BOP-50.001A, Energy System Acquisition Advisory Board (ESAAB) Equivalent Process
This document specifies the procedures that shall be followed by Program Offices (POs) with regard to the DOE ESAAB and the NNSA ESAAB Equivalent (ESAAB-E) processes. NNSA Site Offices will develop and implement procedures that will govern Field ESAAB Equivalent processes.
Cancels BOP-50.001, National Nuclear Security Administration Energy Systems Acquisition Advisory Board Equivalent Process, dated 8-7-06.
Associated DOE Directive:
Version history and related documents
Supersedes
Earlier documents this one replaced.
- BOP-50.001NNSA ESAAB Equivalent Process (Jan 28, 2011)
Related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
AVAILABLE ONLINE AT: INITIATED BY:
http://hq.na.gov Office of Enterprise Project Management
BUSINESS OPERATING PROCEDURE
Approved: 07-28-11
Energy System Acquisition Advisory Board
(ESAAB) Equivalent Process
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Office of Acquisition and Project Management
BOP-50.001A
BOP-50.001A 1
07-28-11
Energy System Acquisition Advisory Board (ESAAB) Equivalent Process
1. PURPOSE.
a. This Business Operating Procedure (BOP) reflects the National Nuclear Security
Administration (NNSA) current requirements, understandings, and expectations
relating to the implementation of the Energy Systems Acquisition Advisory Board
(ESAAB) process as specified in the current version of Department of Energy
(DOE) Order (O) 413.3B, Program and Project Management for the Acquisition
of Capital Assets. It covers both the NNSA ESAAB Equivalent process and the
DOE ESAAB process up to and through the Preparatory (Pre) ESAAB, after
which point the DOE Office of Engineering and Construction Management
(OECM) acquires the Departmental ESAAB process lead for Major System
projects.
b. This document specifies the procedures that shall be followed by Program Offices
(POs) with regard to the DOE ESAAB and the NNSA ESAAB Equivalent
(ESAAB-E) processes. NNSA Site Offices will develop and implement
procedures that will govern Field ESAAB Equivalent processes. These
procedures are to meet the ESAAB requirements in DOE O 413.3B, and the
supporting expectations in the related guides under the DOE G 413.3-XX series.
c. This document provides assurance for:
(1) Line management involvement and accountability for project
performance,
(2) Acquisition Executive (AE) oversight to the NNSA acquisition process for
construction projects greater than $50 million, and
(3) Effective integration of safety and project management practices as early
in the project as is practicable.
2. CANCELLATION. BOP-50.001, National Nuclear Security Administration Energy
Systems Acquisition Advisory Board Equivalent Process, dated August 7, 2006.
3. APPLICABILITY.
a. NNSA Applicability. The requirements identified in this BOP are mandatory for
all NNSA Elements (unless identified in the exclusions paragraph), for all capital
asset acquisition projects having a Total Project Cost greater than or equal to $50
Million. The principles as set forth in this BOP apply to all projects with a Total
Project Cost greater than or equal to $5 Million.
2 BOP-50.001A
07-28-11
(1) While all requirements are to be addressed, the approach to meeting the
requirements should be tailored consistent with the risk, complexity,
visibility, cost, safety, security, and schedule of the project.
(2) Projects meeting certain criteria may request, at Critical Decision (CD)-1,
that the AE authority for all future CDs be delegated to the Site Office.
The AE determines whether or not to approve this delegation. Projects of
low risk, low monetary value and that are non-controversial (e.g. simple
civil projects) may request a CD-0/CD-1 approval from the AE. These
projects must have an assigned Federal Project Director (FPD), a
developed cost range with life cycle cost, an alternative analysis and a
Project Execution Plan (PEP) with the project strategy and a tailoring plan
at the time of the CD-0/CD-1 ESAAB-E. The PEP should adequately
describe the strategy for project reporting and project reviews. Projects
Section 2
requesting a combined CD-0/CD-1 may request AE delegation at the
ESAAB-E. In order to qualify to make this request, projects must meet
the following minimum requirements:
Top-end of the CD-1 estimated cost range has a Total Project Cost
(TPC) less than $100M.
Project is not a major modification to or a new Hazard category 1,
2 or 3 nuclear facility.
Project can reasonably be classified as a low-risk, non-
controversial project.
Site must demonstrate a favorable track record for the successful
completion of projects of similar size and complexity.
(3) Whether or not authority is delegated, all projects must follow the
mandatory requirements included in DOE O 413.3B. The PEP will
address the tailoring of the IPR, project reporting and yearly Peer reviews
to meet the objectives of DOE O 413.3B. In addition, CD, BCP, IPR and
Quarterly Project Review (QPR) documentation will be readily available
to the Office of Enterprise Project Management (NA-APM-20). For CDs
for which AE authority has been delegated to the site, Site Office specific
ESAAB Equivalent procedures shall be followed.
(4) NNSA Major System (MS) projects may incur Level 1 Baseline Change
Proposals (BCP) requiring disposition at the NNSA Program Office (PO)
level (i.e. at a level between the SAE and project‘s FPD level). In these
situations, the MS project can utilize the NNSA ESAAB Equivalent
review process, or utilize any PO established Level 1 Change Control
Board (CCB) for the BCP review for approval. These PO-established
Level 1 CCB‘s should be supplemented with other disciplines from the
BOP-50.001A 3
07-28-11
NNSA ESAAB Equivalent Board (i.e. Nuclear Safety, General Counsel,
Procurement, etc.) to meet the DOE O 413.3B review requirements.
b. Exclusions.
(1) Financial Assistance awards (grants and cooperative agreements) are
excluded, which are covered under 10 CFR 600.
(2) Alternative finance projects post-CD-1.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 USC sections 2406, 2511 and to ensure
consistency throughout the joint Navy/DOE Naval Nuclear Propulsion Program,
the Deputy Administrator for Naval Reactors (Director) will implement and
oversee requirements and practices pertaining to this Directive for activities under
the Director's cognizance, as deemed appropriate.
4. BACKGROUND. As DOE projects proceed from concept through design, construction,
and eventually start of operations, DOE O 413.3B requires that at the end of each phase
for subject projects, the AE approve the project‘s continuation into the next phase. These
approval points in the acquisition process are named ‗Critical Decisions‘. The Critical
Decision (CD) authority resides with the Secretarial Acquisition Executive (SAE) for
Major Systems (MS) projects and with an AE (Program Secretarial Officer or designated
PO AE) for non-Major Systems projects. In addition to CDs, Level 0 Baseline Change
Proposals (BCPs) and Level 1 BCPs are also subject to decision review for approval by
the SAE and by the AE for MS projects and Non-MS projects, respectively. ESAABs
and PO (i.e. NNSA ESAAB-Equivalent) Acquisition Advisory Boards are required by
DOE O 413.3B to advise the AE‘s on the CDs and BCPs that are presented before them
for disposition.
5. REQUIREMENTS.
a. Integration of Safety in Design: Hazard Category 1, 2, and 3 nuclear projects are
Section 3
required to follow DOE Standard 1189-2008, Integration of Safety into the Design
Process and DOE O 420.1B, Facility Safety. At Critical Decision points, the
ESAAB process ensures that the projects and their documentation address, at a
minimum, the safety requirements included in these policies.
b. Scheduling and Coordination.
(1) The FPD, with the concurrence of the PO, will request an ESAAB or an
ESAAB Equivalent Board review for the approval of a CD or a BCP.
This ESAAB Equivalent Board request will follow the format in
Attachment 2 and be forwarded to the NNSA ESAAB Equivalent
Secretariat (NA-APM-20) a minimum of three weeks
1
before the
requested NNSA ESAAB Equivalent Board review: Note that 1 month is
recommended to adequately allow for resolution of any ESAAB-
Equivalent related issues.
