVALENT PROCESS
NNSA 40
July 2006
project completion plan
transition plan complete
operating funds in place
Federal Project Acquisition Team - plan for continued operation of team or dissolution of
team in place.
Technical/Functional Requirements
ORR has been completed
has project validated functional requirements been met?/design criteria
were authorized technical performance objectives as stated in the design met?
was the project fully integrated with the site/systems as proposed?
operations and maintenance plan is prepared/approved
facility staff trained in the maintenance and operation of the facility/systems
facility staffing plans implemented
Safety, including Nuclear Safety
construction changes have been analyzed for effect on safety
safety component specifications are written
System Design Descriptions (SDD) are complete and approved
Facility Design Descriptions (FDD) updated as needed and approved
DSA is complete and approved
DSA SER issued
as-builts control safety features
ES&H program plan has been reviewed and revised as necessary
OSHA compliance plan in place for operations
Configuration Management
as-built drawings and documents reflect facility as completed
configuration management plan is complete and approved
configuration management documentation integrated into operations/maintenance/safety.
Acquisition Strategy
status of construction contracts - closeout
outstanding claims processed
Risks - contingency status - plan against outstanding project issues
Cost and Schedule
status of funds
expected closeout of project - report
Section 24
schedule status
documented lessons learned
“as builts” complete?
Environmental Status
Have applicable permits, licenses, and regulatory approvals been obtained?
pollution prevention plans or strategies executed as planned
waste minimization efforts completed
have stakeholders concerns been fully addressed?
Have project benefits been fully documented in public participation plans or documents?
Security
security requirements as stated in the DOE orders have been met
project integrated into Site Safeguards & Security Plan
security systems physically integrated into site security systems
facility specific security training and procedures are in place
NNSA ESAAB EQUIVALENT PROCESS
NNSA 41
July 2006
appropriate protective force is in place
Legal
outstanding claims against project identified and plan to resolve addressed
local agreements have been satisfied
NEPA and permitting complete
NNSA ESAAB EQUIVALENT PROCESS
NNSA 42
July 2006
Demolition and Disposal
D&D plan is complete and approved
agreements/contracts in place for construction/demolition debris disposal
Organizational Interfaces
Involvement of related agencies
compliance with state and regulatory agency agreements
cooperation/collaboration processes/procedures in place with agencies
Evaluate appropriateness of initial assumptions.
NNSA ESAAB EQUIVALENT PROCESS
NNSA 43
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
ATTACHMENT 4 - ESAAB EQUIVALENT PRESENTATION OUTLINE
NNSA ESA
NNSA 44
July 2006
NATIONAL NUCLEAR SECURITY ADMINISTRATION
ESAAB EQUIVALENT PROCESS
ATTACHMENT 4- ESAAB EQUIVALENT PRESENTATION OUTLINE
What follows is a proposed outline of an ESAAB Equivalent presentation:
• What decision is being requested from the ESAAB Equivalent AE
(1 slide)
• Extremely brief Project Overview (i.e. mission and project description)
(1 –2 slides )
• Evidence of compliance with programmatic, safety, environmental, security, legal,
procurement, and departmental requirements
(1-3 slides)
• Evidence of the integration of above requirements into the design and execution of
the project
(1-3 slides)
• Changes to project status and resolution of prior issues since last ESAAB Equivalent
Meeting
(1-2 slides)
What progress has been made on the project since the last ESAAB Equivalent
meeting – including progress on Corrective Action Plans and resolution of other
issues
• Brief summary of results of ESAAB Equivalent member staff review
(1-2 slides)
Summarize results of ESAAB Equivalent discussions, issue resolution, and
corrective action plan
• Specific Issues that require AE action
(1 slide)
Federal Project Director and Program Office will work with board members to
prepare specific major issues for presentation to AE, in advance of the ESAAB
for presentation and discussion. This should be reserved for issues that have
significant programmatic implications.
• Decision Approval Summary
(1 slide)
Summary of presentation and requested decision
Project request for
critical decision
or BCP approval
NA-54 coordinates
Pre-ESAAB
Equivalent Meetings
Supporting documentation
distributed to ESAAB Eq.
staff for review
Pre-ESAAB
Equivalent
meeting
Action items/
review issues given
to project team
Project team
resolves action
items/ issues
Updated project
documentation distributed
to ESAAB Eq. board
ESAAB Eq. meeting
with Acquisition
Executive
Decision
approved?
Decision memorandum
approved and forwarded
to site and project director
Action items/
review issues given
to project team
Project team
resolves action
items/ issues
ESAAB Equivalent Process Flow
YES
NO