NAP-33, Planning, Programming, Budgeting, and Evaluation (PPBE) Process
Establish procedures to ensure that the planning, programming, budgeting, and financial activities of the National Nuclear Security Administration (NNSA) comply with sound financial and fiscal management principles.
Cancels:
BOP-001.1, PPBE Planning Process on Jan 17, 2017
BOP-001.2, PPBE Programming Process on Jan 17, 2017
BOP-001.031, PPBE Budget Formulation Process on Jan 17, 2017
BOP-001.311, Budget Validation Process on Jan 17, 2017
BOP-001.331, Budget Execution Headquarters Approved Funding Program (HQ AFP) and Work Authorization (WA) Business Operation Policy on Jan 17, 2017
BOP-001.333, NNSA Operations Under a Continuing Resolution on Jan 17, 2017
BOP-001.4, PPBE Evaluation Process on Jan 17, 2017
Renumbered From:
Version history and related documents
Document text
Text extracted from the attached file. Refer to the original document for the authoritative version.
Section 1
CONTROLLED DOCUMENT OFFICE OF PRIMARY INTEREST (OPI):
AVAILABLE ON-LINE AT: Planning, Programming, Budget & Evaluation
https://nnsa.energy.gov/aboutus/ouroperations/managementandbudget/policysystem/nnsapolicies
printed copies are uncontrolled
NNSA POLICY LETTER
Approved: 1-17-17
PLANNING, PROGRAMMING,
BUDGETING, AND EVALUATION (PPBE)
PROCESS
NATIONAL NUCLEAR SECURITY ADMINISTRATION
Management and Budget
NAP-33
https://nnsa.energy.gov/aboutus/ouroperations/managementandbudget/policysystem/nnsapolicies
THIS PAGE INTENTIONALLY LEFT BLANK
NAP-33 1
1-17-17
PLANNING, PROGRAMMING, BUDGETING, AND EVALUATION (PPBE) PROCESS
1. PURPOSE. Establish procedures to ensure that the planning, programming, budgeting,
and financial activities of the National Nuclear Security Administration (NNSA) comply
with sound financial and fiscal management principles.
2. CANCELLATIONS.
a. Business Operating Procedure (BOP)-001, Planning, Programming, Budgeting,
and Evaluation (PPBE) Process, dated 11-8-11.
b. BOP-001.01, Application of PPBE Process for Activities Funded by the Office of
the Administrator Appropriation, dated 11-8-11.
c. BOP-001.1, PPBE Planning Process, dated 11-8-11.
d. BOP-001.2, PPBE Programming Process, dated 11-8-11.
e. BOP-001.31, PPBE Budget Formulation Process, dated 11-8-11.
f. BOP-001.311, Budget Validation Process, dated 11-8-11.
g. BOP-001.331, Budget Execution Headquarters Approved Funding Program (HQ
AFP) and Work Authorization (WA) Business Operation Policy, dated 2-15-08.
h. BOP-001.332, PPBE Reprogramming/Appropriation Transfer/Notification
Process, dated 11-8-11.
i. BOP-001.333, NNSA Operations Under a Continuing Resolution, dated 2-15-08.
j. BOP-001.4, PPBE Evaluation Process, dated 10-05-12.
3. APPLICABILITY. Unless otherwise stated in the Appendixes, the applicability is the
same for each appendix.
a. Federal. This policy applies to all NNSA elements.
b. Contractors. Does not apply to contractors.
c. Equivalency. In accordance with the responsibilities and authorities assigned by
Executive Order 12344, codified at 50 United States Code sections 2406 and
2511, and to ensure consistency through the joint Navy/DOE Naval Nuclear
Propulsion Program, the Deputy Administrator for Naval Reactors (Director) will
implement and oversee requirements and practices pertaining to this Directive for
activities under the Director's cognizance, as deemed appropriate.
4. SUMMARY OF CHANGES. This NNSA Policy Letter (NAP) updates the planning
process to reflect the current planning documents, including the Planning, Programming,
2 NAP-33
1-17-17
and Fiscal Guidance (PPFG), removing references to legacy documents such as the
NNSA Strategic Planning Guidance and NNSA Strategic Plan. This NAP revises the
programming process to reflect the two-phased approach of integration and prioritization,
and program review. Also, roles and responsibilities for all NNSA elements have been
updated to address the PPBE process relative to the Federal Salaries and Expenses (FSE)
appropriation.
This document also reflects the establishment of the Office of Cost Estimating and
Program Evaluation (CEPE), which reports directly to the Administrator, and CEPE’s
role in the PPBE process. CEPE now leads the enterprise level planning phase and
incorporates planning guidance into the PPFG document, eliminating the need for a
separate issuance of the NNSA Strategic Planning Guidance. CEPE and Management
and Budget (NA-MB) share responsibility for the programming phase; NA-MB leads the
integration and prioritization activity while CEPE leads the program review activity.
Section 2
This NAP consolidates all previous BOPs on PPBE.