4 BOP-50.001A
07-28-11
1
A three week minimum lead time is required prior to an ESAAB
Equivalent review in that a week and a half is needed before the
Preparatory (Pre-) ESAAB Equivalent review for members to review the
source materials and prepare questions for the Pre ESAAB review. In
addition, an absolute minimum of one week (and often two weeks) is
necessary between the Pre ESAAB Equivalent and the ESAAB Equivalent
Board meeting to resolve any questions and issues arising from the Pre
ESAAB and for the project/program to Pre-Brief the Acquisition
Executive on the upcoming ESAAB. These time frames demand a three-
week lead time before the actual ESAAB Equivalent Board event for the
submission of the project‘s ESAAB Equivalent request.
(2) For a full DOE ESAAB Board review request, allow a minimum of six
weeks: Note that an eight week lead-time is often required. Full
Departmental ESAAB Board Reviews are presided by the Secretarial
Acquisition Executive (SAE) (i.e. the Deputy Secretary of Energy) and the
ESAAB Board Review meeting itself is only scheduled after a Pre-
ESAAB is conducted by NNSA to determine the merits and the readiness
of the ESAAB request to proceed. The DOE Office of Engineering and
Construction Management (OECM) is the Departmental ESAAB
Secretariat, and as a participant of the NNSA Pre-ESAAB review session,
makes this determination regarding the merits/readiness of the subject CD
or BCP action to proceed forward in the ESAAB review process.
(3) To support both the DOE ESAAB and NNSA ESAAB Equivalent process,
a Pre ESAAB / ESAAB-E review meeting must be scheduled. An
absolute minimum of one week is required before the Pre-ESAAB event
for the review members to be able to review the project‘s ESAAB
materials and to prepare questions for the Pre ESAAB meeting.
(4) A complete set of ESAAB / ESAAB-E review materials must be
submitted to the NNSA ESAAB Equivalent Secretariat for distribution at
least one week prior to the Pre-ESAAB Equivalent review meeting.
(5) For an NNSA level ESAAB Equivalent Board review, the NA-APM-20
ESAAB Equivalent Secretariat will coordinate with the AE for scheduling
the ESAAB-Equivalent board meeting.
c. Review and Comment Resolution
(1) The major facet of the NNSA ESAAB Equivalent process is the review
and comment resolution phase. In this phase the ESAAB Equivalent
members evaluate the project request and formulate their comments,
issues, and recommendations. The goals of this phase are to:
Assure that the project is in compliance with programmatic, safety,
environmental; security, legal, procurement, and departmental
requirements;
Section 4
BOP-50.001A 5
07-28-11
Assure that those requirements have been integrated into the
design and execution of the project;
Resolve, prior to the ESAAB Equivalent meeting with the AE, as
many of the comments and the issues as possible that were raised
in the Pre-ESAAB Equivalent process; and
Identify unresolved comments and issues that will need to be
raised to the ESAAB Equivalent Board for decision.
(2) The materials provided will be the requested action documents (i.e. CD
request or BCP), results from any external and/or internal reviews since
the last ESAAB Equivalent meeting, Corrective Action Plans, and other
materials that support the proposed decision or BCP.
(3) Attachment 3 refers to the required review materials for CDs 0 through 4
which are listed in Table 2, CD Requirements, in DOE O 413.3B, and on
the NA-APM-20 website (http://hq.na.gov/pmnet). Suggested project
preparation topics for CDs are also available on the NA-APM-20 website.
(4) The board members and the Secretariat (see Attachment 1) will examine
the project materials and provide directed questions/comments to the FPD
and PO. Board members evaluations should identify project inadequacies,
with emphasis on the following:
Areas where the project is not in compliance with programmatic,
safety, environmental, security, legal, procurement, and
departmental requirements or where requirements have not been
addressed.
Areas where the project has not demonstrated that the requirements
have been integrated into the design and execution of the project.
Items to be corrected to support project success.
Critical findings with supporting documentation that includes cost
or other impacts that are a result of any associated
recommendations or project reviews.
Recommendations whether or not the project should proceed, and
any additional requirements needed as conditions to proceed.
d. Preparatory (Pre) ESAAB Equivalent Review meeting.
(1) For both the DOE ESAAB process for MS projects and for the NNSA
ESAAB Equivalent process for non-MS projects, a Preparatory (Pre)
ESAAB or ESAAB-E review meeting will be held to identify issues of
concerns and areas needing additional information or action, prior to
conducting the ESAAB or ESAAB-E Board review.
(2) For non-MS projects, these Pre-ESAAB review meetings will be staffed
with representatives of the NNSA ESAAB Equivalent Board.
http://hq.na.gov/pmnet
6 BOP-50.001A
07-28-11
(3) For MS projects, the staff members of the DOE ESAAB Board will be
invited to participate in a combined Pre-ESAAB Review meeting. In
particular, OECM as the ESAAB secretariat must be in attendance and its
presence may affect the timing and scheduling availability of this Pre-
ESAAB meeting.
(4) A conference call will be held with the FPD, the other Integrated Project
Team (IPT) members in the field, PO, Board staff, and the Secretariat, to:
Review the project‘s ESAAB-Equivalent request and supporting
documentation,
Discuss the comments/questions of the board members, and
Set a schedule for resolving the outstanding issues/requirements.
(5) The Pre-ESAAB review will be recorded. The NNSA ESAAB Secretariat
will generate draft meeting minutes from notes and the recording. These
minutes will identify any Action Items resulting from the review and
comment process.
(6) The FPD and PO will work with the board members and their staffs to
answer inquiries and resolve issues prior to the formal ESAAB Equivalent
Section 5
Board meeting.
e. NNSA ―Paper/Tailored ESAAB-E‖ Option.
(1) A ―Paper‖ ESAAB is a tailored approach to streamlining the ESAAB
process for projects that are low risk, low monetary value and non-
controversial. Under DOE O 413.3B, the role of the ESAAB is to advise
the AE; however, in some cases, this advice can be provided without
holding a formal meeting of the ESAAB. In certain circumstances for low
risk, low monetary value and non-controversial ESAABs, the ―Paper‖
ESAAB is a more efficient and effective path to achieve the required
coordination and approval without convening a formal meeting of all
ESAAB members.
(2) For SAE ESAABS:
All issues that are Program-specific, are non-controversial, and can
be resolved with the SAE without convening a formal ESAAB;
The PO requests that OECM conduct a ―paper‖ ESAAB in lieu of
a formal ESAAB;
OECM has determined that a ―Paper‖ ESAAB is appropriate and
which offices to coordinate action.
At a minimum, all ―Paper‖ ESAABs will be coordinated with the
Chief Financial Officer and the Office of General Counsel with the
expectation of expeditious concurrences.
BOP-50.001A 7
07-28-11
(3) For NA-1 ESAABS for non-controversial decisions where the NNSA
Administrator is the AE, a ―Paper/Tailored‖ ESAAB-E allows for a
smaller, core group of ESSAB-E members to meet with the NNSA
Administrator.
(4) The NNSA ―Paper/Tailored‖ ESAAB Equivalent process utilizes the Pre-
ESAAB Equivalent Review meeting to identify issues and confirm that:
Any issues that are Program-specific, are non-controversial, and
can be resolved with the AE without convening a formal ESAAB-
Equivalent;
The NA-APM-20 ESAAB-Equivalent Secretariat will determine if
the ―Paper‖ ESAAB Equivalent process is appropriate and which
offices to coordinate the action.
(5) After the Pre-ESAAB Equivalent, the ―Paper/Tailored‖ ESAAB
Equivalent process can be concluded with a short meeting with the AE
that includes relevant parties, instead of a holding a full ESAAB
Equivalent Board review. This path may include multiple meetings with
the AE, such as an initial to discuss the remaining issues and a final
meeting to resolve those issues.
(6) Alternatively, the ―Paper/Tailored‖ ESAAB Equivalent process can also
proceed to conclusion through the paper correspondence process, with the
preparation of a Decision Memorandum package with supporting
documents that is routed through relevant parties for concurrence and then
onto the AE for final approval determination. Throughout this ―Paper‖
ESAAB process, the NNSA ESAAB Equivalent Secretariat is to be the
active center-point and is to oversee the process between involved parties:
1) the project/program area, 2) the ESAAB-Equivalent Board members,
and 3) the AE. It is incumbent upon the project/program to keep the
NNSA ESAAB Equivalent Secretariat fully apprised of related actions.
f. Pre-Briefings to the Acquisition Executive.
(1) The purpose of the Pre-Brief is to prepare the SAE/AE for the upcoming
ESAAB / ESAAB-E Board Meeting. If the NA-APM- Associate
Administrator is the AE, then a Pre-Brief is mandatory. This Pre-Brief is
the responsibility of the PO. The PO is to make the scheduling
arrangements with the AE for this briefing and is to invite the NNSA
ESAAB Secretariat. It is recommended that the PO schedule the Pre-Brief
to the AE approximately 1 week before the ESAAB Equivalent review. At
the discretion of the AE, additional project and program representatives
Section 6
may be required at this briefing, including additional ESAAB Equivalent
board members. The PO shall present the project status and issues, and
obtain additional feedback on the presentation prior to the ESAAB
Equivalent Board meeting.
8 BOP-50.001A
07-28-11
(2) The NNSA Administrator is a senior member of the ESAAB board and the
NA-APM Associate Administrator serves as a back-up to the NNSA
Administrator in this ESAAB Board position. Given other potential last-
minute conflicts on the Administrator‘s schedule, it is important to have
the NA-APM Associate Administrator well informed, along with the
NNSA ESAAB Equivalent Secretariat, to ensure adequate ESAAB
representation. For a Departmental ESAAB of an NNSA project, an
initial Pre-Brief by the PO is required for the NNSA Administrator. NA-
APM and NA-APM-20 (and CDNS for nuclear projects) are required
attendees of the Administrator Pre-Brief. This Pre-Brief should be
scheduled approximately one week before the ESAAB, and not less than
three days before, to allow for any additional coordination or any potential
Action Items that may be necessary. The Pre-Brief presentation materials
must be provided to the NNSA ESAAB Equivalent Secretariat two days
prior to the Pre-Brief.
(3) For a non-NNSA ESAAB, the NNSA ESAAB Secretariat will pre-brief
NA-APM who in turn will brief the NNSA Administrator.
(4) Additional Pre-Briefs along the project or program‘s chain of command
will be the responsibility of the subject PO. Again, invitations to the
NNSA ESAAB Equivalent Secretariat must occur.
g. Preparation of the Decision Memorandum by the NNSA Program Office (PO).
(1) After the Pre-ESAAB, the PO is to prepare a Decision Memorandum for
the AE to sign at the ESAAB-Equivalent Board meeting. The Decision
Memorandum is to describe the decision requested and incorporate the key
information associated with the CD or the BCP. Specifically:
For CD-0, Statement of Mission Need
For CD-1, the Alternative Selected, the Cost Range and the FPD
appointment.
For CD-0/CD-1, Statement of Mission Need, the Alternative
Selected, the Cost Range, the FPD appointment and the Tailoring
Strategy.
For CD-2, the Performance Baseline or Cost and Schedule
Baseline addressing the Total Project Costs (TPC) including the
portion that is the Total Estimated Cost (TEC), the CD-4
completion date, the amount of contingency (cost and schedule),
the amount of management reserve, and Key Performance
Parameters.
For CD-4, the CD-4 document shall state whether the project has
met all key performance parameters (and what they are) and the
approved CD-4 date and TPC. The CD-4 document should also
state and discuss if there are any known outstanding liabilities that
BOP-50.001A 9
07-28-11
could affect the project's TPC after the approved CD-4 date such as
contractor claims, etc.
(2) Examples of Decision Memorandum are provided in Attachment 2.
(3) If the modifications are substantial, the PO can utilize the ESAAB-E
meeting minutes, prepared by the ESAAB-Equivalent Secretariat, as a
material source for the modifications to the DM. The ESAAB-Equivalent
Secretariat can assist the PO in identifying the core relevant parties that
should be included in the DM prior to its submission to the AE for
approval (CDNS should be included for all nuclear projects). The only
required concurrence is NA-APM-20 as the ESAAB-Equivalent
Secretariat; other relevant parties may be required as directed by NA-
Section 7
APM-20. (CDNS should be included for all nuclear projects)
(4) For MS projects, the Office of Engineering and Construction Management
will prepare the decision memorandum for the Under Secretary‘s (S-2)
signature. PO, Project Team, and Secretariat will be asked for input in the
drafting of the memorandum.
h. ESAAB Equivalent Board Meetings.
(1) After the review and comment phase has been completed, the FPD and PO
will confirm their intent to continue with the ESAAB Equivalent meeting
with the Secretariat. The Secretariat will make final meeting preparations,
distribute the project presentation to the board members, and coordinate
with the FPD on any remaining issues.
(2) At the ESAAB-Equivalent meeting, the NNSA ESAAB Equivalent
Secretariat representative will make a short introductory statement for the
record as a call-to-order for the ESAAB Equivalent Board and will update
the Board on any developments that may affect the review. The
Secretariat will also record the proceedings of the meeting to support the
generation of meeting minutes. The FPD (and/or a PO member) will then
present the Board with the project to support the requested decision. The
presentation should be brief and emphasize:
Programmatic issues;
Basic overview of the project;
Actions taken to assure that the project has addressed
programmatic, safety, environmental, security, legal, procurement,
and departmental requirements;
Actions taken to assure that the requirements have been
appropriately integrated into the design and execution of the
project;
Comment / issue resolution including any Corrective Action Plan
(CAP) items from any applicable reviews such as an Independent
10 BOP-50.001A
07-28-11
Project Reviews (IPR). Note: Any unresolved issues that requires
action by the AE should be presented at this time; and
The decision that is being requested of the AE.
(3) See Attachment 4 for outline of ESAAB Equivalent presentation.
(4) During the review, comments are offered by the ESAAB equivalent Board
members or other participants. At the conclusion of the presentation, the
AE will issue a verbal determination regarding the requested decision and
the ESAAB board will adjourn.
(5) Within one week of the ESAAB Equivalent event, the Secretariat will
develop draft meeting minutes intending to capture all significant topics of
discussion, decisions, issues, and action items. These draft meeting
minutes will be distributed via email to all attendees to capture all
significant comments raised in the ESAAB-Equivalent Board meeting.
6. RESPONSIBILITIES.
a. Board Membership Areas of Expertise Requirements.
(1) The following areas of expertise must be reflected in the membership for
the NNSA ESAAB Equivalent Board. Each area of expertise must have a
designated principal board member. Line item projects below $100
million that have been delegated to Site Office Managers will be reviewed
by a similar board that constitutes the Site Office level ESAAB Equivalent
Board. (The NNSA Board membership is listed in Attachment 1).
(2) Functional areas of expertise include: Budget, Environmental, Legal,
Procurement, Project Management, Nuclear Safety, Security, and other
areas as required.
b. Acquisition Executive – Board Chair.
(1) Establishment of the AE for a particular project is based on the criteria
stated in DOE O 413.3B. If the AE authority is delegated to a Site Office
Manager, then the Site Office must implement an ‗ESAAB Equivalent
Section 8
type‘ Board to review decisions that are presented to the Site Manager.