5. BACKGROUND.
a. Section 3252 of the NNSA Act requires the Administrator to develop a planning,
programming, and budgeting process that operates under sound financial and
fiscal management principles. The NNSA Act also requires NNSA to annually
provide to Congress a Future Years Nuclear Security Program (FYNSP) that
details NNSA’s planned expenditures and proposed appropriations for the next
five fiscal years. This NAP describes the requirements, basic processes, and
responsibilities for the conduct of each element of the PPBE process. The NNSA
PPBE process is similar to PPBE processes in use across the United States
Government and has four major phases for each budget cycle: Planning,
Programming, Budgeting (includes formulation, execution, and validation), and
Evaluation. At any particular point in time, multiple PPBE phases for different
budget cycles will be ongoing.
(1) Planning. The purpose of the Planning phase of the PPBE process is to
gather or update all the information, cost data, and options necessary to
prepare to make resource decisions based on priorities during
programming. It constitutes a preparation phase for the conduct of
programming. It considers the full range of work to be done against
current plans and should be fiscally unconstrained to ensure that all
requirements and other mission needs are considered. While planning is
typically a year-round, continuous activity conducted by line
organizations, a discrete Planning phase with stated objectives and
guidance (provided by the NNSA Planning, Programming, and Fiscal
Guidance (PPFG)) provides a specific corporate focus as preparations
begin for Programming.
Key documents to be consulted during the Planning phase:
NAP-33 3
1-17-17
(a) NNSA periodically issues the NNSA Enterprise Strategic Vision
that provides clear direction and reflects the Administrator’s goals
and expectations for the NNSA. It cascades from the DOE
Strategic Plan and establishes the Administrator’s short and long-
term vision, priorities, and issues; it also articulates goals, means,
and strategies for the NNSA moving forward. The NNSA
Enterprise Strategic Vision provides the framework for top to
bottom linkages in PPBE activities.
(b) The PPFG updates the Administrator’s vision and priorities for the
current PPBE cycle. It also identifies emerging issues that might
challenge the NNSA baseline program and directs some potential
excursions for further study and exploration during the planning
process. The PPFG will also define budget levels under various
scenarios and describe the calendar for the planning, programming,
and budget formulation cycles. The PPFG will include NNSA-
wide programmatic and budgetary guidance and, as necessary,
program-specific guidance for use during programing. It provides
program elements with the context within which the Programming
Phase will be conducted and, therefore, better inform their
activities during the Planning phase.
(c) Program or project plans developed by NNSA’s program managers
to provide a roadmap of work activities, metrics and milestones
derived from the NNSA Strategic Vision.
(2) Programming. The purpose of the Programming phase of the PPBE
process is to make decisions to align available program resources with
priorities resulting in a balanced, integrated, executable NNSA FYNSP to
be proposed to the Office of Management and Budget as the basis for that
year’s Congressional budget request. This is primarily an NNSA HQ-
driven process that progressively allocates resources and integrates the
program from the program office to DOE level. This process is fiscally
conscious, allocating available resources against NNSA and DOE
priorities.
Section 3
The Programming process is guided by the PPFG:
(a) Each NNSA program element develops and provides programming
deliverables required in the PPFG in accordance with their own
internal processes for doing so;
(b) Then NNSA conducts activities at the NNSA level within major
appropriations focused on integration and prioritization of the
programs that make up each major appropriation. Actions during
this phase include review of program materials, cost review and
validation of budget estimates, and holding integration meetings to
4 NAP-33
1-17-17
identify and resolve disconnects between program elements within
major appropriations.
(c) The process then shifts to program review activities to develop
options and proposals for balancing resources across NNSA and
the major appropriations. This may include standing up of issue
teams to examine items requiring leadership decisions. The issue
teams will be federally staffed and will collaboratively determine
program alternatives, offsets, and programmatic and portfolio
effects and risks.
(d) The Management Council adjudicates unresolved issues and makes
recommendations for the overall NNSA program and resource
allocations for the Administrator’s approval and transmittal to the
Department.
(e) The last step in determining NNSA’s budget request to the Office
of Management and Budget (OMB) is the Department’s
Programming process. Here, DOE organizations brief the
Secretary on their proposed budget and reprioritize as necessary.
The Secretary issues the program decision guidance completing the
programming process for NNSA.
(3) Budgeting. The Budgeting process includes development of the OMB and
President’s budget requests, budget execution, and the budget validation
processes.
(a) OMB budget justification materials, for the FYNSP, are developed
articulating work scope and schedules commensurate with the
funding request.
1 NNSA, as part of the Department’s budget request,
transmits its budget requirements to OMB.
2 After a review of the budget materials and a series of
briefings, OMB issues policy and resource decisions to
guide the formulation of the President’s budget request
back to the Department; this is also known as the passback.
3 The Department can choose to appeal these decisions,
which may require additional integration meetings by the
Management Council, the Administrator, and the Secretary.
If the Department decides to appeal, documentation is sent
to OMB identifying what is being appealed and the
rationale for the appeal.
NAP-33 5
1-17-17
4 OMB issues the final settlement decisions which are
binding and form the basis for the President’s budget
request.
(b) The President’s budget request is developed and normally
transmitted to Congress on or before the first Monday in February.
1 Justifying President’s budget requests requires that NNSA
elements interact formally with Congress.
2 Congressional interactions include briefing, testifying, and
responding to questions for the record.
(c) Budget execution is the process in which appropriated resources
are distributed and controlled to achieve their approved purpose.