The site board will follow the principles of DOE O 413.3B, with board
membership and processes tailored to the site and the nature of the
projects. Board membership and procedures must be validated by the
NNSA ESAAB Equivalent Secretariat, NA-APM-20. Copies of the
meeting minutes and decisions rendered must be supplied to the respective
PO and NA-APM-20 for documentation purposes.
(2) Presides over ESAAB Equivalent Board (EEB) meetings.
(3) Makes decisions on the disposition of all requested CDs and BCPs.
(4) Assures that:
BOP-50.001A 11
07-28-11
The EEB members and project team members fulfill their ESAAB
Equivalent process responsibilities,
The EEB members have taken the appropriate measures to ensure
the project is meeting the programmatic, safety, environmental,
security, legal, procurement, and departmental requirements,
These various requirements have been integrated into the design
and execution of the project, and
(5) Reviews Corrective Action Plan (CAP) reports on the project undergoing
the ESAAB / ESAAB-E review.
c. NNSA Chief of Defense Nuclear Safety (CDNS): The Chief (and staff) is
responsible for evaluating nuclear safety issues and providing expert advice to the
CTA and other senior officials. For Hazard Category 1, 2, and 3 nuclear facilities
not regulated by the Nuclear Regulatory Commission (NRC), or as requested by
the CTA or other senior officials for facilities regulated by the NRC, the Chief
shall:
(1) For Hazard Category 1, 2, and 3 nuclear projects, the NNSA Chief of
Defense Nuclear Safety will be included as a Board member providing
specific advice to the AE regarding the effectiveness of efforts to integrate
safety into design. This will normally be in the form of a written Project
Evaluation prepared by CDNS. If the CDNS cannot attend the ESAAB-E
Board meeting, he/she shall provide a representative.
(2) Ensure that Technical IPRs and IPRs, as appropriate, evaluate: 1) the
qualifications of IPT members having nuclear safety-related
responsibilities, and 2) the effective implementation of DOE-STD-1189-
2008 as applicable for design and construction of nuclear facilities.
(3) Ensure that TIPRs and IPRs evaluate the status of project planning to
achieve operational readiness. For nuclear facilities, concur on the nuclear
safety scope and breadth of TIPRs and IPRs.
(4) Provide a representative for the Pre-ESAAB Equivalent review meeting.
d. NNSA Chief Defense Nuclear Security (NA-70).
(1) For projects with significant security aspects, validate that the federal
personnel assigned to the Integrated Project Teams are appropriately
qualified and that the level of effort expected from them is appropriate. If
NA-70 cannot attend the ESAAB-E Board meeting, he/she shall provide a
representative.
(2) Required board member for projects with significant security aspect,
providing specific advice to the AE regarding the effectiveness of efforts
to integrate security into design.
12 BOP-50.001A
07-28-11
(3) For projects with significant security aspects, the NA-70 shall provide a
representative for the Pre-ESAAB Equivalent review meeting.
e. ESAAB Equivalent Board Members.
(1) NNSA ESAAB Equivalent Board members will act as subject matter
experts in the evaluation of the proposed CD or BCP to assure that NNSA
and DOE requirements are met and common construction/business
Section 9
practices are followed; and provide effective recommendations and advice
to the Acquisition Executive.
(2) Fully evaluate the project for compliance with the requirements in the
member‘s area of expertise (programmatic, safety, environmental,
security, legal, procurement, and Departmental requirements).
Provide timely review of project materials.
Prepare directed questions/comments on specific project items that
need to be resolved as part of the ESAAB / ESAAB-E process.
Substantial issues are to be coordinated with the PO and the NNSA
ESAAB Equivalent Secretariat, if possible, prior to the Pre-
ESAAB / ESAAB-E meeting.
Work to resolve issues with the program/project area keeping
ESAAB-E Secretariat informed, and as necessary, engaged.
(3) Attend all ESAAB Equivalent Board meetings or provide an alternate.
(4) Provide a representative for the member‘s area to the Preparatory (Pre)
ESAAB/ESAAB-Equivalent review meetings.
(5) Provide assurance that relevant requirements have been integrated into the
design and execution of the project.
(6) Provide recommendation(s) of disposition and/or further actions to the
Acquisition Executive.
f. NNSA Program Office (PO)
(1) Coordinates with the FPD and NNSA ESAAB Equivalent Secretariat to
manage the project through the ESAAB Equivalent process.
(2) Works with the FPD and the IPT to assure that the project is in compliance
with programmatic, safety, environmental, security, legal, procurement,
and departmental requirements and those requirements have been
integrated into the design and execution of the project.
(3) Co-signs on request for the DOE ESAAB or for the NNSA ESAAB-
Equivalent Board review submitted by the FPD. PO shall insure that all
required documents have been signed up to the level of the AE (or PSO, if
applicable) such that the approval of the applicable CD or BCP at or in
BOP-50.001A 13
07-28-11
conjunction with the ESAAB-E process constitutes approval of the
documents.
(4) Works with the FPD to prepare the project and related materials for
presentation to the board. PO is to ensure the supporting documents for
the ESAAB related action are approved at a level one office below that of
Acquisition Executive.
(5) Coordinates with FPD and NNSA ESAAB Equivalent Secretariat to
schedule meetings.
(6) Works with FPD to answer ESAAB-related inquiries/resolve issues.
(7) Before the ESAAB Equivalent Board review, it is the responsibility of the
PO to coordinate with the AE on the upcoming ESAAB-E action. This
would include performing any required Pre-brief to the Acquisition
Executive on any issues/concerns that have arisen either at the Preparatory
(Pre-) ESAAB review meeting, or otherwise related to the forthcoming
ESAAB Equivalent Board meeting. This Pre-Brief to the AE is to occur at
least two days before the ESAAB-E Board review to allow for any
required follow-up directed by the AE.
(8) Prepares the Decision Memorandum for AE signature at the ESAAB–
Equivalent Board Meeting. Also ensures that the NNSA ESAAB
Equivalent Secretariat is on distribution for the signed Decision
Memorandum for use in the NNSA ESAAB Equivalent database/library.
(9) Coordinates the Decision Memorandum with NA-APM-20 and CDNS
(where applicable) to capture action items and/or issues resulting from the
pre ESAAB and ESAAB-E. Note: For DOE ESAAB reviews the
Decision Memorandum is generated by OECM.
(10) When the FPD is not available, the PO presents the proposed CD or BCP
Section 10
to the ESAAB-E Board.
g. Federal Project Director (FPD)
(1) The FPD, as part of the IPT, will prepare the project decision packages,
coordinate project responses to board members‘ comments/questions, and
present the information to the AE and the board for consideration.
(2) Works with the IPT and PO to ensure that the project is in compliance
with programmatic, safety, environmental, security, legal, procurement,
and departmental requirements and those requirements have been
integrated into the design and execution of the project.
(3) Obtains the PO concurrence on the request for the DOE ESAAB or for the
NNSA ESAAB-Equivalent Board review.
14 BOP-50.001A
07-28-11
(4) Coordinates preparation of project documents supporting the decision
process. The FPD is to work with the PO to ensure that the supporting
documents for the ESAAB related action are approved at a level one office
below that of Acquisition Executive. (See Attachment 2)
(5) Coordinates with the PO and the NNSA ESAAB Equivalent Board
Secretariat to schedule board meeting.
(6) Prepares the Preparatory (Pre-) ESAAB Equivalent and the final ESAAB
Equivalent Board presentations.
(7) Presents proposed action at the Pre-ESAAB Equivalent review and to the
ESAAB Equivalent Board.
(8) Incorporates comments from the Pre-ESAAB review, supports the PO in
preparing the Decision Memorandum for signature by the AE at the
ESAAB Equivalent Board meeting.
(9) Works with PO and IPT to respond to ESAAB Equivalent Board
questions/requests and resolves issues.
h. NNSA ESAAB Equivalent Secretariat (NA-APM-20).
(1) The secretariat will coordinate the meetings, participate in the ESAAB
Equivalent process, advise the acquisition executive on the issues of the
project, and assist the AE in disseminating information to and from the
meeting.
(2) Coordinates and schedules the Preparatory (Pre-) ESAAB Equivalent
review and final ESAAB Equivalent Board review. This includes
collection and distribution of related project information prepared by the
project or program.
(3) Coordinates with OECM on Departmental ESAAB Board reviews for CDs
on MS projects, or for BCPs that require approval at the SAE level.
(4) Offers ESAAB-related improvements/suggestions on project planning and
process to the AE, PO, and IPT.
(5) Provides written comments on significant project issues to the AE, PO,
and IPT.
(6) Assists the AE on the technical and management significance of
issues/lessons learned identified from previous ESAAB and Quarterly
reviews of the subject project, or from that of other projects.
(7) Provides science-based recommendations on the root cause of issues and
how they can be resolved.
(8) Records minutes and action items resulting from the Preparatory (Pre-)
ESAAB Equivalent review and the final ESAAB Equivalent Board
BOP-50.001A
07-28-11
15
(8) Records minutes and action items resulting from the Preparatory (Pre-)
ESAAB Equivalent review and the final ESAAB Equivalent Board
meetings. Distributes draft and final meeting minutes in a timely fashion,
for both the Pre-ESAAB and ESAAB-E reviewtneetings to aid in the
preparation of following deliverables and E~AAB-E process steps, such as
the preparation of the resulting Decision Memorandum for signature by
the AE.
(9) Assures that the Decision Memorandum prepared by the program/project
area:
• Appropriately documents the determination of the AE, and
• Captures relevant items/issues.
Section 11
(10) Maintains the NA-APM-20 database/library ofHQ ESAAB Equivalent
Board meetings minutes, approval/decision memorandums, supporting
documentation, and related action items.
(II) Works with FPD, PO, and ESAAB Equivalent members to facilitate
review process and track issues to resolution.
(12) Works with all parties to improve the ESAAB Equivalent Board process.
(13) Monitors/validates procedures and processes from Site Offices ESAAB
Equivalent boards.
7. REFERENCES.
a. DOE Order 413.3B, Program and Project Management for the Acquisition of
Capital Assets, November 29, 2010.
b. DOE STD 1189-2008, Integration of Safety into the Design Process.
c. DOE Order 420.1B Chg I, Facility Safety, April19, 2010.
8. CONTACT. O±Iice of Enterprise Project Management (NA-APM-20), 301-903-3557.
BY ORDER OF THE ADMINISTRATOR:
Acting Associate Administrator
for Acquisition and Project Management
16 BOP-50.001A
07-28-11
ATTACHMENT 1 ESAAB EQUIVALENT BOARD MEMBERSHIPS
ATTACHMENT 2 NNSA ESAAB EQUIVALENT REQUEST FORM, CRITICAL
DECISION, AND APPROVAL MEMORANDUM EXAMPLES
ATTACHMENT 3 CRITICAL DECISION INFORMATION OUTLINES
ATTACHMENT 4 ESAAB EQUIVALENT PRESENTATION OUTLINE
ATTACHMENT 5 ESAAB EQUIVALENT PROCESS FLOWCHART
BOP-50.001A Attachment 1
07-28-11 Page 1
ATTACHMENT 1: ESAAB EQUIVALENT BOARD MEMBERSHIPS
Role/Area of Inquiry Principal Board Member
Board Chairperson Acquisition Executive
Nuclear Safety Chief of Defense Nuclear Safety
Legal
NNSA General Counsel, NA-GC
Budget Director, Office of Planning, Programming, Budgeting, and
Evaluation (PPBE), NA-MB-30
Environmental Environment, Safety and Health (NA-SH)
Safety & Health (includes
Integrated Safety Management)
Environment, Safety and Health (NA-SH)
Security Associate Administrator for Defense Nuclear Security,
NA-70
Procurement Office of Acquisition Management, NA-APM-10
Director, Office of Procurement and Assistance, MA-60
Project Management and
NNSA ESAAB Equivalent
Secretariat
Director, Office of Enterprise Project Management, NA-
APM-20
OECM Participants Office of Engineering and Construction Management,
MA-50
Specialized support, as
required
Project-specific technology support:
R&D subject matter experts (SMEs),
Program specialists,
ES&H subject matter experts (SMEs)
Other support, as required
Diversity – Office of Management and Budget (NA-MB)
Public Affairs
Congressional Affairs
Office of the CFO
BOP-50.001A Attachment 2
07-28-11 Page 1
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
REQUEST FOR
NNSA ENERGY SYSTEMS ACQUISITION ADVISORY BOARD (ESAAB)
EQUIVALENT REVIEW, AND DEPARTMENTAL ESAABS
Name of Project
Project Location
Project Number Major System? Yes No
Acquisition Executive
Type of Review:
Critical Decision 0
Critical Decision 1
Critical Decision 2
Critical Decision 3
Critical Decision 4
Baseline Change Proposal, Level
Other:
Name E-Mail Organization
NNSA Project Director:
Contractor Project Manager:
HQ Program Manager(s):
An NNSA Pre-ESAAB Equivalent review is Requested on the week of this date. (THIS FORM MUST BE
SUBMITTED AT LEAST ONE AND A HALF WEEKS BEFORE THE REQUESTED PRE-ESAAB)
A NNSA ESAAB Equivalent Board meeting is Requested on the week of this date (THIS FORM MUST
SUBMITTED AT LEAST THREE WEEKS BEFORE THE REQUESTED ESAAB-EQUIVALENT)
ADDITIONAL ATTENDEES
Section 12
If your office would like to have the electronic meeting notice for this meeting sent to individuals in addition to the names provided on this
form, include those names and e-mail addresses here:
NAME E-MAIL ADDRESS ORG
(As necessary, provide a separate list of additional Attendees and
related information: email, organization.)
ALL SUPPORTING DOCUMENTATION must be provided to the NA-APM-20 ESAAB Equivalent Secretariat a minimum of one week
prior to the Pre-ESAAB Equivalent review meeting. NOTE, If this form is being used to request a full Departmental ESAAB action (i.e.
CD for a Major System or a Baseline Change Proposal (BCP), allow 4 weeks after the Pre-ESAAB of a minimum total of six weeks after the
submission of this form and related requisite documentation: Please see related NNSA ESAAB Equivalent BOP for more details.
1. I acknowledge and accept
the above requirement:
Federal Project Director Date Phone #
2. Approved for scheduling:
Headquarters Program Manager Date Phone #
3. Email to NA-APM-20 for scheduling:
Email this form to Jane Gartner (Jane.Gartner@nnsa.doe.gov; 301-903-8235) AND to Katie O‘Mara
(Katherine.Omara@nnsa.doe.gov; 202-586-6867).
Electronic versions of this file are available on the NA-APM-20 IntraNet WebSite.
REQUIRED REVIEW MATERIALS
mailto:Jane.Gartner@nnsa.doe.gov
mailto:Katherine.Omara@nnsa.doe.gov
Attachment 2 BOP-50.001A
Page 2 07-28-11
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
(Documents previously submitted to NA-APM-20 for an Independent Project Review (IPR) need
not be resubmitted—documents require approval/concurrence at one level below the AE)
CD-0 Approve Mission Need
1. Pre-conceptual Planning (Also, for Hazard Category 1, 2, and 3 nuclear facilities, and to the specificity possible,
document DOE expectations for safety in design. (See DOE-STD-1189, as amended.)