The OMB apportionment process makes funds available to DOE
for obligation and expenditure. DOE’s Base Table is the
controlling document for funds distribution and displays the
budgetary resources available for obligation by congressional
controls. The DOE funds distribution process makes funding
available for obligation by congressional control.
Section 4
(d) Budget validation is a process focused on determining consistency
with NNSA planning and programing guidance, integration of
planned activities and milestones with budget estimates, and
reasonableness of budget estimates.
b. Evaluation. Evaluation is the process to assess progress made toward achieving
identified performance measures at multiple levels within NNSA. These
performance measures can either be low-level milestones for internal use, or high-
level performance measures in accordance with the Government Performance and
Results Modernization Act (GPRA) of 2010 and Executive Order 13450
Improving Government Program Performance. The results of the evaluation
process feed back into the Planning process for the next PPBE cycle and input
into the performance evaluation of our managers and contractors (per NAP-4C,
Corporate Performance Evaluation Process for Management and Operating
Contractors).
This NAP includes the following appendices for delineation of phases:
• Appendix 1: Planning and Programming
• Appendix 2: Budgeting - Formulation
• Appendix 3: Budgeting - Execution (Reserved) and Validation
• Appendix 4: Evaluation
6 NAP-33
1-17-17
6. REQUIREMENTS. The identified organization must meet the requirements established
in each appendix.
7. RESPONSIBILITIES. The defined responsible person must execute the responsibilities
established in each appendix.
8. REFERENCES. References are listed in each appendix.
9. DEFINITIONS/ACRONYMS. Definitions and acronyms are listed in each appendix.
10. CONTACT. Associate Administrator for Management and Budget (NA-MB),
202-586-0101.
BY ORDER OF THE ADMINISTRATOR:
7~(~·~
Administrator
Appendixes:
1. Planning and Progranuning Process
2. Budgeting- Formulation Process
3. Budgeting- Execution Process (Reserved)
4. Evaluation Process
NAP-33 Appendix 1
1-17-17 AP1-1
APPENDIX 1: PLANNING AND PROGRAMMING PROCESS
This Appendix describes the process for conducting the planning and programming phases of the
annual Planning, Programming, Budgeting, and Evaluation (PPBE) process.
1. REQUIREMENTS. The processes described for the Planning and Programming phases
of the PPBE process must be followed.
a. During the Planning phase, the Administrator’s Planning, Programming, and
Fiscal Guidance (PPFG) must:
(1) Express the Department and Administrator’s priorities and define budget
levels under various funding scenarios;
(2) Describe the calendar for the planning, programming, and budget
formulation cycle;
(3) Include National Nuclear Security Administration (NNSA)-wide
programmatic and budgetary guidance and, as necessary, program-specific
guidance; and
(4) Be signed by the Administrator.
b. During the Programming phase, NNSA elements must transmit programming
deliverables and supporting documents detailing program work scope and risk to
NNSA’s Management and Budget (NA-MB) and Office of Cost Estimating and
Program Evaluation (CEPE). The programming phase includes two major
actions:
(1) The integration and prioritization phase:
(a) Reviewing program materials; conducting a series of integration
meetings; and updating Integrated Priority Lists (IPLs) for
Administrator approval.
(b) Reviewing costs and validating budget estimates to ensure they are
reasonable.
(2) The program review phase:
(a) Establishing issue teams to determine program alternatives, offsets,
and programmatic and portfolio effects and risks, requiring
leadership decisions during the current budget cycle. Specific
guidance on potential issue team topics and schedules must be
provided following the release of the PPFG.
Section 5
(b) Adjudicating issues identified during program review by the
Management Council.
Appendix 1 NAP-33
AP1-2 1-17-17
(c) Updating IPL’s to reflect Management Council decisions.
(d) Documenting final disposition of all issues in the Administrator’s
Preliminary Decision Memorandum (APDM).
2. PROCESS.
a. The PPBE planning and programming process consists of several major actions:
guidance, integration and prioritization, and program review. NA-MB and CEPE
direct the PPBE planning and programming process by leading or supporting each
phase.
(1) Planning: The planning process is essential for the organization to
understand how their individual efforts contribute to mission success.
(a) CEPE will initiate the planning phase by developing the PPFG
with support from NA-MB and coordination from all NNSA
elements. The Administrator signs the PPFG.
(b) NA-MB will issue supplementary guidance regarding formats for
programming materials (e.g., IPLs, supporting budget
documentation). CEPE will issue supplementary guidance on
issue teams and the program review calendar.
(2) Programming: The Programming process updates the NNSA’s resource
strategy to reflect the current Administrator’s priorities and fiscal
environment.
(a) NNSA elements develop IPLs and supporting programming
materials to transmit to NA-MB and CEPE by the dates specified
in the PPFG. Elements will also provide senior representation at
the integration meetings and communicate work scope, risks, and
issues they see in the initial budget cases. All NNSA elements will
support cost validation efforts by providing appropriate
documentation and expertise.
(b) NA-MB will lead the integration and prioritization actions through
the collection of program deliverables, and will lead a series of
integration meetings. These budget meetings will facilitate the
integration of the NNSA portfolio and updated IPLs.