2. Mission Need Statement
3. Tailoring Strategy
4. Program Requirements Document
5. Results from Mission Validation Independent Review (if required), and any external and/or internal reviews including
Corrective Action Plans
6. Evaluate projects for Information Technology elements within the Departmental Enterprise Architecture framework
7. Presentation
CD-1 Approve Alternative Selection and Cost Range
1. Conceptual Design Report
2. Safety Design Strategy for projects subject to DOE-STD 1189, as amended.
3. Cost Estimate, including documentation on the basis and assumptions
4. Acquisition Strategy
5. One-for-One Replacement documentation
6. Preliminary Project Execution Plan
7. Federal Project Director appointment
8. Integrated Project Team
9. Design Review Results, including Technical Independent Project Review (when required)
10. Project Data Sheet
11. Long-Lead Procurements (if any)
12. NEPA strategy and analysis documents
13. High Performance Sustainable Building documentation
14. Preliminary Security Vulnerability Assessment Report
15. Integrated Safety Management documentation
16. Conceptual Safety Design Report (for Hazard Category 1, 2, and 3 nuclear facilities)
17. Conceptual Safety Validation Report (for Hazard Category 1, 2, and 3 nuclear facilities)
18. Preliminary Hazard Analysis Report (for facilities that are below Hazard Category 3 threshold as defined in 10 CFR
830, Subpart B and obtain DOE approval (field level)
19. Quality Assurance Program documentation
20. Presentation
CD-2 Approve Performance Baseline
Section 13
1. Project Execution Plan
2. Performance Baseline (i.e., scope, cost, schedule, risk mitigation, etc.)
3. Cost Estimate, including documentation on the basis and assumptions
4. Performance Baseline Validation Review results including Corrective Action Plans
5. Performance Baseline Validation Letter
6. Independent Cost Estimate or Independent Cost Review (when required)
7. Quality Assurance Program documentation
8. Earned Value Management System (when required)
9. Updated Project Data Sheet
10. Preliminary Design
11. Design Review results
12. Updated Safety Design Strategy (for projects subject to DOE-STD 1189)
13. Preliminary Safety Design Report (for Hazard Category 1, 2, and 3 nuclear facilities)
14. Preliminary Safety Validation Report (for Hazard Category 1, 2, and 3 nuclear facilities)
15. Approved Hazard Analysis Report (for facilities that are below Hazard Category 3 threshold as defined in 10 CFR 830,
Subpart B and obtain DOE approval (field level)
16. Updated Security Vulnerability Assessment Report
17. Evidence of incorporating Sustainable Environmental Stewardship – High Performance Sustainable Building
BOP-50.001A Attachment 2
07-28-11 Page 3
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
provisions
18. Final NEPA documentation
19. Presentation
CD-3 Approve Start of Construction
1. Design Review results from final design review
2. Updated Project Execution Plan and Performance Baseline
3. Execution Readiness or External Independent Review Results for Major Systems
4. Updated Safety Design Strategy (for projects subject to DOE-STD 1189)
5. Preliminary Documented Safety Analysis Report (for Hazard Category 1, 2, and 3 nuclear facilities)
6. Updated Hazards Analysis Report (for facilities that are below Hazard Category 3 threshold as defined in 10 CFR 830,
Subpart B and obtain DOE approval (field level)
7. Updated Security Vulnerability Assessment Report
8. Safety Evaluation Report (for Hazard Category 1, 2, and 3 nuclear facilities)
9. Approved Construction Project Safety and Health Plan
10. Evidence of incorporating Sustainable Environmental Stewardship – High Performance Sustainable Building
provisions
11. Updated Quality Assurance Program
12. Project Data Sheet
13. Presentation
CD-4 Approve Start of Operations or Project Closeout
1. Verification of Key Performance Parameters or Project Completion Criteria
2. Completed Operational Readiness Review or Readiness Assessment
3. Checkout, Testing and Commissioning Plan
4. Project Transition to Operations Plan
5. Updated Quality Assurance Plan
6. Revised environmental management system
7. Documented Safety Analysis Report with Technical Safety Requirements (for Hazard Category 1, 2, and 3 nuclear
facilities)
8. Updated Construction Project safety and Health Plan
9. Approved Final Hazards Analysis Report
10. Final Security Vulnerability Assessment Report
11. Safety Evaluation Report (for Hazard Category 1, 2, and 3 nuclear facilities)
12. Presentation
PLEASE NOTE:
The project provide ALL review documents to the NA-APM-20 ESAAB Secretariat
(Katherine.Omara@nnsa.doe.gov or Jane.Gartner@nnsa.doe.gov ) at least one week prior to the scheduled
Preparatory (Pre-) ESAAB Equivalent meeting to allow ESAAB Equivalent Board members adequate time to
prepare comments.
The Project Director agrees to notify Katherine.Omara@nnsa.doe.gov or Jane.Gartner@nnsa.doe.gov if the
Section 14
supporting documentation will not be ready for review one week prior to the scheduled Preparatory (Pre-)
ESAAB Equivalent meeting.
Board members may postpone meetings if adequate review time is not provided.
SHARED FILES
Authorized Headquarters users can access the NA-APM-20 Shared Files Folder at: \\hqnas009.na.local\public
Remote users will need to login through: https://workplace.doe.gov/
To request access to the NA-APM-20 Shared Files folder, email Ginnie Marshall at Virginia.Marshall@nnsa.doe.gov
DO NOT FAX THIS PAGE
mailto:katherine.o'mara@nnsa.doe.gov
mailto:Jane.Gartner@nnsa.doe.gov
mailto:katherine.o'mara@nnsa.doe.gov
mailto:Jane.Gartner@nnsa.doe.gov
file://hqnas009.na.local/public
https://workplace.doe.gov/
Attachment 2 BOP-50.001A
Page 4 07-28-11
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
SAMPLES CD-1, CD-2/3, AND CD-3 MEMORANDA
Department of Energy
National Nuclear Security Administration
Washington, DC 20565
January 8, 2010
MEMORANDUM FOR: DONALD L. WINCHELL, JR.
REVITALIZATION MANAGER
LOS ALAMOS SITE OFFICE
FROM: ROBERT DINO HERRER.o/) A _£]__ "";\ · J..)
DIRECTOR ~~~
OFFICE OF INFRASTRUCURE
AND FACILITIES MANAGEMENT
SUBJECT: Sanitary Etlluent Reclamation Facility Expansion Project at the Los Alamos
National Laboratory (LANL)
By this memorandum, I approve the Critical Decision (CD)- 1, Alternative Analysis and
Cost Range, for the subject project. The approved alternative (alternative 3 of the
Alternative Analysis Report dated September 29, 2009,) is to expand the existing SERF
to accommodate new equipment to handle additional quantities of liquid to be treated. In
addition, I approve the acquisition strategy for the project to be design/build. Appro•,al
of CD-1 allows the Department to request construction funds in Fiscal Year (FY) 2011.
The approved Total Project Cost range is $10 million to $16 million and the Total
Estimated Cost range is $9 million to SIS million. The CD-4 approval date range is
4Q Fiscal Year (FY) 2012 to lQ FY 2013. The Deputy Secretary's memorandum dated
January 16,2009, and the FY 2011 Field Budget Call dated December 14, 2009, require
that all pre-CD-2 projects with a total project cost (TPC) of less than $20 million request
all construction funds within the same appropriation year of start of construction. As a
result, the project will be fully funded in FY 2011, its construction year, in the amount of
S 13.8 million. My approval authorizes the project team to initiate the design/build
procurement process.
If you have any questions, please call me at 202-586-5366 or have your staff call Shah
Jaghoory at 301-903-73768.