(c) CEPE will support programming through cost validation of budget
estimates to ensure they are reasonable and executable.
(d) CEPE will lead program review; conduct analyses of the IPLs; and
lead issue teams comprised of federal staff from the programs.
Issue teams determine program options, offsets, programmatic and
portfolio effects, and risks for adjudication by the Management
NAP-33 Appendix 1
1-17-17 AP1-3
Council. NNSA elements are responsible for informing the issue
teams of the effects of the options identified during program
review.
(e) CEPE and NA-MB will coordinate the communication of
Management Council decisions to the Administrator for review
and approval. CEPE will record final decisions in the APDM.
The diagram below illustrates the interface between NA-MB and CEPE as well as NNSA
elements, field offices and M&O partners.
PPBE Interface & Responsibilities
3. RESPONSIBILITIES.
a. Administrator:
(1) Approves the Enterprise Strategic Vision;
(2) Signs the PPFG;
(3) Adjudicates issues identified during program review by the Principal
Deputy; and
Appendix 1 NAP-33
AP1-4 1-17-17
(4) Makes final resource allocation recommendations to the Department by
signing the APDM.
b. Principal Deputy Administrator:
(1) Chairs Management Council programming discussions in preparation for
the Administrator’s approval of the APDM;
(2) Leads a consensus-orientated decision process in the Management Council
to:
(a) Integrate and prioritize the IPL;
(b) Review the validation of the reasonableness of budget estimates;
and
Section 6
(c) Adjudicate program options, offsets, programmatic and portfolio
effects and risks identified by the issue teams.
c. Associate Administrator of NA-MB, with support from CEPE:
(1) Leads the integration and prioritization portion of the programming phase;
(2) Coordinates the preparation of programming deliverables with all NNSA
elements;
(3) In coordination with NNSA elements, updates the IPL by integrating
NNSA element inputs;
(4) Maintains NNSA statistical tables;
(5) Consolidates and synthesizes program direction requirements and funding
by object class and full time equivalents (FTE) levels for all organizational
elements under the Federal Salaries and Expenses (FSE) appropriation;
(6) Leads the development of materials for the Department’s Programming
process; and
(7) Maintains all PPBE policy and guidance documents on NNSA SharePoint
or other similar sites as necessary.
d. Director of CEPE, with support from NA-MB:
(1) Leads the PPBE planning phase by developing the PPFG;
(2) Leads the program review portion of the programming phase;
(3) Provides cost validation in support of the programming phase;
NAP-33 Appendix 1
1-17-17 AP1-5
(4) Leads issue teams to develop program alternatives and trades, and presents
these alternatives to the Management Council; and
(5) Develops the APDM in coordination with NA-MB.
e. NNSA Elements:
(1) Incorporate the PPFG into their respective multiyear program planning
and project planning functions; update schedules and cost estimates,
evaluate options and alternatives and consider excursions from current
plans.
(2) Incorporate inputs from other elements into multiyear program and project
plans;
(3) Conduct appropriate internal processes to ensure that the best data is
available to develop an integrated, updated, executable program at all
levels specified in the PPFG, and provide information that meets the
requirements of the guidance for the programming phase (integration,
prioritization, and program review) instructions;
(4) Develop IPLs to include capital asset construction projects and supporting
documentation as called for in the PPFG; and
(5) Support CEPE and NA-MB by participating in the integration and
prioritization, and program review activities.
4. REFERENCES.
Executive Order 13450 Improving Government Program Performance.
5. DEFINITIONS.
NNSA Management Council: The NNSA Management Council is NNSA’s highest-level
forum for decisionmaking regarding strategy, policy, planning, practices, priorities, and
proposed initiatives. The Management Council also provides guidance on NNSA
program integration and dispute resolution. The Management Council is comprised of
Deputy Administrators, Associate Administrators, Field Office Managers, Chief of Staff,
Associate Principal Deputy Administrator, and General Counsel. The NNSA Chief
Scientist is an advisor to the Management Council. The Administrator chairs the
Management Council and the Principal Deputy Administrator serves as the Alternate
Chair. As needed, other NNSA senior officials may be called upon to participate in
Management Council activities as advisors. Further details can be found in BOP-00.01A,
Senior Leadership Councils.
6. CONTACT. Management and Budget (NA-MB), 202-586-0101 or Office of Cost
Estimating and Program Evaluation (CEPE), 202-586-6910.
THIS PAGE INTENTIONALLY LEFT BLANK
NAP-33 Appendix 2
1-17-17 AP2-1
APPENDIX 2: BUDGETING - FORMULATION PROCESS
Section 7
This appendix describes the procedures for developing the annual NNSA budget transmissions as
required by the Planning, Programming, Budgeting, and Evaluation (PPBE) process.
1. REQUIREMENTS. National Nuclear Security Administration (NNSA) participates in
the Department’s budget formulation process, which includes the Office of Management
and Budget (OMB) and Congressional budget review processes. Budget justifications
include the Future Years Nuclear Security Program (FYNSP) and performance data.
a. NNSA must prepare and transmit the OMB and President’s budget request to
Congress through the Department’s Chief Financial Officer (CFO) in accordance
with guidance and the OMB passback process.
b. Budget justifications and ancillary materials such as Construction Project
Datasheets and crosscutting exhibits, must be prepared for transmission to OMB
and Congress. Budget justifications provide the basis for the Congressional
review process, including testimony, questions and answers, markups, and
appeals.
c. Guidance is issued to NNSA elements to request information needed to develop
the OMB and President’s budget request.
d. NNSA participates in OMB reviews and the OMB passback process to determine
final funding decisions and policy guidance for the President’s budget request.
2. RESPONSIBILITIES.
a. Administrator:
(1) Provides formal NNSA funding decisions to develop the FYNSP and
statistical tables; and
(2) Approves NNSA’s budget request to DOE CFO for transmission to OMB
and Congress.
b. Associate Administrator for Management and Budget:
(1) Leads the overall budget formulation process and coordinates with the
DOE CFO;
(2) Develops and issues the NNSA budget guidance to support OMB and the
President’s budget requests;
(3) Develops budget justification materials specifying the funding and full
time equivalents (FTE) levels for the Federal Salaries and Expenses (FSE)
appropriation;
Appendix 2 NAP-33
AP2-2 1-17-17
(4) Reviews and integrates input from program offices including crosscut and
ancillary data to ensure the requests meet Departmental and OMB
guidance;
(5) Implements budget formulation policies and procedures, and provides
guidance and assistance to program staff in the development of budget
formulation materials, including coordinating Office of Declassification
final review;
(6) Produces final integrated NNSA budget documentation and maintains
NNSA statistical tables and databases that support budget justifications;
(7) Serves as NNSA’s liaison to DOE CFO and OMB on NNSA budget
deliverables; and
(8) Leads the Budget Validation process to determine consistency with NNSA
planning and program guidance documents, integration of planned
activities/milestones with budget estimates, and reasonableness of budget
estimates.
c. NNSA Elements:
(1) Provide budget formulation input in response to NNSA budget guidance;
(2) Ensure all estimates for construction projects are consistent with the top
end of the CD-1 cost range prior to being baselined, and that Construction
Project Data Sheets are reviewed by NNSA APM to ensure they are in
accordance with the NNSA Project Management BOP and have the most
recent and accurate information.
(3) Participate in the NNSA Budget Validation process as required;
(4) Coordinate with NNSA Management and Operating (M&O) partners;
(5) Create, review, and comment on final budget documents;
(6) Participate in the OMB budget briefings and passback process;
Section 8
(7) Respond to formulation findings, recommendations, and OMB and CFO
inquiries; and
(8) Brief Congressional authorization and appropriation committee and
subcommittee staff on budget requests.
REFERENCES.
a. OMB Circular A-11, Preparation, Submission, and Execution of the Budget, July
2016
NAP-33 Appendix 2
1-17-17 AP2-3
b. DOE O 413.3B, Program and Project Management for the Acquisition of Capital
Assets, dated 11-29-10
c. DOE O 520.1A, Chief Financial Officer Responsibilities, dated 11-21-06
5. DEFINITIONS.
Passback: Budgetary decisions of OMB Director that are passed back to the agencies.
6. CONTACT. Management and Budget, 202-586-1087.
THIS PAGE INTENTIONALLY LEFT BLANK
NAP-33 Appendix 3
1-17-17 AP3-1
APPENDIX 3: BUDGETING - EXECUTION PROCESS
The budget execution process will be added when NNSA has sufficient experience with the
Department’s new Funds Distribution System (FDS 2.0). NNSA’s final budget execution
process is also described and refined through the implementation process of Supplemental
Directive 412, Work Authorization.
THIS PAGE INTENTIONALLY LEFT BLANK
NAP-33 Appendix 4
1-17-17 AP4-1
APPENDIX 4: EVALUATION PROCESS
This appendix describes how the National Nuclear Security Administration (NNSA) implements
the annual planning, programming, budgeting, and evaluation (PPBE) Evaluation process.
1. REQUIREMENTS. NNSA articulates the unique contribution each performance
measure makes towards achieving the Department of Energy (DOE) mission by linking
them in a cascade to better focus resources on fulfilling the overall mission, as illustrated
in the diagram below.
a. Integrated Criteria. Each Government Performance and Results Act (GPRA)
program must have at least one performance measure, preferably an outcome
measure versus an output measure, that:
(1) Evaluates activities meaningful to achieve complex, long-term outcomes
focused on the health of the program;
(2) Is validated during the annual budget formulation process;
Appendix 4 NAP-33
AP4-2 1-17-17
(3) Uses terms that are concise and meaningful to the public; and
(4) Includes an annual endpoint target that measures progress over time
toward achieving the intended outcome.
b. NNSA annually issues guidance for updating performance measures.
c. Each GPRA program must strive for consistency in performance measures from
year to year to allow identification of multiyear performance trends to be used to
inform future resource decisions:
(1) Unless the GPRA program undergoes major changes or an update is
required to provide a more meaningful and accurate representation of
program performance, goals, and target text must remain unchanged.
(2) NNSA must provide proposed changes to performance indicators and
current year targets in a formal change request to the Office of the Chief
Financial Officer (OCFO) who will review the request and, upon approval,
transmit to OMB.