BOP-50.001A Attachment 2
07-28-11 Page 5
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
Department of Energy
National Nuclear Securhy Administration
Washington,. DC 20585
July 17,2009
OFFICE OF THE ADMINISTRATOR
MEMORANDUM FOR REYIT ALIZA TION MANAGER
LOS ALAMOS SITE OFFICE
FROM: THOMAS P. D'AGOSTINO /T) ---;-') 1' ~ ~t\-..
ADMINISTRATOR ~ \. ~ 0
SUBJECT: Critical Decision-2 and 3 (CD-2/3) for the Chemistry and
Metallurgy Research Replacement Facility (CMRR) -
Radiological Laboratory Utility Office Building (RLUOB)
Equipment Installation (REI) project at Los Alamos National
Laboratory, Line Item Project 04-D-125
Section 15
By this memorandum, I am approving CD-2, Approve Perfonnance Baseline, and CD-3,
Approve Start of Construction, for the REI project, subject to availability of
appropriations. The Total Project Cost is $199.4 million, the Total Estimated Cost is
$152.9 million, and the project completion date (CD-4, start of Operations) is June 30,
201 3. Accordingly, the project is authorized to use the available construction funds for
the acquisition of REI work scope.
The RLOUB, REI, and the Nuclear Facility are three phases of the overall CMRR
Project. The Nuclear Facility, which is a major system acquisition, falls under the
authority of the Secretarial Acquisition Executive. The RLOUB and REI are below the
major system acquisitions threshold and, therefore, are managed as separate projects
with separate baselines within the CMRR Project, with Acquisition Executive Authority
vested in the Administrator NNSA. This interpretation of acquisition authorities is based
on a decision from the Office of Engineering and Construction Management (MA-50), as
the Secretariat of the DOE Energy System Acquisition Advisory Board process and
cognizant authority to interpret DOE Order 413.3A, "Program and Project Management
for the Acquisition of Capital Assets." The infom1ation reported in the CMRR
Congressional Project Budget Data Sheet is not affected by this action.
The project's high level scope includes:
• Equipping the RLUOB to make it suitable for perfonning programmatic work,
such as completing identified laboratories for operational use, radioactive waste
utility tie-ins, purchase and installation of equipment including radiation
protection health physics equipment, and completing fuel oil storage above
ground tank(s ),
Attachment 2 BOP-50.001A
Page 6 07-28-11
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
2
• Completing activities necessary to make the facility functionally operational, such
as the inclusion of telecommunications services and requisite security features.
The attachment to this memorandum contains the detailed funding baseline.
Completion of REI will make the RLUOB operational to enable it to perfonn
programmatic work, mostly related to chemical analysis of small samples containing
actinides, especially plutonium. Once completed, this project will reduce the risk of
disruption of analytical chemistry services for nuclear programs at Los Alamos.
If you have any questions, please call me or have your staff call Patrick Rhoads at
(202) 586-7859.
Attachment
BOP-50.001A Attachment 2
07-28-11 Page 7
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
DepartmentofEn~y
National Nuclear Security Administration
Washington, DC 20585
July9, 2009
MEMORANDUM FOR: STEVEN C. ERHART
MANAGER
FROM:
SUBJECT:
PANTEX SITE OFFICE
THAD T. KONOPNICKil'f~
ASSOCIATE ADMINISTRATOR FOR
INFRASTRUCTURE AND ENVIRONMENT
Critical Decision-3 (CD-3) for the High Pressure Fire Loop
(HPFL) Project at Pantex Production Facility, Line Item
Project 08-D-801
By this memorandum, I am approving CD-3, Approve Start of Construction, for the
HPFL Project, subject to availability of appropriations. The Total Project Cost is
$42.364 million, the Total Estimated Cost $40.899 million, and the project completion
date (CD-4, start of Operations) is September 30, 2012. Accordingly, the project is
authorized to use the available construction funds to prepare for construction activities.
Section 16
My approval is based on the recommendation of members of the National Nuclear
Security Administration's (NNSA) Energy System Acquisition Advisory Board
(ESAAB)- Equivalent and my staff.
The project's high level scope includes:
• Replace deteriorating ductile iron piping with new high density polyethylene
piping.
• Replace Post Indicator Valves and installation of Cathodic Protection and other
appurtenances.
• Replace Hydrants and installation of Cathodic Protection and other
appurtenances.
More detailed scope is provided in the Project Execution Plan, which will be the subject
of another approval memorandum.
It is my understanding that the project team has received confirmation from the Chief of
Defense Nuclear Safety that the project is not considered to be a "Major Modification."
Therefore, the DOE Standard I 189 "Integration of Safety into Design Process"
requirements do not apply. I have also received confirmation that the system's ability to
• Primedwlth tc;ll'lkon recydedPI!Pfl r
Attachment 2 BOP-50.001A
Page 8 07-28-11
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
2
meet the intended safety function requirements is documented in the existing safety basis
and the project's design documents.
As the Acquisition Executive for the HPFL Project, I am conditionally approving
Amanda Clark as the Federal Project Director for the HPFL Project, subject to her ability
to obtain Level II Project Management Certification within twelve months of this
approval as required by Section 5.a.(3), Chapter N of DOE Order 36l.lA. I am
postponing my decision to delegate the CD-4, Approve Start of Operations, to the Site
Office Manager until a later point in time.
Completion of HPFL will enhance reliability of safety-class fire suppression system to
ensure that the Pantex Plant will be able to meet mission assignments in Zone 12 South
Material Access Area. Once completed, this project will reduce the risk of unplanned
facility system outages and reduce system maintenance requirements.
Although I am approving the Total Estimated Cost to be $40.899 million, because of the
favorable bids that the project has received, I will withhold the $7.303 million increase in
the Total Estimated Cost proposed in the Baseline Chang Proposal 6A as the
Headquarters reserve. This approach was proposed by your staff at the Energy System
Acquisition Advisory Board- Equivalent CD-3 review.
The attachment to this memorandum contains the funding and cost profiles and the major
milestones for the project, subject to Congressional approval of the funding request and
the Deputy Secretary approval of BCP 6A.
If you have any question, please call me at (202) 586-7349 or have your staff contact
Thomas Robinson, of my staff, at (202) 586-0139.
Attachment
BOP-50.001A Attachment 2
07-28-11 Page 9
ATTACHMENT 2: NNSA ESAAB EQUIVALENT REQUEST FORM,
CRITICAL DECISION, AND APPROVAL MEMORANDUM EXAMPLES
Attachment to the HPFL Project Critical Decision 3 Approval Memorandum from
Thad T. Konopnicki to Steven C. Erhart
Approved FundiDg ProfUe ($Million)
FWldingType Prior FY 2008 FY2009 FY 20 10 Total
Years
PED: 06-D-160-01 1.686 1.686
Construction: 08-D-801 6.866 1.94 31.9fT 40.716
OPC 0.746 0.106 0.178 0.435 1.465
Total 2.432 6.972 2.118 32.345 43.867
Approved Cost Profile
FWlding Type Prior FY2009 FY2010 FY2011 FY2012 Total
Years
Section 17
PED: 06-D-160-01 1.479 0.207 1.686
Construction: 08-D-801 1.223 15.713 15.479 0.766 33.181
OPC 0.670 0.020 0.170 0.188 0.243 1.291
Total 2.149 1.450 15.883 15.667 1.009 36.158
Approved Major Milestones
Milestone Name Baseline Date Actual Date
Critical Decision 0 09/15/2004
Critical Decision I 12/23/2005
Complete Design 09/2112007
Critical Decision 2 12/1/2006
Critical Decision 3 4"'0FY 2009 Actual date after aooroval
Begin Construction 4"' OFY2009
Complete Construction 2'"'0FY2012
Critical Decision 4 September 30,2012
Final Cost Report March 31,2013
1 Consistent with the BCP 6A, the project is authorized for S30.347M.
BOP-50.001A Attachment 3
07-28-11 Page 1
ATTACHMENT 3: CRITICAL DECISION INFORMATION OUTLINES
Required Review Materials for Critical Decisions 0 through 4 are listed in Table 2, Critical
Decision Requirements, in DOE Order 413.3B, Program and Project Management for the
Acquisition of Capital Assets, and on the NA-APM-20 website (http://hq.na.gov/pmnet).