(3) Budgets must link to annual targets in order to assess the effects of
funding decisions.
d. Performance Reviews. The NNSA must validate results, evaluate planning
integrity, inform resource decisions, and hold managers accountable by
conducting credible, tiered, and linked performance reviews. Annually results are
reported to the Administrator in the NNSA Annual Performance Report (APR)
and are published alongside out-year targets in the DOE Annual Performance
Report. Internal and external performance reviews to be conducted on a recurring
basis include:
Section 9
(1) Agency Priority Goal Reviews. The GPRA Modernization Act of 2010
requires quarterly reviews of progress towards achievement of those
performance measures designated as APGs. Each quarter OCFO will
request a progress update and next steps for each APG. This information
is discussed with the Deputy Secretary during the quarterly data driven
review, approved by the Deputy Secretary, and subsequently provided to
OMB by OCFO for publication on Performance.gov. Goal Leaders and
Owners must respond to OMB questions on the information provided.
(2) Annual Program Reviews. NNSA leadership must review NNSA
programs at various times throughout the fiscal year to validate that
NNSA programs are on track to meet their long-term goals, annual targets,
as well as to alert management of potential issues that could impact
program success.
NAP-33 Appendix 4
1-17-17 AP4-3
(3) Program Manager Reviews. Program Managers must conduct detailed
reviews of program, project, and contractor performance annually, but
quarterly reviews are recommended, to validate progress on milestones
leading to achievement of annual targets. The format for these reviews is
the responsibility of the appropriate manager. However, this policy
requires NNSA program managers to document and maintain their
detailed review process and track findings until resolved. Programs must
document and use consistent and current internal control procedures to
describe the data, formulas, and detailed processes used to determine
results. This documentation is required to provide evidence to substantiate
the accuracy of reported results to auditors.
e. OMB and DOE Performance Reports.
(1) OMB requires NNSA provide an APR and APP in conjunction with the
Congressional Justification. This report is published on the DOE website
(http://energy.gov/cfo/reports/annual-performance-reports) detailing the
annual performance of each GPRA program and summarizing the results
of each performance measure reported in the President’s budget.
(2) DOE requires programs to provide quarterly and end-of-year results input
into the Performance Measures Manager (PMM) on the progress made
toward achieving annual targets. This data provides senior managers with
an early warning and corrective actions if an annual target is at risk.
2 RESPONSIBILITIES.
a. Administrator:
(1) Approves overall NNSA corporate performance measures; and
(2) Approves NNSA-related APGs prior to their transmittal to DOE for
Secretarial approval for transmission to OMB.
b. Associate Administrator for Management and Budget:
(1) Manages the overall PPBE Evaluation process;
(2) Coordinates and issues the annual Evaluation process-related guidance
documents;
(3) Maintains the integrated NNSA Performance Cascade;
(4) Assesses expenditures, full-time equivalents (FTE) usage and other
metrics for Federal Salaries and Expenses (FSE) components of all
organizational elements;
http://energy.gov/cfo/reports/annual-performance-reports
Appendix 4 NAP-33
AP4-4 1-17-17
(5) Maintains configuration control over the NNSA Corporate Performance
Measures and publishes them in the budget;
(6) Provides performance management feedback and advice to Headquarters
NNSA program elements;
(7) Reviews, consolidates, and transmits the NNSA quarterly PMM data to
DOE/OCFO; and
(8) Provides training to NNSA staff on the elements of the NNSA PPBE
Evaluation process.
c. NNSA Elements:
(1) Understand the requirements of the NNSA PPBE Evaluation process;
Section 10
(2) Generate products that fulfill NNSA PPBE Evaluation process
requirements (quality performance measures, credible Program Managers
Reviews, and timely and accurate PMM reporting); and
(3) Document and use consistent internal control procedures that provide
evidence to substantiate the accuracy of reported results to auditors.
3. REFERENCES.
a. Government Performances and Results Act (GPRA) of 1993
b. GPRA Modernization Act of 2010
c. Executive Order 13450 – Improving Government Program Performance
d. DOE G 120.1-5, Guidelines for Performance Measurement
4. DEFINITIONS.
a. Agency Priority Goals (APG): The Department establishes APGs that must be
updated every two years and represent the top priorities for the agency and the
current Administration and align with the Secretarial priorities. NNSA is
responsible for the APGs related to Nuclear Security. Current and past APGs are
published on the internet at the following URL: (https://www.performance.gov).
b. Performance Measures: Refers to external corporate performance data that
includes goals, indicators, endpoints, and annual targets. Performance measures
explain what a program expects to accomplish for a specified funding profile over
a specific period. This data links resources to performance objectives, informs
resource decisions, justifies budget requests, improves delivery of products and
services, and holds program managers accountable for results.
https://www.performance.gov/
NAP-33 Appendix 4
1-17-17 AP4-5
c. Indicators: An index or set of units to measure progress toward the goal.
Indicators should use common qualifiers (e.g., annual or cumulative) to clarify the
unit of measure.
d. Endpoint Targets: Long-term objectives that are critical steps toward achieving
the goal. Each goal should have three to five endpoint targets written in specific
measureable numerical units and must include the projected fiscal year that the
objective is to be completed. Endpoint targets may be completed before the goal
is reached.
e. Annual Targets: Specific and auditable outcomes and outputs toward achieving
the endpoint target measured in the same numerical units as the endpoint target.
Annual targets should be a specific numerical value, not a range, and must be
linked to and substantiated by technical milestones.
f. Milestones: Refers to key internal technical performance data that is required to
meet program criteria. Milestones are meaningful for subject matter experts to
oversee day-to-day operations aimed at achieving annual targets. Milestones are
in validated program baselines; one of three levels of detail below the annual
targets; and are contained in published program documentation. Agency Priority
Goals process requires quarterly milestones to be reported on the official United
States Government website: (https://www.performance.gov).
5. CONTACT. Management and Budget, 202-586-0101.
http://performance.gov/
Section 11
1. PURPOSE. Establish procedures to ensure that the planning, programming, budgeting, and financial activities of the National Nuclear Security Administration (NNSA) comply with sound financial and fiscal management principles.
2. CANCELLATIONS.
a. Business Operating Procedure (BOP)-001, Planning, Programming, Budgeting, and Evaluation (PPBE) Process, dated 11-8-11.
b. BOP-001.01, Application of PPBE Process for Activities Funded by the Office of the Administrator Appropriation, dated 11-8-11.
c. BOP-001.1, PPBE Planning Process, dated 11-8-11.
d. BOP-001.2, PPBE Programming Process, dated 11-8-11.
e. BOP-001.31, PPBE Budget Formulation Process, dated 11-8-11.
f. BOP-001.311, Budget Validation Process, dated 11-8-11.
g. BOP-001.331, Budget Execution Headquarters Approved Funding Program (HQ AFP) and Work Authorization (WA) Business Operation Policy, dated 2-15-08.
h. BOP-001.332, PPBE Reprogramming/Appropriation Transfer/Notification Process, dated 11-8-11.
i. BOP-001.333, NNSA Operations Under a Continuing Resolution, dated 2-15-08.
j. BOP-001.4, PPBE Evaluation Process, dated 10-05-12.
3. APPLICABILITY. Unless otherwise stated in the Appendixes, the applicability is the same for each appendix.
4. Summary of Changes. This NNSA Policy Letter (NAP) updates the planning process to reflect the current planning documents, including the Planning, Programming, and Fiscal Guidance (PPFG), removing references to legacy documents such as the NNSA Str...
5. BACKGROUND.
a. Section 3252 of the NNSA Act requires the Administrator to develop a planning, programming, and budgeting process that operates under sound financial and fiscal management principles. The NNSA Act also requires NNSA to annually provide to Congress...
(1) Planning. The purpose of the Planning phase of the PPBE process is to gather or update all the information, cost data, and options necessary to prepare to make resource decisions based on priorities during programming. It constitutes a preparati...
(a) NNSA periodically issues the NNSA Enterprise Strategic Vision that provides clear direction and reflects the Administrator’s goals and expectations for the NNSA. It cascades from the DOE Strategic Plan and establishes the Administrator’s short an...
(b) The PPFG updates the Administrator’s vision and priorities for the current PPBE cycle. It also identifies emerging issues that might challenge the NNSA baseline program and directs some potential excursions for further study and exploration durin...
(c) Program or project plans developed by NNSA’s program managers to provide a roadmap of work activities, metrics and milestones derived from the NNSA Strategic Vision.
(2) Programming. The purpose of the Programming phase of the PPBE process is to make decisions to align available program resources with priorities resulting in a balanced, integrated, executable NNSA FYNSP to be proposed to the Office of Management ...
The Programming process is guided by the PPFG:
(a) Each NNSA program element develops and provides programming deliverables required in the PPFG in accordance with their own internal processes for doing so;
(b) Then NNSA conducts activities at the NNSA level within major appropriations focused on integration and prioritization of the programs that make up each major appropriation. Actions during this phase include review of program materials, cost revie...
(c) The process then shifts to program review activities to develop options and proposals for balancing resources across NNSA and the major appropriations. This may include standing up of issue teams to examine items requiring leadership decisions. ...
(d) The Management Council adjudicates unresolved issues and makes recommendations for the overall NNSA program and resource allocations for the Administrator’s approval and transmittal to the Department.
(e) The last step in determining NNSA’s budget request to the Office of Management and Budget (OMB) is the Department’s Programming process. Here, DOE organizations brief the Secretary on their proposed budget and reprioritize as necessary. The Secr...
Section 12
(3) Budgeting. The Budgeting process includes development of the OMB and President’s budget requests, budget execution, and the budget validation processes.
(a) OMB budget justification materials, for the FYNSP, are developed articulating work scope and schedules commensurate with the funding request.
1 NNSA, as part of the Department’s budget request, transmits its budget requirements to OMB.
2 After a review of the budget materials and a series of briefings, OMB issues policy and resource decisions to guide the formulation of the President’s budget request back to the Department; this is also known as the passback.
3 The Department can choose to appeal these decisions, which may require additional integration meetings by the Management Council, the Administrator, and the Secretary. If the Department decides to appeal, documentation is sent to OMB identifying wh...
4 OMB issues the final settlement decisions which are binding and form the basis for the President’s budget request.
(b) The President’s budget request is developed and normally transmitted to Congress on or before the first Monday in February.