Suggested project preparation topics for Critical Decisions are also available on the NA-APM-20
website.
Documents previously submitted to NA-APM-20 for an Independent Project Review (IPR) need
not be resubmitted. However, the documents require approval/concurrence at one level below
the AE.
http://hq.na.gov/pmnet
BOP-50.001A Attachment 4
07-28-11 Page 1
ATTACHMENT 4: ESAAB EQUIVALENT PRESENTATION OUTLINE
General Requirements for all Presentations (also see the following specific guidance for
each Critical Decision below):
What decision(s) is being requested from the ESAAB Equivalent AE (1 slide)
Extremely brief Project Overview (i.e., mission and project description) (1-2 slides)
Integration of Safety into Design (e.g.DOE-STD-1189) for Hazard Category 1, 2, and 3
nuclear facilities. Include discussion of Safety Design Strategy, limiting Design Basis
Accidents, engineered controls, and unresolved issues related to safety in design (1-2
slides)
Organization Chart (1 slide)
Changes to project status and resolution of prior issues since last ESAAB Equivalent
Meeting—progress on Corrective Action Plans and resolution of other issues (1-2 slides)
Required funding profile (1 slide)
Results from recent reviews (e.g., Independent/External Project Reviews ) supporting the
Critical Decision: to include evidence of compliance with programmatic, safety,
environmental energy efficiency/LEED/High Performance Sustainable Building, security,
legal, procurement, and departmental requirements, (1-3 slides)
o (e.g. DOE Orders 430.2B, 450.1A and related Executive Orders),
Specific issues that require AE action—FPD and PO will work with board members to
prepare specific major issues for presentation to AE, in advance of the ESAAB for
presentation and discussion. This should be reserved for issues that have significant
programmatic implications (1 slide)
o Brief summary of results of Preparatory (Pre-) ESAAB Equivalent member staff
review—summarize results of ESAAB Equivalent discussions, issue resolution,
and corrective action plan (1-2 slides)
High risks and mitigation (1 slide)
Decision Approval Summary (1 slide)
(Optional) BACKGROUND section to include relevant additional information for
reference as needed
Following are Specific Requirements for Presentations for Critical Decisions 0 through 4:
Critical Decision 0
State Mission Need, capability gap, and document mission requirement that cannot be
met through other than material means
Section 18
State Tailoring Strategy—describe project‘s approach for appropriately adapting critical
decision requirements based on project‘s risk and complexity, if tailoring is planned
Define ultimate goals from Program Requirements Document which project must satisfy
Attachment 4 BOP-50.001A
Page 2 07-28-11
ATTACHMENT 4: ESAAB EQUIVALENT PRESENTATION OUTLINE
Request approval of Mission Need Statement and Program Requirements Document
(documents require approval/concurrence of one level below the AE)
Critical Decision 1
Address acquisition strategy that decribes the high-level business and technical
management approach designed to achieve project objectives, including Key
Performance Parameters, within specified resource constraints
List alternatives considered and preferred/recommended alternative
For Hazard Category 1, 2, and 3 nuclear facilities, discuss the Safety Design Strategy,
including how it will be aligned to reflect the approved Tailoring Strategy, if applicable.
Discuss the results of the Conceptual Safety Validation Report, including any Conditions
of Approval.
Show cost range and estimated funding requirements, by year if available
Request approval of Federal Project Director, if not previously approved
Identify Integrated Project Team
Address NEPA strategy and timeline
Request approval of Long-Lead Procurements, if necessary
Request approval of Acquisition Strategy and Preliminary Project Execution Plan,
(documents require approval/concurrence of one level below the AE)
Critical Decision 2
Address the Performance Baseline, total project cost, schedule, and scope
Address changes to Project Execution Plan resulting from the design effort in all areas
including design considerations; performance baseline; project, risk, and configuration
management, including EVMS usage; and roles and responsibilities
Indicate changes to Mission Need Statement; Program Requirements Document; and
Acquisition Strategy
For Hazard Category 1, 2, and 3 nuclear facilities, discuss any significant changes to the
Safety Design Strategy since CD-1. Discuss the results of the Preliminary Safety
Validation Report, including any Conditions of Approval.
Discuss NEPA implementation
Report results from Performance Baseline Validation External Independent Review (EIR)
(required for Major System projects) or Performance Baseline Validation Independent
Project Review (IPR) and Independent Cost Review (ICR)
Address Quality Assurance Program
Address Preliminary Design—this stage of the design is complete when it provides
sufficient information to support development of the Performance Baseline
BOP-50.001A Attachment 4
07-28-11 Page 3
ATTACHMENT 4: ESAAB EQUIVALENT PRESENTATION OUTLINE
Critical Decision 3
Request approval of updates to CD-2 project documentation to reflect any changes
resulting from final Design, such as the Project Execution Plan, Performance Baseline,
Project Data Sheet, etc.
For Hazard Category 1, 2, and 3 nuclear facilities, discuss any significant changes to the
Safety Design Strategy since CD-2. Discuss the results of the Safety Evaluation Report
based on the review of the Preliminary Documented Safety Analysis, including any
Conditions of Approval.
Report results from External Independent Review (EIR) or Independent Project Review
(IPR)
Discuss construction readiness and implementation (e.g. any pending award of
construction contract)
Section 19
Address updates to Quality Assurance Program for construction, field design changes,
and procurement activities
Critical Decision 4
Verify Key Performance Parameters or Project Completion Criteria have been met and
mission requirements achieved
For Hazard Category 1, 2, and 3 nuclear facilities, discuss any significant changes to the
Safety Design Strategy since CD-3. Discuss the results of the Safety Evaluation Report
based on the review of the Documented Safety Analysis and Technical Safety
Requirements, including any Conditions of Approval.
Address the Readiness Assessment or Operational Readiness Review and all pre-start
findings for nuclear facilities
Address a Checkout, Testing, and Commissioning Plan that identifies subtasks, systems,
and equipment
Address a Project Transition to Operations Plan that clearly defines the basis for attaining
initial operating capability, full operating capability, or project closeout, as applicable
Address an updated Quality Assurance Plan to address testing, identified deficiencies,
and startup, transition, and operation activities.
Address any new environmental aspects related to turnover and operations.
BOP-50.001A Attachment 5
07-28-11 Page 1
ATTACHMENT 5: ESAAB EQUIVALENT PROCESS FLOWCHART
Federal Project Director (FPD)
and PO jointly request ESAAB-
E Board meeting
NA-APM-20 coordinates
Pre-ESAAB-E review
meeting
FPD/PO provides supporting documentation to NA-APM-20
one and a half weeks prior to scheduled Pre-ESAAB-E meeting
Pre-ESAAB-E review
meeting
Draft and Final Pre-
ESAAB-E meeting
minutes prepared.
Resulting Action Items
given to project team
Decision Memo prepared by PO
and FPD
ESAAB-E meeting
with Acquisition
Executive
Decision
Determined?
Decision Memo signed at
ESAAB or within two weeks
Action Items / issues
provided to project
team within two
weeks
Project team
resolves Action
Items / issues
YES
NO
Draft and Final ESAAB-E
meeting minutes prepared
Draft and Final
ESAAB-E meeting
minutes prepared
Project team resolves
Action Items / issues