1 Justifying President’s budget requests requires that NNSA elements interact formally with Congress.
2 Congressional interactions include briefing, testifying, and responding to questions for the record.
(c) Budget execution is the process in which appropriated resources are distributed and controlled to achieve their approved purpose. The OMB apportionment process makes funds available to DOE for obligation and expenditure. DOE’s Base Table is the ...
(d) Budget validation is a process focused on determining consistency with NNSA planning and programing guidance, integration of planned activities and milestones with budget estimates, and reasonableness of budget estimates.
b. Evaluation. Evaluation is the process to assess progress made toward achieving identified performance measures at multiple levels within NNSA. These performance measures can either be low-level milestones for internal use, or high-level performan...
6. requirements. The identified organization must meet the requirements established in each appendix.
7. responsibilities. The defined responsible person must execute the responsibilities established in each appendix.
8. REFERENCES. References are listed in each appendix.
9. DEFINITIONS/ACRONYMS. Definitions and acronyms are listed in each appendix.
10. CONTACT. Associate Administrator for Management and Budget (NA-MB), 202-586-0101.
a. The PPBE planning and programming process consists of several major actions: guidance, integration and prioritization, and program review. NA-MB and CEPE direct the PPBE planning and programming process by leading or supporting each phase.
(a) CEPE will initiate the planning phase by developing the PPFG with support from NA-MB and coordination from all NNSA elements. The Administrator signs the PPFG.
(b) NA-MB will issue supplementary guidance regarding formats for programming materials (e.g., IPLs, supporting budget documentation). CEPE will issue supplementary guidance on issue teams and the program review calendar.
(a) NNSA elements develop IPLs and supporting programming materials to transmit to NA-MB and CEPE by the dates specified in the PPFG. Elements will also provide senior representation at the integration meetings and communicate work scope, risks, and ...
(b) NA-MB will lead the integration and prioritization actions through the collection of program deliverables, and will lead a series of integration meetings. These budget meetings will facilitate the integration of the NNSA portfolio and updated IPLs.
(c) CEPE will support programming through cost validation of budget estimates to ensure they are reasonable and executable.
(d) CEPE will lead program review; conduct analyses of the IPLs; and lead issue teams comprised of federal staff from the programs. Issue teams determine program options, offsets, programmatic and portfolio effects, and risks for adjudication by the ...
(e) CEPE and NA-MB will coordinate the communication of Management Council decisions to the Administrator for review and approval. CEPE will record final decisions in the APDM.
(a) Integrate and prioritize the IPL;
(b) Review the validation of the reasonableness of budget estimates; and
(c) Adjudicate program options, offsets, programmatic and portfolio effects and risks identified by the issue teams.
Section 13
b. Budget justifications and ancillary materials such as Construction Project Datasheets and crosscutting exhibits, must be prepared for transmission to OMB and Congress. Budget justifications provide the basis for the Congressional review process, i...
c. Guidance is issued to NNSA elements to request information needed to develop the OMB and President’s budget request.
d. NNSA participates in OMB reviews and the OMB passback process to determine final funding decisions and policy guidance for the President’s budget request.
Passback: Budgetary decisions of OMB Director that are passed back to the agencies.
a. Integrated Criteria. Each Government Performance and Results Act (GPRA) program must have at least one performance measure, preferably an outcome measure versus an output measure, that:
b. NNSA annually issues guidance for updating performance measures.
c. Each GPRA program must strive for consistency in performance measures from year to year to allow identification of multiyear performance trends to be used to inform future resource decisions:
d. Performance Reviews. The NNSA must validate results, evaluate planning integrity, inform resource decisions, and hold managers accountable by conducting credible, tiered, and linked performance reviews. Annually results are reported to the Admini...
e. OMB and DOE Performance Reports.
a. Administrator:
b. Associate Administrator for Management and Budget:
c. NNSA Elements:
a. Government Performances and Results Act (GPRA) of 1993
b. GPRA Modernization Act of 2010
c. Executive Order 13450 – Improving Government Program Performance
d. DOE G 120.1-5, Guidelines for Performance Measurement
a. Agency Priority Goals (APG): The Department establishes APGs that must be updated every two years and represent the top priorities for the agency and the current Administration and align with the Secretarial priorities. NNSA is responsible for th...
b. Performance Measures: Refers to external corporate performance data that includes goals, indicators, endpoints, and annual targets. Performance measures explain what a program expects to accomplish for a specified funding profile over a specific ...
c. Indicators: An index or set of units to measure progress toward the goal. Indicators should use common qualifiers (e.g., annual or cumulative) to clarify the unit of measure.
d. Endpoint Targets: Long-term objectives that are critical steps toward achieving the goal. Each goal should have three to five endpoint targets written in specific measureable numerical units and must include the projected fiscal year that the obj...
e. Annual Targets: Specific and auditable outcomes and outputs toward achieving the endpoint target measured in the same numerical units as the endpoint target. Annual targets should be a specific numerical value, not a range, and must be linked to ...
f. Milestones: Refers to key internal technical performance data that is required to meet program criteria. Milestones are meaningful for subject matter experts to oversee day-to-day operations aimed at achieving annual targets. Milestones are in v...